期刊名称:International Journal of Innovative Research in Science, Engineering and Technology
印刷版ISSN:2347-6710
电子版ISSN:2319-8753
出版年度:2018
卷号:7
期号:5
页码:6234-6242
DOI:10.15680/IJIRSET.2018.0705213
出版社:S&S Publications
摘要:Delay in project schedule is a common issue in construction industry. Considerable percentage of
projects are falling behind the schedule causing damage to almost every involved party. In this thesis, schedule
crashing for compensating delay and reducing the duration of project have been studied. A framework is developed for
the process of crashing and quantitative risk evaluation. Framework consist of two parts, in first part linear
programming approach is used for the formulation of crashing problem and it is solved using excel solver. In second
part probabilistic Quantitative risk evaluation of schedule after crashing is done with the aid of @RISK7.5. An example
of crashing is solved using the developed framework which shows that the optimum crashed duration of an undertaken
project is 51 days at which the total project cost is minimum and it is also seen that the project duration can further
reduce to 49 days but at this duration total project cost is not minimum. After 49 days crashing is not possible. Then
quantitative risk evaluation is done and it is found that initial probability of project completion is more than that after
crashing which shows that after crashing the project we get desired completion date but the risk of completing project
on time is increased..
关键词:Crashing; Linear Programming; Risk Evaluation; Solver; Framework; Probabilistic;