期刊名称:International Journal of Innovative Research in Science, Engineering and Technology
印刷版ISSN:2347-6710
电子版ISSN:2319-8753
出版年度:2018
卷号:7
期号:6
页码:7354-7360
DOI:10.15680/IJIRSET.2018.0706103
出版社:S&S Publications
摘要:Implementation of construction projects is often faced with problems during the project period, one of
which is the occurrence of a request to implement changes in the construction of a project called Change Order. Change
order occurs during the process of project construction work. Change order is also one of the main causes in using and
managing cost efficiency in construction. This research uses case study of high-rise building project in DKI Jakarta.
Instrument This research consists of among others 7 factors causing change order, 47 independent variables and 1
dependent variable. This research uses qualitative and quantitative methods with statistical study approaches processed
with SPSS (Stastistical Package for the Social Sciences) program. The required data is a high building construction
project in DKI Jakarta experiencing change order. The results of this study were obtained from the results of correlation
analysis, linear regression, model test, and R square test. The purpose of this research is to know the factors and
variable of change order risk in high building building in DKI Jakarta, to know the result of change order risk analysis
to project cost performance in construction process, to know the cause of modeling risk, and give recommendation of
the most effective improvement from result of risk analysis change order on high building project in DKI Jakarta.
关键词:Change Order; Cost Performance; Risk; High Rise Building;