Information technology in the development of the Polish construction industry/Informacines technologijos ir lenkijos statybos pramones pletra.
Kaplinski, Oleg
1. Introduction
The IT market (not only in construction sector) changes faster than
we can notice. The situation in this market is easy to become familiar
with through websites. What is clear is the lack of synthetic analyses
whose results more form the dynamics in the IT market and changing
challenges.
In Poland, it is the ITB (Building Research Institute), which had
begun the integration of research on saturation of measurement processes
with IT, and on broadly understood quality management in the
construction sector. Characteristic results of the said integration have
been presented in the following reports: Witakowski, 2005, 2007, 2008.
The examples of papers prepared at the department steered by the Author
are following: Gajzler 2008; Karlowski 2008; Karlowski and Paslawski
2008; Paslawski 2008a; Thiel 2008. The preliminary results of these
research are presented by Kaplinski and Milosz 1996; Kaplinski and
Meszek 1992; Kaplinski and Thiel 1995; Kaplinski and Janusz 2006; Janusz
and Kaplinski 2006, 2007; Kaplinski 2007.
Polish construction sector is, in principle, influenced by four
factors. They are indicated as N, S, E, W and presented in Fig. 1.
Factor S is a general tendency towards knowledge based economy. Factor W
is IT equipment development, development of methods, including decision
making methods; a new way of functioning of a business. Factor E
encapsulates technical and economic conditions; good economic climate in
construction sector; fast growth of profitability of the sector; and
even the philosophy underlying company management. Factor N, the
REALITY, is situated on the borderline of all conditions, equipment
capabilities, as well as psychological barriers (i.e., in new IT methods
implementation).
A review of the basic factors, E and W, in the context of IT
development and implementation is the subject of this paper.
Construction Management is the context of the discussion.
2. Changes in approach towards information technology
Deeper and quite sudden interest in IT has resulted from changes in
a manner of decision making and production planning. Fig. 2 presents
those changes: what is clear is the tendency to replace intuition with
research (Kaplinski 1994). This was undoubtedly fostered by the
development of IT tools. The universal trend is marked as (d). The
situation in EU before 1990, and in 2005 is presented in two ovals (a),
whereas the situation in Poland before 1999 and in 2005 is marked as (b)
and (c). The results of the Author's research covering the 1990s
and 2005 have been published in a variety of form--see: Kaplinski 1994,
1997, 2008a, b, c.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
The evolution of IT tools in construction project management (Fig.
3) is very characteristic. The dominating identification covers the area
from identification of promotion state to object identification. The
right side of the graph presents respective techniques: from statistical
analysis to radio frequency identification (RFID). Constant and dynamic
development of those techniques can be observed (Kaplinski 2008b, c).
Numerous examples of the development of these techniques are published,
for example: Jurkevicius and Laukaitis 2007; Kaplinski and Zavadskas
1997; Krylovas and Kosareva 2008; Mickaityte et al. 2007; Nassar and
Casavant 2008; Lee and Egbu 2007; Turskis et al. 2006; Turskis 2008;
Popov et al. 2006; Schafer and Sedziwy 2001; Scheer et al. 2007. Various
other aspects was analysed by: Khamkanya and Sloan 2008; Mitkus and
Trinkuniene 2008; Rutkauskas 2008; Rutkauskas et al. 2008; Samuelson
2008; Selih 2007; Skorupka 2005; Zavadskas et al. 2008a.
Other considerations in the context of economy are presented by:
Ginevicius and Podvezko 2008; Kaganova et al. 2008; Kaklauskas et al.
2007; Kaplinski 1985, 1993, 2001; Kaplinski et al. 2002; Mickaityte et
al. 2008; Mitkus and Sostak 2008. The synthesis of these comparisons and
analysis have been presented by Kaplinski and Zavadskas 2002.
RFID finishes left part of the Fig. 3. This aspect will be very
significant in the development of IT in the construction. Effects of
this approach are already visible, for example: Cheng, M.-Y. and Chen,
J. C. 2002; Cheng et al. 2008; Karlowski 2008; Turskis et al. 2006;
Witakowski 2007; Yagi et al. 2005.
[FIGURE 3 OMITTED]
3. Diversification and variety of IT software. The Polish
experience
Due to a specific situation (growth in profitability) and
relatively low level of investment in the area of management systems,
Polish construction companies may be an ideal market for IT companies.
The character of activity (construction services) makes project
management a dominating issue. Companies generally look for such project
management systems which would be integrated with financial management,
human resources, stock management and machinery maintenance. All
companies create timetables but, unfortunately, they use different
systems. What dominates here is the package called MS Project. Source
data on materials, availability of workforce and machinery is introduced
using a variety of applications (for example, Oracle, Lotus
Notes/Domino), by hand, or with considerable delay.
ERP (Enterprise Resource Planning) has recently been the best known
IT offer for construction industry (Brzozowski 2007; Inwestycje 2007;
IDC 2007; Piotrowski 2007). Unfortunately, it is usually a standard
package which does not take specific character of construction industry
into consideration. This is why there are more and more IT companies in
Poland that have been making modifications focused on construction
industry. Some of them create modules supporting solely building
companies. The following tendencies can be observed: management of the
building site on-line which makes it possible to acquire information
form the Internet (for example, tender announcements, supplier price
lists) and WORKFLOW, supposedly based on processes. It is known from
experience that an ERP package must be equipped with cost estimation
tools.
It is the manner of organisation in a construction company that is
decisive in a success of implementation of ERP. Polish companies notoriously switch to the so-called process management. Regardless of
the size, or organisational structure, all building companies are
similar from the standpoint of function of the processes. Therefore, it
is possible to present a "normalised" process management
model. The most popular model in this field is the model presented by
Athena Soft, a company geared exclusively towards construction industry
(Capital 2005). The model embraces finding customers, presentation of
offers, signing an agreement, and etc., the whole series of events
connected to production preparation through to final accounting of the
investment. Such activities (according to the pattern) are also expected
to: accelerate and ensure the reliability of information flow within the
company; swiftly detect departures from plan; counteract wasting
resources and lead to avoiding penalties for delays.
Creating a model of a learning company is an important background
to such a discussion, so that the knowledge was available to entire
company, and not become a residue in the heads of only some of the
employees.
The experience of construction companies suggests that in order to
operate well, they need to integrate their management system with the
surroundings. This goal is usually achieved by the means of:
--integrating the system with cost estimation programmes and work
scheduling programmes;
--co-operation with suppliers, sub-contractors, and with the
investor;
--communications with banking systems and official institutions.
For example, integration means that labour, materials and equipment
information, gathered in the cost estimate, and processed in the work
schedule, are downloaded to the computerised management system (ERP).
Therefore, future users trust those programmes which are made up
from modules. An additional condition for successful ERP implementation
is a division into three levels and, what is most important, correct
data flow between system modules and the surroundings. Building site and
construction management is the main level (MRP, Manufacturing Resource
Planning). What is also important is the integration with cost
estimating and work scheduling. At level two, the PROCESSES module is
one of the most important ones. It supports the process management model
in the company. Level three, containing modules used to manage
relationships with customers and accounting, is called communications
with the surroundings (ERP II).
Departing from reasonable data flow between system modules and the
surroundings will generally waste the effort of implementing IT. One can
say, Microsoft creates the Polish construction market at present. MS
Office System 2007 (with MS Project and EPM--Enterprise Project
Management family--project management elements, Unified Communications
solutions for communication) is a modified proposal (Infosystem 2008).
Additional internal Windows Sharepoint Services website makes building
site status reporting more precise. This is foreign software,
nonetheless, capable of supporting an order portfolio. Some Microsoft
Office mutations have also appeared. The best graphic solutions are
offered by Microsoft Office Enterprise 2007 package which is based on
the following applications:
--Microsoft Office Professional Plus 2007,
--Microsoft Office Groove 2007,
--Microsoft Office OneNote 2007.
The package offers to users the availability of information
regardless of the fact that they may be using their computers on-line or
off-line. Notably, industrial companies are major clients for such
applications.
There exists software assisting communications, namely Microsoft
Office Communication 2007. On the other hand, Microsoft Unified
Communications enables effective communication between an individual and
an organisation.
Some interesting Polish solutions of integrated management have
already appeared, for example: ERP-Impuls 5 (written by BPSC), and
Microsoft Dynamics AX (formerly Axapta), (Infovision 2008). The latter
is an ERP II class IT system, i.e., a merger of ERP and e-Biznes.
Software for construction companies is individually written and
tailored. This is how Xpertis Deweloper (created by Macrologic) was
created, including a number of modules, also a communications management module (Piotrowski 2007). This software is addressed to real estate
developers and general contractors.
An example of efficient adjustment of an integrated SAP type (SAP
Global Hosting Partner) IT system to the construction sector is an offer
of a company called intelligence. This software, called it.construction,
is addressed to the industrial construction sector (see: Capital 2005).
It is particularly useful at the offer presentation stage. It takes into
account the following: changes, for example in material and service
prices, currencies; sub-contractor cost valuations. The companies which
took interest in the it.construction use this software to search for new
offers, and to compare them to historical data.
Valuation and cost-quotation software is another major group of
applications. They use a wide range of interactive price databases.
Traditional spreadsheets are replaced with interactive applications
which facilitate simultaneous work of team members on the same
spreadsheet. Users indicate that such applications make sense if they
help in timetabling and monitoring the process of erecting a building.
Athenasoft proposes to integrate Norma Pro cost quotation development
software with Capital, a construction company management system (see:
Opon 2006). Capital system uses the XML standard, and co-operates with
MS Project network planning packages, as well as Planista, a Polish
application. The integration is based on uploading information on
resources (labour costs, materials, equipment) gathered in the estimate
to the Capital system, and processed in the timetable. A four stage
model of implementation of a construction work contract embraces the
following: procuring an offer, preparing production, construction work
as such, accounting stage.
There is an abundance of software used to make cost estimates.
Apart from Norma Pro mentioned above, there are other software packages:
Edbud, Expert, Forte, Kobra, Leonardo, Norma 3, Norma Standard, Rodos,
Seko, Skobud, Strix, Sykal Winbud, Zuzia. They use the following pricing
databases: Sekocenbud, Orgbud-Serwis, Bistyp, PZU, and Intercenbud
databases (on CDs and on-line) (Paradowski 2007). Apart from those
mentioned above, there are software packages which will write cost
estimates in ath and XML (ath2) formats, which is especially important
when cost estimates are transferred to investors--public investors in
particular--who often do not have any cost estimate software at all. It
also fosters data exchange between building companies (basing their work
on different software) in electronic form. The XML format facilitates
storage, publishing, and exchange of data between users. This format is
supported by major software producers. Moreover, the software which
produces cost estimates in keeping with foreign documentation, for
example in the FIDIC or PRINCE2 standards (Ministry ... 2008), or based
on German standards, is more competitive, for instance: DBD-Bauteile,
STBL-Bau, DBD-Baupreise (Paradowski 2007).
It is worth mentioning that 20% of construction companies use their
own databases of labour consumption and prices. The remaining 80% use
averaged databases (for instance, KNR).
As it is clear from own experience, IT products in the Polish
market satisfy 80% of needs in electrical and machinery sector; barely
2% of the construction sector; while the remaining 18% can be allocated
to other sectors.
The best software saturated branch of the construction sector is
the branch of building materials production and distribution (Bielewicz
2005; Brzozowski 2007; Mitura 2006). It has surpassed the bridge branch,
i.e., generally speaking, the area of bridge management (Bien 2002).
Further down the line there are industrial construction and real estate
companies.
The building material branch is slowly turning away from SCM (Supply Chain Management). For instance, Polskie Sklady Budowlane
(Polish Construction Warehouses) have based the recent version of their
system (distribution network) on Microsoft SQL Server (Bielewicz 2005).
This step was caused by growing competition from international networks,
such as Castorama and Leroy Merlin. Mostostal implemented Business
Intelligence (Mitura 2006). A number of companies have set up their own
EDI (Electronic Data Interchange). This branch will probably be first to
introduce an RFID system.
In construction sector, following a number of experiences, there is
a belief that:
--there is a irrevocable demand for a thorough analysis before IT
software is bought,
--a supplier who can offer a tailored application package, not a
ready made system ought to be chosen; the system that meets the needs of
the company should be created. It must analyse crucial data, for
example, cost of labour, cost of materials, etc., and be able to compare
them with the scheduled budget,
--the system to be implemented must have open architecture, as in
the future it is supposed to enable extension and guarantee openness to
co-operation with application packages from other IT suppliers,
--complete hardware and network infrastructure should be secured.
4. Prosperity in construction industry and IT solutions
The profitability trend in construction sector has been evident
since 2002. In the years of stagnation, building companies rarely
invested in IT systems. A specific paradox can be observed, namely that
favourable market conditions in the sector and rapid development of
construction companies make IT solutions implementation more difficult,
especially ERP class systems. It can be explained by the fact that the
choice between distant benefits (which an IT system may bring in the
future) and a short term profit resulting from a number of projects
which are worked on is difficult. In Poland, at the moment, it is the
builder who dictates conditions in the market (see: Brzozowski 2007; IDC
2007; Kaplinski 2008a; Inwestycje 2007; Mitura 2006; Wierzbicki 2007).
The degree of utilisation of techniques and methods (mentioned in
Fig. 2 and 3) under discussion in Polish enterprises is insufficient.
Their usage before 1990 has been compared to 2005 (Kaplinski 2008b). The
interest in mathematical programming decreased. Similarly to digital
simulation. The said degree, regarding expert systems stayed at its
level. There has been an increase of: scheduling 4D (modelling space +
time), WEB-based project management systems and RFID.
The research on the degree of software utilisation (mainly:
planning methods, decision making techniques are illustrated in Fig. 2
and 3) has been made basing on two surveys (in 2000 and in 2005),
interviews in the Wielkopolska Building Chamber, and data obtained at
BUDMA, an annual construction fair (International Trade Fair in Poznan).
In January 2008, an "IT island" has been created at the fair,
with IT systems proposals (Infosystem 2008).
With such results in mind, the author has checked the relationship
between the degree of usage of the above mentioned methods and
techniques and their type, size (see Table 1), and properties of a
building enterprise. Regression and correlation calculation methods have
been used. Unfortunately, determination coefficient (Table 1) was nearly
equal to zero in all cases. The lack of such a relationship proves
scarce utilisation of construction management (CM) tools. It may be the
result of limited usage of research results, and excessively refined
questions, as well as a result of companies' reluctance or aversion to such confessions which may violate secrecy, obligatory in a
competitive market.
Further research has made it clear that there is a discrepancy in
the assessment of "attractiveness" of recommended or used
methods between academics and businessmen.
Indications regarding attractiveness of recommended or used methods
between academics and businessmen in 2005 have been presented in Fig. 4.
The differences in indications are quite significant.
[FIGURE 4 OMITTED]
Similar research, but dated January 2008, have been illustrated in
Fig. 5. This data added to earlier results presented in Fig. 4.
The academics found fuzzy and stochastic approaches most
attractive. After 2005, such issues as flexible management, advisory
systems appeared, as well as a range of problems with GIS, GPS, and GSM.
Building managers have high hopes not only about RFID, but also
about GIS working together with GPS navigation system supported by GSM.
This merger can bring about an interesting effect regarding monitoring
and controlling production in construction industry, for example with
respect to sequencing deliveries, site of construction, and precision of
assembly.
On the other hand, planning departments find the following most
attractive: scheduling & network methods; risk analysis; cost
analysis programmes. After 2005, there has been more demand for ERP,
communication, as well as information and documentation transfer (see
Fig. 5).
The following are currently experienced problems: human resources
management (including head hunting for professionals and skilled
craftsmen); Public Private Partnership (PPP); cash flow. It means that
there is a greater demand for software packages focusing on budgeting,
risk management, time and cost contingency, ways of financing
investment.
5. The phenomenon of saturation with IT solutions
Various methods flourish in various periods of time, followed by
periods of stabilisation or stagnation. The major criterion of their
assessment is usefulness. The following course of events can be
observed: it happens that some methods become extinct. It confirms
author's earlier thesis that "pure" methods--for
practical reasons--lose their position to combined and hybrid methods.
DSS (Decision Support System)--c.f. Fig. 3--is a good example of such an
evolution. DSS methods initiated other methods, such as: WEB-management
systems, advisory systems, as well as agent technology (see Kaplinski
2008c). The statements presented above are confirmed in the research
work by Brauers et al. 2008; Hola 2006; Hola and Schabowicz 2007; Konior
2007; Marcinkowska and Rejment 2007; Zavadskas et al. 2008b; Zavadskas
and Turskis 2008.
[FIGURE 5 OMITTED]
Parallel to the development or extinction of IT methods and
techniques, a phenomenon of saturation with IT solutions can be
observed. Those methods and software will not be available to all
potential users. It means that there will never be a full (i.e., 100 per
cent) saturation with a given product, for example with a specific
software package, and so on. This situation is presented in Fig. 6.
There is, hypothetically, a saturation limit. The point is that it would
be better to "move" those lines more to the right in order to
"take over" the area in the middle. The existence of the area
towards the far right also results from inertia (in acquiring new
tools); the barriers mentioned above (resulting from the possibility of
achieving profitability without investing in IT); as well as the time
threshold (new methods appear, old solutions have to go). IT suppliers
should investigate this phenomenon in depth.
6. Conclusions
A number of detailed conclusions were presented in the text. The
conclusions below have a more general character.
[FIGURE 6 OMITTED]
1. What follows from the review of IT methods and software in
Polish construction sector is that the development of those tools is
dynamic, though not all solutions account for specific character of the
construction industry. This is particularly visible in applications of
ERP.
2. Expenditure and investment in IT tools in construction sector is
insufficient.
3. The market for IT suppliers is huge. Nonetheless, IT suppliers
(and designers), in order to satisfy their ambitions, should take into
account the phenomenon of saturation with IT products.
4. The study of the construction market in Poland indicates the
discrepancy in the assessment of attractiveness and usefulness of IT by
decision-makers from companies and universities. The Polish companies at
present still manage to be highly profitable and do not need to invest
in IT tools.
5. The period of prosperity for building companies who chose not to
use IT on the regular basis is coming to an end--because of financial
crisis disclosed in 2008.
doi: 10.3846/1392-8619.2009.15.437-452
Received 23 December 2008, accepted 20 August 2009
References
Bielewicz, A. 2005. Wielka kariera rodzimej sieci [The great career
of the native net]. Available from Internet:
<http://erpstandard.pl/artykuly/49236.html>. Published: Oct. 3rd
2005.
Bien, J. 2002. Modelowanie obiektow mostowych w procesie ich
eksploatacji [Modelling of bridge objects in process of their
maintenance]. Wroclaw Technical University Press, Wroclaw. 348 p.
Brauers, W. K. M.; Zavadskas, E. K.; Peldschus, F.; Turskis, Z.
2008. Multi-objective decision-making for road design, Transport 23(3):
183-193. doi:10.3846/1648-4142.2008.23.183-193.
Brzozowski, A. 2007. IT dla budowlanca [IT for builder], Nowy
Przemysl, 7/8. Available from Internet: <http://wnp.pl>.
Capital. Zintegrowany system zarzadzania dla budownictwa. 2005.
[Capital. The integrated system of the management for the construction
industry]. Warszawa, Athenasoft. 24 p.
Cheng, M.-Y.; Tsai, H.-C.; Lien, L.-C.; Kuo, C.-H. 2008. GIS-based
restoration system for historic timber buildings using RFID technology,
Journal of Civil Engineering and Management 14(4): 227-234.
doi:10.3846/1392-3730.2008.14.21.
Cheng, M. Y.; Chen, J. C. 2002. Integrating barcode and GIS for
monitoring construction progress, Automation in Construction 11(1):
23-33. doi:10.1016/S0926-5805(01)00043-7.
Gajzler, M. 2008. Hybrid advisory systems and the possibilities of
it usage in the process of industrial flooring repairs, in The 25th
International Symposium on Automation and Robotics in Construction.
ISARC-2008. Selected papers (June 26-29, Vilnius, Lithuania). Edited by
E. K. Zavadskas, A. Kaklauskas, M. J. Skibniewski, 459-464.
Ginevicius, R.; Podvezko, V. 2008. A feasibility study of
multicriteria methods' application to quantitative evaluation of
social phenomena, Business: Theory and Practice. Vilnius: Technika,
9(2): 81-87.
Hola, B. 2006. Model of development tendency of accident situation
in construction industry, Archives of Civil Engineering 52(1): 177-188.
Hola, B.; Schabowicz, K. 2007. Neural identification of earthmoving
machinery's productivity, Archives of Civil Engineering 53(4):
607-711.
IDC, 2007. Poland enterprise application software 2007-2011
forecast and 2006 vendor shares. Source: www.sap.com, July 2, 2007.
Infosystem 2008. Informatyka dla budownictwa i nieruchomosci
22.01.2008 [Computer science for building and property 22.01.2008].
"IT island" on the building trades fair BUDMA. Accessed from:
www.decyzje-IT.pl.
Infovision 2008. Microsoft Dynamics AX. Available from Internet:
<http://www.infovision.pl/>.
Inwestycje w IT: konkurencja coraz ostrzejsza. 2007. [Investments
in IT: more and more sharp competition]. Available from Internet:
<http://www.erp-view.pl>. Published: 2nd March 2007.
Janusz, L.; Kaplinski, O. 2006. The application of multifactor
modelling LITCAC in the organization of assembly work of flexible
corrugated steel structures, Technological and Economic Development of
Economy 12(3): 195-199.
Janusz, L.; Kaplinski, O. 2007. A new approach to design and
modeling of flexible corrugated steel plate structures under
construction, in Xie, Y. M. & Patnaikuni, I. (Eds.). Innovations in
Structural Engineering and Construction. Taylor & Francis Group,
London, 219-224. ISBN 978-0-415-45755-2.
Jurkevicius, D.; Laukaitis, A. 2007. Programinio agento,
naudojancio nekilnojamojo turto ontologija, taikymas kaip duomenu
Saltinis sprendimu paramos sistemai [Application of the program AGENT,
that uses reality ontology, as data source for the decision support
system], Technological and Economic Development of Economy 13(3):
237-243.
Kaganova, O.; Akmatov, A.; Undeland, C. 2008. Introducing more
transparent and efficient land management in post-socialist cities:
lessons from Kyrgyzstan, International Journal of Strategic Property
Management 12(3): 161-181. doi:10.3846/1648-715X.2008.12.161-181.
Kaklauskas, A.; Zavadskas, E. K.; Banaitis, A.; Satkauskas, G.
2007. Defining the utility and market value of a real estate: a multiple
criteria approach, International Journal of Strategic Property
Management 11(2): 107-120.
Kaplinski, O. (Ed.). 2007. Metody i modele badan w inzynierii
przedsiewziec budowlanych [Methods and models of research in
construction project engineering], Warszawa, KILiW, IPPT PAN, Seria:
Studia z Zakresu Inzynierii, Nr 57. 415 p.
Kaplinski, O. 1985. Die Ausnutzung der Simulationstechnik zur
Untersuchung und die Steuerung der Zuverlassigkeit von
Produktionsprozessen im Bauwesen, Informatik-Fachberichte,
Simulatiostechnik, Springer-Verlag, Band 109: 517-521.
Kaplinski, O. 1993. Diminishing non-uniformity of construction
processes, Journal of Construction Management and Economics 11(1):
53-61. doi:10.1080/01446199300000064.
Kaplinski, O. 1994. Decision techniques in construction management.
State of the art and computerisation problems, Computer Methods in Civil
Engineering--MKIL 4(2): 37-56.
Kaplinski, O. 1997. Modelling of construction processes. A
managerial approach. Warszawa, KILiW PAN, IPPT, Seria: Studia z Zakresu
Inzynierii, Nr 43. 175 p.
Kaplinski, O. 2001. Phenomenon of inertia in construction industry,
Journal of Civil Engineering and Management 7(4): 281-285.
Kaplinski, O. 2008a. Usefulness and credibility of scoring methods
in construction industry, Journal of Civil Engineering and Management
14(1): 21-28. doi:10.3846/1392-3730.2008.14.21-28.
Kaplinski, O. 2008b. Development and usefulness of planning
techniques and decision making foundations on the example of
construction enterprises in Poland, Technological and Economic
Development of Economy 14(4): 492-502.
doi:10.3846/1392-8619.2008.14.492-502.
Kaplinski, O. 2008c. It applications in Polish construction sector,
in The 25th International Symposium on Automation and Robotics in
Construction. ISARC-2008. Selected papers (June 26-29, Vilnius,
Lithuania). Edited by E. K. Zavadskas, A. Kaklauskas, M. J. Skibniewski,
483-489.
Kaplinski, O.; Janusz, L. 2006. Three phases of multifactor
modelling of construction processes, Journal of Civil Engineering and
Management 12(2): 127-134.
Kaplinski, O.; Meszek, W. 1992. Catastrophic and strategic aspects
of building processes balancing, Journal of Construction Management and
Economics 10(1): 81-88. doi:10.1080/01446199200000007.
Kaplinski, O.; Milosz, M. 1996. Reliability of complex production
systems, Civil Engineering Systems 13(1): 61-73.
doi:10.1080/02630259608970186.
Kaplinski, O.; Thiel, T. 1995. Evaluation of multi-family housing
systems in Poland, Journal of Construction Management and Economics
13(4): 291-298. doi:10.1080/01446199500000034.
Kaplinski, O.; Werner, W.; Kosecki, A.; Biernacki, J.; Kuczmarski,
F. 2002. Current state and perspectives of research on construction
management and mechanization in Poland, Journal of Civil Engineering and
Management 8(4): 221-230.
Kaplinski, O.; Zavadskas, E. 1997. Expert systems for construction
processes, Statyba (Journal of Civil Engineering and Management) 12(4):
49-61.
Kaplinski, O.; Zavadskas, E. K. 2002. An overview of problems
related to the research in construction engineering, management and
economics in Poland, Journal of Civil Engineering and Management 8(4):
231-239.
Karlowski, A. 2008. Telemetric system for management in concrete
process, in The 25th International Symposium on Automation and Robotics
in Construction. ISARC-2008. Selected papers (June 26-29, Vilnius,
Lithuania). Edited by E. K. Zavadskas, A. Kaklauskas, M. J. Skibniewski,
318-323.
Karlowski, A.; Paslawski, J. 2008. Monitoring of construction
processes in the variable environment, Technological and Economic
Development of Economy 14(4): 503-517.
doi:10.3846/1392-8619.2008.14.503-517.
Khamkanya, T.; Sloan, B. 2008. Flexible working in Scottish local
authority property: developing a combined resource management strategy,
International Journal of Strategic Property Management 12(3): 183-202.
doi:10.3846/1648-715X.2008.12.183-202.
Konior, J. 2007. Decision assumption on building maintenance
management probabilistic method, Archives of Civil Engineering 53(2):
403-423.
Krylovas, A.; Kosareva, N. 2008. Mathematical modelling of
forecasting the results of knowledge testing, Technological and Economic
Development of Economy 14(3): 338-401.
doi:10.3846/1392-8619.2008.14.388-401.
Lee, C. C.; Egbu, C. O. 2007. Information technology tools for
capturing and communicating learning and experiences in construction
SMEs in developed and developing countries, ITcon 12: 167-180. Available
from Internet: < http://www.itcon.org/>.2007/11.
Marcinkowska, E.; Rejment, M. 2007. Comparison of theoretical and
practical research results concerning build ability of building external
walls thermal overcladdings, Archives of Civil Engineering 52(2):
425-443.
Mickaityte, A.; Zavadskas, E. K.; Kaklauskas, A. 2007. The
knowledge presentation according to the needs of the participants in the
public refurbishment sector, Technological and Economic Development of
Economy 13(1): 47-55.
Mickaityte, A.; Zavadskas, E. K.; Kaklauskas, A.; Tupenaite, L.
2008. The concept model of sustainable buildings refurbishment,
International Journal of Strategic Property Management 12(1): 53-68.
doi:10.3846/1648-715X.2008.12.53-68.
Ministry of Infrastructure. 2008. Krajowy system zarzadzania
budowlanymi przedsiewzieciami inwestycyjnymi finansowanymi z udzialem
srodkow publicznych i pomocowych Unii Europejskiej [The national system
of the management building investment projects funded with the
participation of the public and aiding resources of European Union].
Warsaw. Available from Internet:
<www.mb.gov.pl/article/system_zarzadzania_budowami/>. Published:
March 17th 2008.
Mitkus, S.; Sostak, O. R. 2008. Modelling the process for defence
of third party rights infringed while implementing construction
investment projects, Technological and Economic Development of Economy
14(2): 208-223. doi:10.3846/1392-8619.2008.14.208-223.
Mitkus, S.; Trinkuniene, E. 2008. Reasoned decisions in
construction contracts evaluation, Technological and Economic
Development of Economy 14(3): 402-416.
doi:10.3846/1392-8619.2008.14.402-416.
Mitura, A. 2006. Przebudzeni. Logika zyskow [Woken up. The logic of
profits], Magazyn Dyrektorow IT, 10. Available from Internet:
<http://cio.cxo.pl.>.
Nassar, K.; Casavant, A. 2008. Analysis of timed Petri nets for
reachability in construction applications, Journal of Civil Engineering
and Management 14(3): 189-198. doi:10.3846/1392-3730.2008.14.16.
Opon, A. 2006. Prekonfigurowany SAP rozwiazuje problemy budownictwa
[Pre-configured SAP solves the problems of building], Forum Budowlane 9:
78-79.
Paradowski, M. 2007. Norma Pro po prawie pieciu latach uzytkowania
[Norma Pro after almost five years of use], Materialy Budowlane 12: 4-5.
Paslawski, J. 2008. Flexibility implementation in construction
process engineering, in The 25th International Symposium on Automation
and Robotics in Construction. ISARC-2008. Selected papers (June 26-29,
Vilnius, Lithuania). Edited by E. K. Zavadskas, A. Kaklauskas, M. J.
Skibniewski, 610-615.
Piotrowski, T. 2007. Przeglad programow komputerowyc dla
budownictwa i perspektywy rozwoju [The review of computer programmes for
building and the perspectives of the development], Materialy Budowlane
12: 2-3.
Popov, V.; Mikalauskas, S.; Migilinskas, D.; Vainiunas, P. 2006.
Complex usage of 4D information modeling concept for building design,
estimation, scheduling and determination of effective variant,
Technological and Economic Development of Economy 12(2): 91-98.
Rutkauskas, A. V. 2008. On the sustainability of regional
competitiveness development considering risk, Technological and Economic
Development of Economy 14(1): 89-99.
doi:10.3846/2029-0187.2008.14.89-99.
Rutkauskas, A. V.; Miecinskiene, A.; Stasytyte, V. 2008. Investment
decisions modelling along sustainable development concept on financial
markets, Technological and Economic Development of Economy 14(3):
417-427. doi:10.3846/1392-8619.2008.14.417-427.
Samuelson, O. 2008. The IT-barometer--a decade's development
of IT use i the Swedish constructor sector, Itcon 13: 1-19. Available
from Internet: <http://www.itcon.org/>.2008/1.
Schafer, R.; Sedziwy, St. (Ed.). 2001. Advances in multi-agent
systems. Wydawnictwo Uniwersytetu Jagiellonskiego, Krakow. 190 p.
Scheer, S.; Mendes, R. Jr.; Quevedo, J. R. S.; Mikado, J. Jr.;
Fontoura, P. S. 2007. The necessary background for implementing and
managing building design process using WEB environments. Available from
Internet: < http://itcon.org/>. Published: March 2007.
Selih, J. 2007. Environmental management systems and construction
SMEs: a case study for Slovenia, Journal of Civil Engineering and
Management 13(3): 217-226.
Skorupka, D. 2005. The method of identification and quantification
of construction project risk, Archives of Civil Engineering 51(4):
647-662.
Thiel, T. 2008. Determination of the relative importance of
criteria when the number of people judging is a small sample,
Technological and Economic Development of Economy 14(4): 566-577.
doi:10.3846/1392-8619.2008.14.566-577.
Turskis, Z. 2008. Multi-attribute contractors ranking method by
applying ordering of feasible alternatives of solutions in terms of
preferability technique, Technological and Economic Development of
Economy 14(2): 224-239. doi:10.3846/1392-8619.2008.14.224-239.
Turskis, Z.; Zavadskas, E. K.; Zagorskas, J. 2006. Sustainable city compactness evaluation on the basis of GIS and Bayes rule, International
Journal of Strategic Property Management 10(3): 185-207.
Wierzbicki, M. 2007. Sukces rozwiazan IT zalezy od przygotowania
[The success of IT solutions depends on the preparation], Gazeta Prawna,
134 (2004), Thursday, 12 July 2007. Available from Internet:
<http//egp.gazetaprawna.pl.>.
Witakowski P. (Ed.). 2005. Informatyzacja procesow pomiarowych jako
warunek kompleksowego zarzadzania jakoscia w budownictwie [The
computerization of measuring processes as the condition of the complex
management of quality in construction industry]. Warsaw: ITB--Building
Research Institute, No. 410. 123 p.
Witakowski, P. 2007. Zdalne monitorowanie obiektow budowlanych
podczas budowy i eksploatacji [Remote monitoring of building objects
during their executing and exploitation], Czasopismo Techniczne.
Srodowisko 104(1-S): 179-189.
Witakowski, P. 2008. Teleinformatyka w budownictwie
[Teleinformatics in building industry], in Problems of preparation and
realization of building investments. Workshop of the building engineers
(Problemy przygotowania i realizacji inwestycji budowlanych. Warsztat
inzynierow budownictwa). PZITB (October 22-24, Pulawy, Poland), 111-150.
Yagi, J.; Arai, E.; Arai, T. 2005. Parts and packets unification
radio frequency identification (RFID) application for construction,
Automation in Construction 14(4): 477-490.
doi:10.1016/j.autcon.2004.09.005.
Zavadskas, E. K.; Kaklauskas, A.; Turskis, Z.; TamoSaitiene, J.
2008a. Selection of the effective dwelling house walls by applying
attributes values determined at intervals, Journal of Civil Engineering
and Management 14(2): 85-93. doi:10.3846/1392-3730.2008.14.3.
Zavadskas, E. K.; Turskis, Z. 2008. A new logarithmic normalization method in games theory, Informatica 19(2): 303-314.
Zavadskas, E. K.; Turskis, Z.; TamoSaitiene, J.; Marina, V. 2008b.
Multi-criteria selection of project managers by applying grey criteria,
Technological and Economic Development of Economy 14(4): 462-477.
doi:10.3846/1392-8619.2008.14.462-477.
Oleg Kaplinski
Poznan University of Technology, Dept of Construction Engineering
and Management,
60-965 Poznan, Piotrowo 5, Poland, e-mail:
[email protected]
Oleg Kaplinski. Professor of Civil Engineering at Poznan University
of Technology, Poland. He is the Head of the Chair of Construction
Engineering and Management. PhD (1971), Doctor Habil (1979), Sc-Title of
Prof (1992). A member of Civil Engineering Committee of Polish Academy
of Science and Chairman of the Section of the Engineering of
Construction Projects in this Committee. Publications: 10 books. His
research interests include the organization and modelling of
construction processes, decision-making theory.
Table 1. Relationships between the usage of IT techniques and
the characteristics of a building company
Relationship Size of building company Property of company
Number of data 5 classes; data: 3 classes; 15 data
31 plus 25 (zero) (in this 3 zero)
Equation y = -0.11x + 9.41 y = -0.1x + 3.5
Determination
coefficient 0.0005 0.0114
[R.sup.2]
Relationship Type (specialization)
Number of data 8 x 4 data; after reduction to average: 8 data
Equation y = 55.573[x.sup.-0.0216]
Determination
coefficient 0.0017
[R.sup.2]