Development of a suitable manufacturing system for developing country.
Park, Hong Seok ; Mun, Si Hwan ; Choi, Hung Won 等
1. INTRODUCTION
Recently, the latest automobile industry has unfavorable conditions
of cost and customers' demand. To survive in global market
environment with such conditions, opening up new markets is very
important for manufacturers. Therefore, fufillment of quality and cost
competition are very important factors to obtain competition in a new
market opened up. Automobile enterprises are trending to transfer
technologies to developing countries due to lower cost. There are not
same conditions in different countries. So, it is difficult to expect
the same goals of productivity and economical efficiency in different
countries.
To develop the optimum manufacturing system under any production
conditions, various studies are carried out. Specially, studies that
search problem of current manufacturing systems and develop new
manufacturing systems using 3D virtual simulation of Digital
Manufacturing technique are becoming salient issues recently.
Jayaraman and Agarwal (1996) introduced the method that designs
factory of automobile engine for processing and assembly efficiently.
The method simulates main parts processing system (Micro Level
Simulation), then it simulates whole engine factory (Macro Level
Simulation).
Jayaraman and Gunal (1997) used simulating problem solution method
for buffer operation between special quality and process of engine
assembly line when designing automobile engine assembly process and Park
et al. (2002) presented operation strategy using virtual automobile body
shop. The operation strategy prevented expected problem beforehand
analyzing material flow before building a factory.
However, creating alternatives to use a heuristic algorithm is
still on study until now. This algorithm has problems that a lot of time
and expenses are invested and improvements appear only in some parts of
system, not the whole.
To solve this problem in this paper, Transmission gear processing
factory builds in overseas to construct optimal Transmission gear
processing factory in early time without consumption of needless capital
and time is developed logically. Moreover, we also used Thinking Process
of TOC (Theory of constrains), 3D Simulation of digital Manufacturing
methodology to achieve our goals.
2. CURRENT PROCESS ANALYSIS
In order to have most suitable model of automobile transmission
manufacturing systems in developing countries we should analyze the
current manufacturing system first. We analyze the products whose the
same (or similar) material flows processes and analyze the same
operations. However, processing time of the same operations is different
due to the difference in the dimensions and the shape of the products.
The specifications of each gear processing line to produce other
items are 2 kinds. This is according to the schedule for each machine
tool. In addition, the processing gear up for the process, because most
of the cutting process perform an operation based on the life cycle of
Tool and Tool must be changed. The cycle of changing machine tool for
each process will be applied differently. In addition, each of the
standards process to determine the actions that were in process, the
flow of logistics, equipment and tools with the distance,
loading/unloading of stock, the worker can bring in and sequence of the
overall process. Based on sequence of a defined process and the cycle
time, work, latency, machine broken rate, waste, and 4M (Material,
Machine, Man, and Method) analysis of the process and time is defined as
constraints. That is the basis for 3D virtual simulation.
[FIGURE 1 OMITTED]
3. DEVELOPMENT STRATEGY AND METHODOLOGY
There would be many problems when we apply the current
manufacturing system to developing countries, by using
Effect-Cause-Effect analysis we pointed out all the problems and solved
them with methodology of Thinking Process, which is one of the methods
of TOC (The theory of constraints) and its tool -Logical Tree. With
Logical Tree, we could find out the objective and logical optimum
solution.
The first phase of Logical Tree was used to define all the problems
when applying the current system to developing countries. The problems
were called UDE (Undesirable Effect). UDE defined based on the core
problem of manufacturing system was solved to find out the developing
countries' unreasonable manufacturing system. Next, CRT (Current
Reality Tree) was also used to point out the causal relationship in the
UDE.
EC (Evaporation Cloud) resolve core problem in order to find out
the antagonistic relationship between alternatives so that we could have
the most appropriate solution. And we decided to change the automation
level of production system according to the analysis of product volume.
To take full use of manpower, the automatic conveyor must be removed and
then the system used worker to put items in the machines and take them
out from the machines. Moreover, transporting items from one station to
the other was also done by manpower. Such a system was called Manual
one. On the contrary, in Automatic system, all the above works were done
by automatic machines. Both of Manual system and Automatic one are not
suitable for developing countries and our task was to determine the most
appropriate automation level for the new system.
The new system is not neither Manual system nor Automatic one; it
could be called semi-automatic system. In this system, the Loading /
Unloading items processes were done by automatic machines, otherwise the
Transporting items processed were done by workers. A batch of items for
each time of transportation had 10 items. In semi-automatic system,
however, the production capacity is only 65.1 UPH, which is lower than
the production requirement- UPH 67. Due to the using more workers in all
processes, especially in moving parts from one station to the other, the
total processing time increased. That resulted the UPH of the
semi-automatic system did not fulfill the requirement of 67 UPH.
Otherwise, Automatic and Manual systems also had low machine
utilization in Deburring processes. And this problem still existed in
the semi-automatic system. Semi-automatic system, however, had an
advantage that the automatic did not have. In automatic system, if one
station had to stop for any reason, all the other had to stop also. In a
working day, the average stop time in the entire line is 1 hour and 30
minute, but in the semi-automatic system, it was only 11 minutes.
Additionally, blocking situation took 1 hour and 20 minutes per day on
average, but it was 0 in the semi-automatic. With Evaporating Cloud diagram we had found out the solution, Semi-automatic system, but it was
not the optimum one.
4. MANUFACTURING SYSTEMS DEVELOPMENT FOR DEVELOPING COUNTRIES
So, we changed to another tool to find the optimum solution, it
were Logical tree of Future Reality in Thinking process.
In Semi-automatic system, blocking situation maintained a low rate
of machine utilization in Deburring process. After analyzing Deburring
station ability, we decided to eliminate some machines in Deburring
process. Because the processing time of Deburring process is lower than
all the others, there were up to 2 hours of idle time on Deburring
process per day. As said in the above, we had to eliminate some machines
in Deburring process in order to increase the machine utilization. Then,
we had to determine how many machines to be eliminated exactly.
After eliminating one machine at Deburring process, one item would
be processed on 2 different lines. And then, the system became mixed
process manufacturing system. However, the mixed production happened at
only Deburring process. As we had known, the number of machines had been
reduced by 1, but we still kept the number of workers. So, we would
build a new production plan. At Hobbing station, each different type of
items was processed on one different machine, but at Deburring station
one machine would process 2 different types. Namely, speed gear number 1
and number 2 would be processed on one Deburring machine; similarly,
speed gear number 2 and number 3, speed gear number 3 and number 4,
Speed Gear number 4 and number 5. We must be aware that there was time
of changing tools before changing to process the other types. And in our
process scheduling, the time of changing tool was taken into account.
Therefore, at Deburring stations the time of changing tools had been
added
[FIGURE 2 OMITTED]
Thanks to all the improvements on the above, the machine
utilization ratio of Deburring process was improved to 81.28% and the
one of the entire line was 78.4%. The values were significant
improvement if we put them in comparison the values of the
semi-automatic system, 63.32% and 76.0%, respectively. As a result, the
mixed process system had 37 units/day more than the capacity of the
semi-automatic system. Namely, the capacity of the mixed process system
was 1209 units/day, and it satisfied our target.
In addition, due to the characteristics of mixed process system, we
had to use 10 workers (higher than 7 of automatic manufacturing system);
the worker utilization ratio was 85.63%, which was also higher than
70.43% of automatic manufacturing system. This result met our goal of
maximizing the use of manpower. Therefore, due to the reduction of 1
machine at Deburring station, it was not only that the machine
utilization ratio had been improved, but also we got cost effective
5. CONCLUSION
In this study, we had used Logical Tree of Thinking Process in
Theory of Constraints to solve a problem in automobile transmission
manufacturing system. Also, we used 3D virtual simulation technique to
get out the problem and analyze the current system. And the solution
came out based on the objective-oriented analysis. After building mixed
process semi- automatic manufacturing system, we used the 3D virtual
simulation method to get the results of the system working. There was
only the output/day of the new system that was not better than the
automatic system's, the output/day still satisfied our goal. All
the others were better than the automatic system's. The main
problem which had happened at Deburring station was also solved clearly.
The solvent also gave us cost effective.
6. ACKNOWLEDGEMENT
This research was supported by the Ministry of Knowledge Economy,
Republic of Korea under the development program of regional industry
technology.
7. REFERENCES
Jayaraman, A. & Agarwal A. (1996). Simulating an Engine Plant,
Manufacturing Engineering, 117/5, 60-68
Jayaraman, A. & Gunal, A. (1997). Applications of Discrete
Event Simulation in the Design of Automotive Power train Manufacturing
Systems, Winter Simulation Conference, 1/1, 758-764
Park, Y. J.; Shin, H. S.; Chung, K. H.; Hong, S. W. & Noh S. D.
(2002). Material Flows Analysis and Storage Plans Evaluations by Virtual
Automotive Body Shop, Conference Proceedings of KSAE, 1/1, 1005-1010