Techno-economic evaluation of chromium recovery pilot plant installed at Kasur Tanneries Complex, Pakistan.
Khan, M. Rafiq
A techno-economic evaluation of the Chromium Recovery Pilot Plant
installed by KTWMA at Kasur Tanneries Complex was carried out. The data
were collected from KTWMA by paying visits to the office of the General
Manager, Tanneries Water Pre-treatment Plant at Kasur to obtain general
information and to have a view of the work-in-progress. The General
Manager and the Plant Supervisor were interviewed. Detailed information
was also supplied by the Plant Supervisor through a questionnaire
provided to him. Subsequently, the data were analysed to determine the
B/C Ratio, NPV, and Payback Period of the Project. The analysis led to
the B/C Ratio of 0.5, negative NPV of Rs 14,650,011, and payback period
36. These indicators are far below the decision criteria. Thus. the
installation is not viable financially or economically. The study, of
course, recommends that the installation, being a social and legal
obligation, is socio-economically justified even if the tanner has to
invest the capital required from his own resources.
JEL classification: Q56
Keywords: Chromium, Recovery, Kasur, Pakistan
1. INTRODUCTION
Chromium metal is widely used as a tanning agent worldwide. The
process called chrome-tanning is accomplished in three steps: Pickling,
Tanning and Basificationl (Pakistan Tanners Association) Chromium
sulfate is the most widely used chemical in this process. Approximately,
60-70 percent of chromium sulfate applied is taken up by the hides and
skins, while its 30 to 40 percent remains un-used and is discharged as a
component of wastewater into natural water bodies such as rivers,
streams, etc., which has adverse environmental impacts on living
organisms particularly to humans and animals [Weitz and Luxenberg
(n.d.)], and water animals such as fish [Eisler (1986)]. The diseases
especially encountered in humans, are of nervous disorders. The
pollution from tanneries effluent particularly their chromium component
has formed the basis that many developed countries have banned tanning
on their soils. Chrome tanned leather, being the need of people all over
the world, has the edge that its manufacture cannot be stopped. This has
given some economic advantage to some developing countries including
Pakistan to manufacture leather and export it to the developed
countries. To sustain, different methods have been developed to recover
chromium from the tannery effluents before their drainage in the natural
water bodies. A few examples of these methods are High Chrome
Exhaustion, Direct Recycling of the Spent Tanning Float and Chrome
Recovery and Reuse [Arrafay Labs (2003)].
The tanneries of Punjab, the largest province of Pakistan are
mostly located in five major clusters: Sialkot, Lahore, Multan,
Gujranwala and Kasur. These are being provided environmental services
under "Introduction of Cleaner Technologies Programme--(ICTP) in
Tannery Clusters of Punjab since December 1997 as joint ventures between
different tanners associations of Pakistan and different national and
international organisations for upgrading environmental conditions in
and around the tanneries. Under these ventures different pollution
abatement measures have been suggested and implemented in complexes and
some also in individual tanneries. An important example of the measures
suggested at the complex level is the Common Effluent Pre-treatment
Plant installed at Kasur. Majority of the suggested measures at the
individual tannery level are based on the principle of waste
minimisation at source. Among the Cleaner Production
Options/Technologies, one is Chrome Recovery. It can be accomplished as
narrated above.
Chrome recovery and reuse process, besides the elimination of
environmental concerns related to chrome, has also economic benefits to
the tanners as the chromium discharged as effluent component as claimed
by Pakistan Tanners Association, can be 100 percent recovered. The
recovery cost has been reported to be about 30 percent of the fresh
chromium cost. The pay back period for the recovery of investment in the
system applied has been reported as one year. It has been also claimed
that the quality of chromium recovered and that of the leather prepared
with its use meet the desired quality standards.
2. MATERIALS AND METHODS
The research methodology involved two major stages: Collection of
Data and Data Analysis. These are described below.
2.1. Collection of Data
The primary information about KTWMA and Kasur Tanneries Pollution
Control Project was gathered from a report published by KTWMA for
general information about Kasur Tanneries Pollution Control Project
(KTWMA) and from "Proceedings of the International Conference on
Pollution in Tanning Industry of Pakistan", held at Lahore on June
11 to 13 [KTWMA (2002)]. These two publications were extremely helpful
in getting the information about the general situation of tanning
industry in Pakistan, technology of effluent treatment to meet the
requisite standards, methods and technology involved in chromium
recovery, general benefits of the Kasur treatment plants, etc.
Next step was the organised visits to Kasur to see the main
pretreatment plant recently installed by the cooperation of provincial,
national and international governments, organisations and agencies to
see the work-in-progress and to dig out information through interviews
with the General Manager KTWMA and other concerned officials and to get
detailed information about the Chromium Recovery Pilot Plant. The plant
was visited, while it was in operation. All the sub-processes involved
and the sub-process equipment were carefully viewed. A flow sheet
diagram was, subsequently, constructed. The GM told us that it is an
Italian Plant exactly the one, currently, in operation in Florence. The
information about price of the machinery and equipment, cost of land and
building, cost of labour and other inputs was provided by the Plant
Supervisor by filling the questionnaire sent to them well before the
dates of visits.
2.2. Data Analysis
The data were analysed by the standard techniques of project
analysis [ADB (2001, 2003)]. Both expenditure and returns were projected
over ten years that is the project life and discounted to the Base Year
(1999-2000) at 10 percent discount rate as the plant started functioning
in December 2000. From the discounted amounts, B/C Ratio and NPV of the
Project were calculated, which were compared with the criteria for
decision-making. The evaluation was also done by Payback Period Method
to compare our results with the results reported by some workers who
have carried out some studies in Pakistan.
2.3. Cost Analysis
The project evaluation was based on the following assumptions:
Project Life: 10 Years
Base-Year: 1999 (1999-2000)
Evaluation Year: 2004
Average Discount Rate in Pakistan: 10 percent
Starting and Closing of Financial Year: July 1 to June 30
Scrap Value of Machinery and Equipment: 10 percent of Suppliers
Price.
2.3.1. Initial Fixed Investment
2.3.1.1. Land
Total Area = 2,500 Sq, ft (11 Marlas)
Constructed Area = 1,500 Sq ft
Open Space = 1,000 Sq ft
Cost of Land per Marla = Rs 45,000
Cost of Land = Rs 495,000
2.3.1.2. Building
Cost of Construction per Sq ft = Rs 700 per Sq ft
Cost of Construction =Rs 1,050,000
Cost of Construction of Drainage System for Feeding into Recovery
Plant and
Disposal of Treated Effluent = Rs 10,000
Original Estimated Cost of Electrical Works = Rs 116,800
Total = Rs (1,050,000 +10,000 +116,000) = Rs 1,176,800
2.3.1.3. Machinery and Equipment
The details of plant machinery and electrical equipment are given
below.
Cost of Plant Machinery, Equipment and Electrical Rs 4,000,000
Works (Table 1)
Site Visits for Civil Works by Contractors Rs 150,000
Sales Tax Rs 747,000
Laboratory Equipment Rs 100,000
Total Rs 4,997,000
2.3.1.4. Vehicles: Two Motor Cycles Rs 150,000
2.3.1.5. Generators Rs 400,000
2.3.1.6. Pre-production Expenditure
Project Supervisor Rs 200,000
Assisting Staff Rs 100,000
Consultants Rs 500,000
Chemicals and Other Expenditure
Before
Commissioning the Plant (Five
Trial Batches) Rs 46,900
Total Rs 846,900
Total Initial Fixed Investment = Rs (495,000 +1,176, 8 00 +
4,997,000 + Rs150, 000 + Rs 400,000 +Rs 846,900) = Rs 8.065,700
2.3.2. Operating Cost
The operating cost components and their costs are given below.
2.3.2.1. Raw Material Cost: The raw material is the effluent that
is to be disposed off. Thus, there is no cost of the raw material.
2.3.2.2. Cost of Other Inputs
Chemicals = Rs 1325 per Batch
Water = Rs 1100 per Batch.
Fuel for Generators, etc. = Rs 300 per Batch
Cost of Electric Power/Batch = Rs 60
Cost of Other Inputs per Batch =Rs 2785
Cost of Other Inputs per Annum = Rs 2785 X 240 = Rs 668,400
Cost of Filter Cloth, etc. = Rs 30,000
Total Cost per Annum = Rs (668,400 +30,000) = Rs 698,400
2.3.2.3. Total Labour Cost per Annum = Rs 69, 000 x12 = Rs 828,000
(Table 2)
2.3.2.4. Maintenance Cost at 10 percent of Sale Price of Supplier
Plant Machinery and Lab Equipment Rs 410,000
Generators Rs 40,000
Vehicles Rs 15,000
Total Maintenance Cost Rs 465,000
2.3.2.5. Cost of Laboratory Reagents per.
Annum Rs 100,000
2.3.2.6. Depreciation at the Rate of 10 percent of Purchase
Price (Plant Machinery and Equipment + Lab
Equipment +Vehicles + Generators) Rs 554,700
Total Operating Cost per Annum =
Rs (698,400 + 828,000 + 465,000+ 100,000 + 554,700) = Rs 2,646,100
2.3.2.7. Expenditure in the Base Year
Initial fixed Investment = Rs 8,065,700
Operating Cost = Nil
2.3.2.8. Expenditure in Future Years
In future, no investment in terms of machinery and equipment will
be involved. Operating cost as in the first year of operation
(2000-2001) will be there in all the years. It may change with the
change in salaries of the employees and change in the prices of other
inputs such as utilities and requisites for maintenance. If it is
assumed that the salaries of labour undergo an increase of 15 percent
after every three years and prices of utilities and other requisites for
maintenance undergo an increase in cost by 10 percent every year. The
operating cost was calculated as below.
Operating Cost = Cost of (Labour +Utilities and Chemicals +
Maintenance + Laboratory Reagents + Depreciation): The picture is
presented in Table 3.
2.3.3. Benefits
The benefits were calculated on the basis of the following data:
Volume of Effluent Processed per Batch = 10,000 [M.sup.3]
Volume of Effluent Processed per Annum = 10,000 [M.sup.3] * 240 =
2.400,000 [M.sup.3]
Amount of Chromium Recovered per Batch = 150 Kg
Cost of Chromium Recovered per Kg = Rs 25
Cost of Chromium Recovered per Batch = Rs 3,750
Cost of Chromium Recovery per Batch = Rs 2,425 (Only chemicals and
consumables considered)
Revenue Return per Batch =Rs 3,750 - Rs 2,425 = Rs 1,325
Revenue Earned per Batch if Only Chemicals and Consumables are
Taken into
Account = Rs 1,325*240 = Rs 318,000
2.3.3.1. Revenue Return per Annum = Rs 3,750 X 240 (Batches) =Rs
900,000
Pollution Charge per [M.sup.3] Received in the Form of Water Bills
= Rs 4
Pollution Charges Received by KTWMA in the Form of Water Bills = Rs
2.400,000 x 4 = 9,600,000
There are overall seven parameters that are controlled by KTWMA by
overall pretreatment. If it is assumed that the charges received for
Chromium per annum are one seventh of the total charges received, the
benefit in this context may be as given below. These have been assumed
not to change in future and thus will be in the form of constant annual
cash flows.
2.3.3.2. Revenue Received by KTWMA vs. Chromium Recovery = Rs
9,600,000/7 = Rs 1,371,429
Total Benefits in 2000-2001 = Rs (900,000 + 1,371,429) = Rs
2,271,429
Scrap Value of the Machinery and Equipment = Rs 554,700
2.3.4. Total Expenditure and Total Returns Discounted to the Base
Year
2.3.4.1. Present Value of Expenditure
The calculations of present values of expenditure and returns are
done by applying the relationship:
Expenditure: Initial Fixed Investment +Operating Cost Present Value
of Operating Cost = Rs 20,754,726 (Table 4)
Present Value of Cash Outlays (Cost) = Rs (20,754,726 + 8,065,700)
= Rs 28,820,426
2.3.4.2. Present Value of Revenue Returns
Present Value of Returns = Rs 13,956,954
Present Value of Scrap = Rs 554,700*0.385543=Rs 213,861
Present Value of Cash Flows (Benefits) =Rs (13,956,954 + 213,861) =
Rs 14,170,815
Benefit / Cost (B/C) Ratio = Present Value of Benefits / Present
Value Cost = 14,170,815 / 28,820,426 = 0.5 (After rounding off)
Net Present Value = Rs (-28,820,826 + 14,170,815) = -Rs 14,650,011
2.3.4.3. Costing by the Application of Payback Period Method (PBP)
The data requisite for computation of PBP is as follows:
Initial fixed investment = Rs 8.066,000
Cost of Land and Building = 1,545,000
Initial price of Machinery, Equipment and Generators = Initial
Fixed Investment--Cost of Land and Building = 8,066,000-1,545,000 = Rs
5,547,000.
Cost of land and building was not considered towards total
investment as in our environment, these components fall into permanent
assets of entrepreneur which rather appreciate with passage of time.
Annual Return = Total Benefits/Annum-Operating Cost/Annum-Scrap
Value of Machinery and Equipment or
Annual Return = Rs (2,271,429-2,646,100-554,000) = Rs 180.029
The PBP was calculated by applying the following formula:
Payback Period = Total Investment / Annual Return = 6,521,000 / 1
80,029 = 36 (Rounded figure)
Thus, the Payback Period will be 36 Years.
3. RESULTS AND DISCUSSION
The results are presented in two parts. The first part is purely
descriptive research that presents our observations on the setup,
technology, and functioning of the plant and the second presents the
results of the data processed above.
3.1. Chromium Recovery Plant at Kasur
The Chromium Recovery Plant installed at Kasur is a pilot plant
installed on experimental basis. It is in operation since December 2000
and is equipped with the capacity of processing 20[M.sup.3] of the
effluent per day. This has been a successful experience as it caters the
need of 35 to 40 small tanneries. The chromium recovery is claimed as 99
percent and the cost of recovered chromium is 50 percent of the
prevailing market price of basic chromium sulfate. The tanners of
Pakistan have been motivated by installation of this plant and are
planning to install such plants in the individual tanneries.
3.1.1. Principle and Processes
The Chromium Recovery Method is based on the principle that the
chromium is present in the effluent in its trivalent form, and thus is
generally insoluble at a pH of 8 to 12. It reacts with an alkali such as
Ca O, Mg O, etc., and precipitates as chromium hydroxide [Cr
[(OH).sub.3]]. The precipitate, after separation by filtration yields
chrome sludge that when treated with sulfuric acid, forms soluble chromium sulfate, which can be reused after alkalification, as it is
turned again into basic chromium sulfate.
3.1.2. Operations and Sub-processes
The operations and sub-processes involved in the Process of
Chromium Recovery are self-explanatory as shown in Fig. 1.
[FIGURE 1 OMITTED]
3.2. Benefit-Cost Ratio and NPV
Benefit to Cost Ratio is one of the important criteria for grading
a project as non-profitable, profitable or socially acceptable. The
decision rule is that if it is more than 1, the project is profitable
and thus acceptable depending upon the expectation of the amount of
profit by the investor. If it is less than one, it is non-profitable and
thus not acceptable if it does not fall in the category of social
obligations. In general, one can say that all such projects meant to
produce salable goods for competing in a specific market must be
rejected if the B/C ratio is less than1.
Let us see the situation in the light of the other criterion that
is Net Present Value or NPV of the Project. The decision rule is that
the project is acceptable if NPV is positive depending upon how much is
the expectation of the entrepreneur. If it is negative, then project is
rejected provided it does not fall in the category of social
obligations. Usually, the projects meant to produce products for sale
for competing in the market are straight away rejected if the NPV is
negative. Of course, these may be considered for acceptance if their
social cost is high and that is in terms of general social benefits such
as cleanliness of environment, response to a community need if no other
appropriate source is available, creation of employment opportunities,
etc.
The cost analysis has led us to the B/C Ratio 0.5 and a negative
NPV of Rs 14, 170,815. Both indices are far below the criteria for
decision to accept the project. We see here that both indices deviate
from the required values, roughly, by 50 percent. Thus, it may be
clearly concluded that the installation is neither financially nor
economically viable.
As the project falls in the social obligations of the tanners as
they are required to process the effluent for elimination of chromium to
meet the NEQS standards, they have to do it, even if, they have to make
investment without expectation of any return. Thus, the study advises
them to invest from their own resources without the expectation of any
financial benefits.
We have not yet come across any study carried out on chromium
recovery in Pakistan by the application of the Technique of Discounted
Cash Flow. Thus, we cannot compare our results with any one with this
reference.
3.3. Payback Period Results
The results of some studies have recently appeared either on
internet or on the brochures of the suppliers of the chrome recovery
plant machinery. These studies claim the payback period, five months to
one year. That means that the initial investment is recoverable in less
than a year. Thus it was considered to carry out cost analysis by
Payback Period Method also.
Our calculation of payback period has led to alarming results. What
to think of payback less than one year, here the payback is 36 years if
the calculations are done without taking into consideration the
fluctuating scrap values of plant and equipment. Why there is such an
abnormal difference? Our observations and indications are as discussed
below.
(1) Some workers have calculated the benefits of chrome recovery
without consideration of all the cost elements. Some, unfortunately,
have just matched the cost of chromium recovered with the cost of
chemicals and other consumables used. They have not considered the costs
of land, building, plant itself and labour that go into millions (Here,
more the Rs 7 million).
(2) As told by the General Manager KTWMA Project, the chromium
recovery plant installed at Kasur is a pilot plant that was imported
from Italy. It is exactly the same as one currently operating in
Florence, Italy. Its cost is very high (Rs 4 million). This study
indicates that its cost is the major factor in rendering recovery of
initial fixed investment difficult. Pakistan Tanners Association, of
course, has advertised in a brochure, titled "Chrome Recovery and
Reuse" that presents some plants with capital costs varying from Rs
0.4 to 2.0 million depending on the size of production per day by the
individual tanneries and nature of the skins and hides to be tanned. As
the plant under study caters the needs of 30 to 40 tanneries, its
equivalent can be a bigger plant. Those bearing price below Rs 1 million
don't make the sense in context of the choice. If we choose midway
between one to two million, say 1.5 million as the capital cost by
changing machinery suppliers, still with this reduction in the capital
cost, a payback of one year cannot be thought of.
(3) The plant under study, in spite of being under the control of
KTWMA, is installed almost independently at a separate site in its own
building. Its initial fixed investment also includes the cost of land
and building (about Rs 1.6 million). It is also one of the important
factors that contribute towards irrecoverable increase in the initial
fixed investment. If such a plant is installed as a part of the tannery
on one to one basis, it is possible that there may not be an investment
on purchase of land and construction of building.
(4) Apart from above factors, another important factor is the
labour that can be either shared between the main set up and the
auxiliary set up or may be deputed from the former to the latter. For
example, Supervisor of the main laboratory can look after the mini-lab
of the chrome recovery plant. Similarly, the surplus unskilled labour
and the semi-skilled labour, if available, can be deployed in the
recovery plant on temporary or permanent basis. Thus the labour cost may
be, significantly, reduced by integrating the recovery plant with main
set up. There is the likelihood that the claimants of one year payback
may be talking about such like integrated set ups. The Plant Supervisor
at Kasur also hinted us about the lower cost of these set ups.
(5) Another important factor is the nature of technology and its
choice. There are different options for making appropriate choices. The
most general choice is the "Core Technology" purchased either
on 'turn key' basis or installed through a contactor on
commissioning basis. An alternative choice is "Synthetic
Technology" that involves the break up of the core process into the
sub-processes and purchase of machinery at sub-process level from local
or foreign market and its installation by the local experts, by foreign
experts or by local and foreign experts as a team. The substitution of
imported components by the local components may reduce the cost of
machinery dramatically.
(6) Finally, the plant installed at Kasur, is running on single
shift basis. Thus, it is operating far below its capacity. If it is run
on double shift basis, other cost factors being the same, the annual
cash flow may be double as a result of which, the payback may be halved (18 instead of 36). Similarly, if it operates on three shit basis, the
payback may reduce to one third (12). The question, here, will be
whether there is so much effluent to cater the plant on two or three
shift basis or not?
In the light of the results presented and discussed above, it may
be concluded without any doubt that the Chromium Recovery Plant
installed by KTWMA is not viable both financially and economically. Its
installation, being a social and legal requirement, it is
socio-economically justified even if it involves the tanner's own
investment. To make it financially and economically viable, this piece
of work should be extended to search the ways to bring its installation
and operating costs down as narrated under the recommendations.
To extend the work reported in this study, we propose the following
research projects to be carried out to make the installation both
financially and economically viable:
* Down-costing of installation of chromium recovery plants in the
developing countries with special reference to Pakistan.
* Choice of technique in installation of chromium recovery plants
in the developing countries with special reference to Pakistan.
* Social analysis of the plants to assess its benefits in terms of
reductions in mortality and morbidity and labour days lost. The results
of social analysis may significantly pull the installation towards
economic viability by increasing BCR and NPV.
It is appreciated that some critics pointed out that the social
link is missing. The social analysis is one of the important aspects and
its conduct has been recommended above. The problem is that focus all
over the world mostly is on assessing the benefits of elimination of air
pollutants from the atmosphere. The author has successfully applied
World Bank Model for assessment of the benefits of banning two-stroke
rickshaws in Lahore, currently in process for publication in The
Pakistan Development Review. Unfortunately, no standardised method of
assessment of disposal of liquid effluents and solid waste has been
encountered yet. The only way to monetise it to identify the diseases,
quantification how much effluent or solid waste will cause how many
cases of morbidity and mortality and finally monetisation by calculating
cost of recovery from the diseases and deaths. This is a difficult local
exercise which is very difficult to carry out. Even this methodology may
be applied to monetise the social costs of Kasur Tannery Waste Water
Pre-treatment Plant, yet monetisation of the benefits of chromium
recovery plant will not be possible because, it forms a part of overall
activity. Moreover, chromium is partly recovered and partly disposed of
in the pre-treatment plant. Thus checking of hospital records will
further confuse the situation. The only thing that sounds helpful is the
monetisation on the basis of amount of chromium recovered per annum. The
assumption will be that if it was not recovered and remained in tannery
waste then how many deaths it would have caused and how many cases of
morbidity will be there. This may be accomplished by using dose response
curves as templates if some studies on liquid effluents and solid waste
have been carried out in advanced countries like USA, UK, Canada, etc.
If not, the researchers with this aim will have no other alternative
except to wait. The investigator of the work being reported is also
after it to cover this dimension at a later stage.
Lack of social analysis does not mean that this study based on
financial analysis loses anything in value. It carries significantly
high value on the basis of reasons given below:
* The industrialist evaluates his projects on profit and loss basis
by application of financial analysis. He is carefree about the social
aspects. Had he been so conscious, he would have not polluted the
environment to the state encountered today.
* There are a number of dimensions that may be enquired as
highlighted while concluding results and discussion by applying
financial analysis techniques and author's group has gone far in
this enquiry. The results are expected to conclude with BCR many-fold of
1, the standard criterion and payback period and with miraculous reduction in the payback period. This evidence when brought to light
will be sufficient to convince the tanners to install chromium recovery
plants in their tanneries for disposal of chromium free waste water in
environment.
REFERENCES
Arrafay Labs (2003) Chrome Recovery and Reuse--A Synoptic Review.
www.ictp.com.pk/aboutus.htm
Asian Development Bank (2001) Guidelines for the Financial
Governance and Management of Investment Projects.
<www.adb.org/Documents/Guidelines/ Fin_Analysis?p=ecopubs>
Asian Development Bank (2003) Guidelines for the Economic Analysis
of Projects. <www.adb.org/Documents/Guidelines/Eco_Analysis>
Eisler, R. (1986) Chromium Hazards to Fish, Wildlife, and
Invertebrates. Biological Report 85:1.6. (Contaminant Hazard Reviews
Report No. 6.) Patuxent Wildlife Research Centre U.S. Fish and Wildlife
Service Laurel, MD 20708.
KTWMA (n.d.) Report on "Kasur Tanneries Pollution Control
Project" under UNDP. Published and available with KTWMA, Kasur,
Pakistan
KTWMA and UNDP (2002) Kasur Tanneries Pollution Control
Project--Proceedings of the International Conference on Pollution
Control in Tanning Industry of Pakistan. Naeem Javed and Zaigham Abbas
(editors).
Pakistan Tanners Association (n.d.) Introduction to Cleaner
Technologies Programme. www.ictp.com.pk/ptaNZ.htm
Weitz and P. C. Luxenberg (n.d.) Chromium Toxicity Summary.
<http://www.weitzlux.com/chromiumtoxicity_3741.html>
M. Rafiq Khan <
[email protected]> is affiliated with the
Lahore School of Economics, Lahore.
Table 1
Original Estimated Cost of Electrical Works--Rupees
Qty Unit Price Amount
S.N. Item Description (No) (Rs) (Rs)
1 TFM Breaker and Board 1 1,500 1,500
2 Breakers (Toshiba 4-6.3A) 16 350 5,600
3 Magnetic Switches(LG)-5.5 Kw 12 1,500 18,000
4 Main Board-Z.T Panel 1 3,000 3,000
5 Electric Motor-2HP 8 3,900 31,200
6 Electric Motor 2HP 2 2,500 5,000
7 Electric Motor 1/2 HP 2 1,500 3,000
8 Water Pump 1 4,500 4,500
9 Tube Lights and Other Items 25 Different Rate 45.000
Total 116,800
Table 2
Labour Cost per Month
Number (No.) Per Month (Rupees)
Plant Supervisor 1 20,000
Operators 2 28,000
Laboratory Assistant 1 8,000
Semi-skilled Labourer 1 5,000
Unskilled Labourer 1 4,000
Laboratory Attendant 1 4,000
Labour Cost per Month Rs 69,000
Table 3
Operating Cost in Future Years
Operating Cost = Cost of (Labour + Utilities and Chemicals +
Maintenance + Laboratory Reagents + Depreciation):
2000-2001: Rs (828,000 + 698,400 + 465,000+ 100,000 + 554,700) = Rs
2,646,100 Or Cost of (Labour + Depreciation + Utilities and Others)
Utilities Operating
Labour Depreciation and Others Cost
2000-2001 828,000 554,700 1,263,400 2,646,100
2001-2002 828,000 554,700 1,389,740 2,772,440
2002-2003 952,200 554,700 1,528,714 2,911,414
2003-2004 952,200 554,700 1,681,585 3,188,485
2004-2005 952,200 554,700 1,849,744 3,356,644
2005-2006 1,095,030 554,700 2,034,718 3,541,618
2006-2007 1,095,030 554,700 2,238,190 3,887,920
2007-2008 1,095,030 554,700 2,462,009 4,111,739
2008-2009 1,095,030 554,700 2,708;210 4,357,940
2009-2010 1,259,285 554,700 2,979,031 4,793,016
Table 4
Present Value of Expenditures Discounted Top the Base Year
Initial Fixed Investment = Rs 8,066,100 Operating Cost-Year
1999-2000 = Nil
Future Costs Discount Factor PV
2000-2001 2,646,100 0.909091 2,405,546
2001-2002 2,772,440 0.826446 2,291,272
2002-2003 2,911,414 0.751315 2,187,389
2003-2004 3,188,485 0.683013 2,177,777
2004-2005 3,356,644 0.620921 2,084,211
2005-2006 3,541,618 0.564474 1,999,151
2006-2007 3,887,920 0.513158 1,995,117
2007-2008 4,111,739 0.466507 1,918,155
2008-2009 4,357,940 0.466507 1,848,194
2009-2010 4,793,016 0.385543 1,847,914
Total Rs 20,754,726