期刊名称:Lecture Notes in Engineering and Computer Science
印刷版ISSN:2078-0958
电子版ISSN:2078-0966
出版年度:2018
卷号:2233&2234
页码:848-853
出版社:Newswood and International Association of Engineers
摘要:Causes of failed roads and the reasons why most
roads stay consistently failed in some nations of the world, like
Nigeria, may be attributed to many factors, salient among
them may be corruption and recession ultimately. Corruption
in the award of road construction contracts make roads not to
be properly done, to meet set standards thereby failing almost
immediately they are completed. So, if corruption is minimized
in awarding road construction contracts, the number of failed
roads maybe minimized. This paper introduces some solution
methods to minimize corruption in road construction projects
so that good and sustainable roads are constructed even if
there is also recession. In our experiment, we formulated the
construction of real life 5km asphalt road as a hybrid resource
constrained project scheduling problem (HRCPSP). Using
priority based project scheduling technique, our results show
the number of skilled workers needed in each period which
gives the idea of the amount of fund needed in each of the
periods. We constructed two Gantt diagrams: when resources
are unconstrained and when resources are constrained to the
minimal demand of jobs in the eligible set in each period. The
unconstrained Gantt diagram helps to know the maximum
amount of fund that should be released to the engineers in each
period. This helps to curb corruption. The constrained Gantt
diagram helps to know the minimum amount that should be
released to the engineers for work to go on and the project to
get to completion stage even there is recession. This helps
project to be completed even if there is recession.