摘要:A half-precast concrete slab system (HPCSS) is reported to exhibit excellent structural performance when compared with traditional slab systems. However, there is a lack of extant research examining the construction issues of an HPCSS. Thus, in this study, we analyze the construction process and productivity of applying an HPCSS by using a simulation method with the data collected from an actual construction case. The results indicate that (i) the construction productivity of HPCSS is 1.7 times that of a traditional slab system, (ii) the cost per productivity unit of HPCSS exceeds that of a traditional slab system, and (iii) critical resources affecting the HPCSS productivity include form crew and rebar crew. The results of this study suggest that it is possible to develop an optimal construction plan of a construction site in which an HPCSS is installed, and that the HPCSS can be actively applied in the future.
关键词:half-precast concrete slab system; construction productivity; construction simulation