Modelling a dispute hearing between an investor and the public concerned in administrative courts of the Republic of Lithuania.
Sostak, Olga Regina ; Makuteniene, Daiva
Introduction
Development of national economy is impossible without construction:
people use such construction products as various types of buildings to
live, work and satisfy other social needs (Burinskiene et al. 2011).
Construction investment contributes to national economic growth and
development extensively (Zavadskas, Kaklauskas 2008; Zavadskas et al.
2010b). Many Lithuanian cities and towns undergo intense transformations
related to commercialisation, land use and built territories. Some
examples from European cities have shown that construction development
can target internal urban areas (Erdis 2013). Lithuanian cities
currently witness concentrated development as well. It facilitates the
use of the existing infrastructure and the reuse of abandoned urban
territories. Such planning cuts the amount of used land and creates a
lasting environment with dense population able to function properly. On
one hand, it is a natural phase related to the revival of the most
valuable neglected urban areas. On the other hand, the course and
outcomes of this process reveal gaps within the renewal process. The
blame may be cast on the failings of laws governing urban planning and
protection of visual identity (investors cannot always be expected to
abandon their self-centred ends for the sake of urban values, etc.).
Largely, this is determined by the confusing, inefficient system
employed when constructions must be coordinated with state authorities
and the public. Construction regulations are confusing, builders breach
requirements, and officials often may choose which requirements to
enforce at their own discretion. A range of problems spring from an
inappropriate distribution of functions among national authorities and
private entities. One outcome of inappropriate legal regulation of
construction processes is infringements of third-party rights (these are
parties with no direct involvement in a construction investment process:
owners of neighbouring plots, users, communities of residential areas,
etc.). Third parties are persons who become involved in a case because
of their legal interest in the dispute outcome; they either join a
procedure in progress themselves, or, in cases established by laws, may
be included by any party or by court.
Third parties fall into two groups by the goal of their involvement
in dispute resolution. The first group is third parties with claims of
their own and the second-third parties without such claims. Third
parties with claims of their own have all rights and duties of a
plaintiff (CPC, Art. 46). Meanwhile, third parties without claims of
their own toward the dispute's subject matter may join the case on
the side of either the plaintiff or the defendant before the closing
speeches, in cases the judgement might affect their rights or duties.
They may also be included in a case under a motivated request of the
parties or by court. The third parties without claims of their own have
procedural rights and duties of a party, save for the right to change
the grounds or the subject matter of the complaint, add new claims or
remove some claims from the complaint, withdraw the complaint, accept
the complaint, or reach an amicable settlement. They are also not
entitled to demand enforcement of the court decision (CPC, Art. 47). To
avoid confusion between third parties with claims of their own and third
parties without claims of their own, the article refers to the former as
the public concerned. The legislator defines the public concerned as the
public affected or likely to be affected by the solutions of the
territorial planning document being prepared or public with interest in
implementation of such solutions (Law on Territorial Planning, Art.
2(34); Mitkus, Sostak, 2008; Sostak, Vakriniene 2011; Lietuvos
Respublikos civilinio proceso kodeksas; Lietuvos Respublikos teritoriju
planavimo istatymas; Chou, Lin 2013).
The investment process in construction is long and complicated; it
requires enormous financial, intellectual and other resources. If a
judicial dispute occurs during this process, the investor may suffer an
enormous loss, and the project implementation may be postponed for an
indefinite term. The litigation may continue for several years (SACL
ruling in the administrative case, 26 January 2007, No.
[A.sup.14]-110-07; SACL ruling in the administrative case, 19 January
2007, No. [A.sup.3]-64-07; SACL ruling in the administrative case, 20
February 2006, No. [A.sup.11]-792/2006). Thus the investor is most
concerned to avoid any legal disputes and should pay considerable
attention to their prevention. Before starting a project, the investor
must be ready for any surprises. Forecasting is the key part in any
strategy, because actions recommended for certain situations stem from
the forecasts of possible outcomes. The article makes use of a
conceptual model, as a method of deliberation, to determine possible
ways to organise two opposing systems (the investor and the public
concerned) in order to achieve the goals defined. The conceptual model
is used as a tool to design two opposing systems. The conceptual model
analyses and defines the behaviour of two opposing parties in certain
states and at certain times (stages of the detailed planning process,
the stage of legal proceedings in an administrative court of first
instance, the stage of proceedings in an administrative court of appeal,
etc.). The conceptual model shows the activities to be performed and
their interrelations (Urbanaviciene et al. 2009). The conceptual model
facilitates proper estimation of the scope of conflict's possible
negative effect and its outcomes on the construction project. The
analysis of risks, done with the help of the conceptual model, should
make an impact on further decision-making (Bao et al. 2012; Desierto
2013; Chamodrakas et al. 2011). Throughout the project lifecycle the
investor must monitor risks and analyse decision-making, improve the
development of its risk management strategies and risk management plan,
make use of risk analysis methods and technologies, implement the
mechanism of risk reports (Lakis 2008; Kersuliene et al. 2010;
Zavadskas, Turskis 2011).
In a construction project, judicial disputes are an unwanted risk
factor, which may disrupt the entire project. It is therefore necessary
to plan and apply preventive measures for the mitigation of such risk at
the initial planning stage of a construction project (Zavadskas et al.
2010a; Yang et al. 2009; Park et al. 2009; Yang et al. 2009; Pinter,
Psunder 2013). The article for that purpose analyses an actual judicial
dispute between an investor and the public concerned heard in
administrative courts of the Republic of Lithuania. The negative
outcomes of this judicial dispute, both on the investor and the public
concerned, have been determined. The investor's blunders that
barred any chance to prevent this judicial dispute and led to several
years of litigation, have also been determined. The article analyses the
behaviour of the disputing parties at various stages of the judicial
dispute. Based on the research, a conceptual model was crafted to enable
analysis of formal model behaviour in future studies and to build a
complex system that would facilitate any construction project with
planning and application of preventive measures that would mitigate the
risk of a judicial dispute as early as during the first project planning
stage (Koziratskiy et al. 2008; Tettey, Marwala 2007; Lin et al. 2011;
Yeh et al. 2012; Wang et al. 2012).
1. Case study: a judicial dispute between an investor and the
public concerned in administrative courts of the Republic of Lithuania
Infringements of rights of the public concerned are of benefit
neither to the public concerned nor to the participants of a
construction investment process. On one hand, such infringements might
wrongfully cause deterioration of life and work conditions of the public
concerned; while on the other hand, infringements of rights of the
public concerned at the phase of construction planning may affect
implementation of the investment project, because all solutions
infringing rights of the public concerned at the same time violate the
provisions of normative legal acts and can be disputed as stipulated by
the Law on Administrative Proceedings (hereinafter LAP), the Law on
Territorial Planning (hereinafter LTP) and other legal acts (Lietuvos
Respublikos teritoriju planavimo istatymas; Lietuvos Respublikos
administracinivj byhj teisenos istatymas; Mitkus, Sostak 2009; Fig. 1).
LAP defines the concept of administrative disputes as conflicts between
persons and entities of public administration or conflicts between
entities of public administration that are not subordinate to each
other; it means conflicts between a municipality and the public
concerned that is affected by detailed plans approved by the
municipality and building permits issued on that basis.
The article will analyse the judicial practice. Figure 1 shows the
defence process of infringed rights of the public concerned in
administrative courts (the diagram is based on the data from an actual
case: SACL ruling in the administrative case, 21 February 2006, No.
[A.sup.7]-85006; SACL ruling in the administrative case, 26 January
2007, No. [A.sup.14]-110-07). The article will analyse an actual
judicial dispute between an investor and the public concerned, determine
the negative effects of this judicial dispute on both the investor and
the public concerned, and determine the investor's blunders that
barred any chance to prevent this judicial dispute and led to three-year
litigation (see Fig. 1).
The parties in this dispute are: natural persons (the occupiers of
the apartment house standing in the plot adjacent to the territory of
the intended construction investment project) as the plaintiffs, the
Administration of Vilnius City Municipality as the defendant, and third
persons without claims of their own on the side of the defendant (the
association of garage owners, hereinafter-the investor, and the
association of new residential construction, hereinafter-the investor).
The complaint submitted by the plaintiffs requested to revoke the
order No. 30-1849 of 19 November 2004 issued by the director of the
Administration of Vilnius City Municipality and approving the detailed
plan of a territory in Vilnius, as well as to revoke the decision passed
on 3 June 2005 by the Administration of Vilnius City Municipality to
grant the investor the building permit No. NR/594/05-0666 for
construction of an apartment house in Vilnius. The complaint of the
plaintiffs pointed out the fact that, on 19 November 2004, the director
of the Administration of Vilnius City Municipality approved the detailed
plan of the territory in Vilnius by the order No. 30-1849. Then, on 3
June 2005, the Administration of Vilnius City Municipality made the
decision to issue the building permit No. NR/594/05-0666 for
construction of an apartment house in Vilnius. The said legal acts
approved the solutions in the detailed plan and in the project
documentation, while the plaintiffs believed these solutions
contradicted legal norms governing territorial planning and construction
and hence violated their rights enjoyed as occupants. The plaintiffs
laid out the following arguments to support their claims:
1) The plot is smaller than the normative minimum allowed. The
minimum plot size is governed by Clause 11 of STR 2.02.01:2004
"Residential Buildings" (approved by the order No. 705 of
Minister of Environment on 24 December 2003)(STR Gyvenamieji pastatai);
the plot area of the designed building fails to comply with the
requirements set forth in the said clause of the normative legal act.
2) The building foreseen in the detailed plan and designed in the
respective design documentation fails to comply with the fire safety
requirements. Clause 54 of STR 2.02.01:2004 "Residential
Buildings" (approved by the order No. 705 of Minister of
Environment on 24 December 2003) states that "access roads for fire
engines to buildings of four storeys and above must be available along
the two longest sides of the building with additional sites for fire
engine ladders". This requirement was not respected. Neither the
detailed plan nor the design documentation foresees any site for fire
engines to turn round. Clause 57 of STR 2.02.01:2004 "Residential
Buildings" sets forth the requirements on access of fire engines to
enclosed or semi-open yards. This clause stipulates that any access road
ending in a cul-des-ac must have a site for fire engines to turn round
with minimum dimensions of 12'12 m. Neither the detailed plan nor
the design documentation foresees such site. Clause 58 of the said STR
stipulates that these special sites must always be unoccupied.
3) The playing grounds foreseen in the solutions of the detailed
plan and the design documentation would fail to comply with the
requirements set forth in Clause 243 of STR 2.02.01:2004
"Residential Buildings", which states that "the playing
ground must be located on the site so as to be visible from at least one
room of a flat or from shared premises and at least 10 m away from: the
access road connecting with the street; the site with waste containers;
the garage; and the residential building". The new construction,
which received the building permit, foresees the playing grounds at a
distance of only 5 metres from the building and close to the car park.
4) The conditions of the plaintiffs to use the playing ground will
suffer and will fail to meet the norms. Clause 243 of STR 2.02.01:2004
"Residential Buildings" sets the requirement that "the
playing ground must be located on the site so as to be visible from at
least one room of a flat or from shared premises". Before the
construction, the children of the plaintiffs used the playing ground
visible from windows of all apartments. When the new building is ready,
part of the new building will block the view to the playing ground.
Article 6(4) of the Law on Construction states that "a construction
works, during and after the construction, as well as the construction
site, must be arranged in such a way that during the construction and
use of a constructed construction works, living and working conditions
of third parties which they enjoyed prior to the beginning of the
construction, might be changed only in compliance with the provisions of
normative technical construction documents". The above provision of
the Law on Construction suggests that construction of the building
foreseen in the detailed plan would damage the living conditions of the
plaintiffs (in particular the possibility to keep an eye on playing
children) contrary to the provisions of normative technical construction
documents.
[FIGURE 1 OMITTED]
The said circumstances suggest that the building to be constructed
close to the building of the plaintiffs will fail to comply with fire
safety requirements, will stand on too small a plot with inadequate
layout, and damage the possibilities for the plaintiffs to keep an eye
on their children. The construction of such a building will make a
negative impact on the residential environment of the plaintiffs and
will violate their rights for proper use of their own homes (SACL ruling
in the administrative case, 21 February 2006, No. [A.sup.7]-850-06).
The article moves on to the analysis of the judicial dispute
proceedings between the investor and the public concerned in
administrative courts of the Republic of Lithuania. The diagram of the
proceedings related to the defence of infringed rights in administrative
courts is shown in Fig. 1.
2. The analysis of the judicial dispute proceedings between the
investor
and the public concerned in administrative courts of the Republic
of Lithuania
The proceedings include the main stages specified below.
1. The public concerned learns its rights have been violated
(infringement determined). The analysis of the case files revealed that
the public concerned learned about the construction investment project
on 20 June 2005, as its implementation started. The public concerned had
not been notified about the approval of the detailed plan and the issue
of the building permit (SACL ruling in the administrative case, 21
February 2006, No. [A.sup.7]-850-06; see Fig. 1). Any disputing parties
are interested to handle all disputes as early as possible and prevent
judicial litigation. But in this case, the conflict reached the court,
which means the parties failed to manage the conflict and collaborate:
both parties took no coordinated actions to arrive at mutually
acceptable goals and the conflict took a destructive path. The investor
failed to consider the interests of the public concerned and lost any
chance to resolve the dispute out of court.
2. Before applying to an administrative court, separate legal acts
or actions/omissions of public administration entities foreseen by laws
can be, and in cases stipulated by laws must be, contested by applying
to an extrajudicial institution for preliminary hearing. The proceedings
related to extrajudicial defence of rights of the public concerned are
discussed in Article 25 of LAP. Unless laws stipulate otherwise,
extrajudicial hearings of administrative disputes are handled by
municipal public commissions of administrative disputes and the Chief
Administrative Disputes Commission (LAP, Art. 26). The public concerned
must be an active party in detailed territorial planning and submit
written proposals on territorial planning documents to the organiser of
planning in the course of the entire period of preparation of
territorial planning documents until and during the public meeting as
well as during the consulting (LTP, Art. 32, Part 1). LTP defines a
proposal as the statement of public opinion on supplementing the
solutions of a territorial planning document, suggestion or amendment of
their alternative. Having analysed the proposals submitted by the
public, the organiser of planning prepares a summary concerning the
adopted proposals and those rejected in a reasoned manner, which it
submits together with prepared territorial planning documents to the
institutions coordinating the territorial planning document. The
organiser of planning must respond in writing in a reasoned manner to
the persons who submitted the proposals. The response may be appealed
against to the institution that carries out state supervision of
territorial planning within one month from receiving the appeal. The
institution that carries out state supervision of territorial planning
submits, within 20 working days from the day of receipt of the appeal, a
reasoned response that may be appealed against to court according to the
procedure established by law (LTP, Art. 32, Part 2).
In the case considered here, the complaint about allegedly
infringed rights of the public concerned was never heard by an
extrajudicial institution. There are several reasons. First, the then
effective legal acts allowed directed application to an administrative
court for the defence of infringed rights. Second, the organiser of
planning failed to comply with publicity procedures: the public
concerned received no proper notification about the detailed planning
and had no opportunity to submit its suggestions to the organiser of
planning (see Figs 1 and 2).
The article now proceeds on to all circumstances surrounding the
preparation and approval of the disputed detailed plan. The preparation
of the disputed detailed plan started following the order of the
director of the municipal administration issued on 16 December 2003
"On the Permission to Prepare a Detailed Plan of the Territory Next
to the Land Plot in Vilnius" The specifics related to the process
of detailed territorial planning are set forth in Article 25 of LTP. It
specifies the following stages of detailed territorial planning:
--the preparatory stage;
--the stage of the preparation of the territorial planning document
and
--the final stage.
The preparatory stage of detailed territorial planning includes:
setting the objectives of planning; preparing and approving the
programme of planning; carrying out investigations, as necessary; public
announcement of the decision to start preparing territorial planning
documents and of planning objectives.
In the case analysed here, the intentions to start detailed
planning were announced on 1 October 2003 in the daily Lietuvos Aidas,
with the place for viewing and the place and time for discussion of this
plan specified. The discussion held on 10 October 2003 approved the
preparation of the detailed plan and design documentation. The said
circumstances suggest that first announcement of the intentions to start
detailed planning were not published in a local newspaper, despite such
requirement set forth in Clause 9 of the then effective Regulations on
Public Participation in the Territorial Planning Procedures. This was a
breach of the regulations governing public discussion of drafted
territorial planning documents; the public concerned was also improperly
notified about the detailed plan and did not take part in public
discussions. The newest version of the Regulations on Informing the
General Public and Public Participation in the Territorial Planning
Procedures tightened this requirement and the organiser of planning now
must notify in writing the owners of property in the vicinity of the
territory to be planned about the intentions to start detailed planning
of the land plot (Regulations on Informing the General Public and Public
Participation in the Territorial Planning Procedures, approved by the
resolution No. 33-1190 of the Government of the Republic of Lithuania on
21 March 2007) (Lietuvos Respublikos visuomenes informavimo ir
dalyvavimo teritorijvj planavimo procese nuostatai). Hence, the
organiser of planning must complete both first and second publicity
procedures (1, 2 PP; see. Fig. 2). In the case analysed here, the
organiser of planning failed to comply with these requirements properly
and, thus, a breach of the detailed territorial planning proceedings has
been determined (P1; see Fig. 2).
[FIGURE 2 OMITTED]
Analysis of the case files revealed that the Construction
Association submitted its application for the design brief on 4 April
2004 and received the brief on 9 May 2004. Interestingly, the conditions
of planning must have been issued before announcing the intentions to
start detailed planning-before 1 October 2003. Here we see a breach of
detailed territorial planning procedures P2 (SACL ruling in the
administrative case, 21 February 2006, No. [A.sup.7]-850-06; see Fig.
2).
The article moves on to the analysis of the disputed detailed plan
during the second stage of the detailed territorial planning procedure.
The preparatory stage of the territorial planning document includes
preparation of all solutions, which also included those infringing the
rights of the public concerned. Although the solutions planned at this
stage are mostly determined by the solutions from previous stages, this
particular stage ends with final solutions of the detailed plan and
these solutions may infringe the rights of the public concerned
directly. The solutions introduced at this stage are therefore the most
frequent cause of disputes between the public concerned and the
organisers of detailed planning.
It has been determined that the designing agreement between the
investor and a designer firm was concluded on 3 November 2003. On 16
December 2003, the director of municipal administration issued the order
"On the Permission to Prepare a Detailed Plan of the Territory Next
to a Land Plot in Vilnius" allowing the preparation of the disputed
detailed plan. The municipality and other companies concerned issued
their technical requirements between 29 January and 5 February 2004. The
main drawing with the chief specifications of the disputed detailed plan
was agreed upon (between the investor and the designer firm) on 9
February 2004. Importantly, the design brief was issued only on 9 May
2004 (SACL ruling in the administrative case, 21 February 2006, No.
[A.sup.7]-850-06; SACL ruling in the administrative case, 26 January
2007, No. [A.sup.14]-110-07; see Fig. 2).
The Regulations on Informing the General Public and Public
Participation in the Territorial Planning Procedures stipulate that the
organiser of planning must announce in mass media that the territorial
planning document is ready and specify the procedure, place and time for
its viewing and discussion. The organiser of planning must also notify
in writing the owners of the property in the vicinity of the territory
about the detailed planning document. This makes sure the third and
fourth publicity procedures are complied with (3, 4 PP; see Fig. 2). In
the case analysed here, the date, place and time related to the detailed
plan were announced in the Sostine, the supplement to the daily Lietuvos
Rytas, on 10 February 2004. On the day specified in the announcement (26
February 2004), the local government unit (seniunija) held the second
discussion of the detailed plan, in which the promoter introduced the
intended solutions of the plan and the project was accepted. The public
concerned, however, was not present in the discussion and all solutions
were accepted without public consent. But the Regulations on Informing
the General Public and Public Participation in the Territorial Planning
Procedure state that at least 20 business days must be allocated for
viewing any detailed plans when they are ready. The organiser of
planning must also arrange public exposure of the detailed plan for at
least 10 business days. These arrangements would ensure the fifth and
sixth publicity procedures (5, 6 PP; see Fig. 2).
The final stage of the detailed territorial planning procedure
includes the following steps:
--the step of considering and coordinating the solutions of the
territorial planning document: public hearing, coordinating with
institutions, examination of disputes and
--the step of approving the territorial planning document:
inspection in the institution supervising state territorial planning,
approval and recording in the register of territorial planning.
The Regulations on Informing the General Public and Public
Participation in the Territorial Planning Procedure provide for the
seventh, and the last, publicity procedure, which is a public discussion
of the detailed plan once it is ready (7 PP; see Fig. 2). LTP defines
public discussion as a procedure to ensure publicity of territorial
planning by introducing the prepared territorial plan to the public in
the manner prescribed. This procedure provides the public concerned with
information about the full set of the solutions of the detailed plan. In
the case analysed here, plans to hold a third discussion of the detailed
plan were announced in the Sostine, the supplement to the daily Lietuvos
Rytas, on 7 July 2004. The discussion held on 22 July 2004 approved the
solutions of the detailed plan. No representatives of the public
concerned were present in the public discussion. The data of the case
suggest that the organiser of planning had no interest in collaboration
with the public concerned, also made no attempts to explain the
solutions of the construction investment project to the public and to
handle the dispute through negotiations. Thus, the investor's
blunders, done while preparing the disputed detailed plan, led to
painful outcomes when the implementation of the solutions of the
construction investment project started.
The disputed detailed plan was agreed with relevant authorities. On
17 September 2004, Vilnius County Governor's Administration issued
the document No. (30)-12-2930 stating there were no substantial
objections to the preparation of the disputed detailed plan. On 30
September 2004 the Department of Territorial Planning and State
Supervision of Construction (Vilnius County Governor's
Administration) issued the document No. 474 expressing its approval. On
19 April 2004 the director of the municipal administration issued the
order No. 30-1849 "On Approval of the Detailed Plan of a Territory
in Vilnius" approving the disputed detailed plan, which served as a
basis to register the plan with the register of territorial planning
documents.
Legal acts governing territorial planning stipulate that the
permission to construct can only be issued having verified whether or
not the design documentation corresponds to the design brief; on 18 May
2005 the Municipality's Department of Urban Development agreed this
project with a representative of Vilnius Fire and Rescue Service. On 3
June 2005 the Municipality's Department of Urban Development issued
the building permit No. 594/05-0666 for construction of an apartment
house in Vilnius. On 6 June 2005 the general contractor started its
preparations for the construction (building a bypass to the construction
site, erecting pylons for provisional power supply line from a power
substation, delivering building materials for fencing of the
construction site, etc.) (SACL ruling in the administrative case, 21
February 2006, No. [A.sup.7]-850-06; SACL ruling in the administrative
case, 26 January 2007, No. [A.sup.14]-110-07; see Fig. 2).
3. Judicial defence of infringed rights. LAP stipulates that the
decision of an appropriate administrative disputes commission or any
other institution for preliminary extrajudicial dispute hearing, adopted
after investigating an administrative dispute in line with the
extrajudicial procedure, may be appealed against to the administrative
court by any of the parties to the dispute, contesting the decision of
the administrative disputes commission or any other institution for
preliminary extrajudicial dispute hearing. In such an event the
administrative court may be appealed to within 20 days from the day of
receipt of the decision (LAP, Art. 32). Persons as well as other
entities of public administration, including state and municipal public
administration employees, officers and agency heads are entitled to file
a complaint/petition against an administrative act adopted by an entity
of public administration or against the act/omission of the above
entities if they believe that their rights or interests protected by law
have been infringed (LAP, Art. 22). LAP defines such complaint/petition
as the form of appeal to the authorised institution requesting the
resolution of an administrative dispute. Complaints are lodged with the
authorised institution by private persons, whereas state and municipal
institutions, their representatives or public servants file petitions
(LAP, Art. 28). LAP stipulates that a complaint/petition may be filed
with the administrative court within one month from the day of
publication of the contested act, or the day of delivery of the
individual act to the party concerned or the notification of the party
concerned of the act/ omission (LAP, Art. 33). The claimant is entitled
to withdraw the complaint/petition before it is found to be receivable,
also to specify and change the grounds or subject matter of the
complaint/petition, or to withdraw the complaint/petition at any stage
of the case investigation before the court retires to the conference
room (LAP, Art. 52). The plaintiff and defendant can also arrive at an
amicable settlement and terminate their litigation at any stage of the
court proceedings (see Fig. 1).
In the case analysed here, the complaint was filed to an
administrative court on 14 July 2005: 24 days after learning about the
infringed rights (see Fig. 1). It means the relevant requirement was
complied with, as the term for filing of a complaint was respected. On
28 July 2005 the Regional Administrative Court (hereinafter RAC)
recognised the complaint submitted by the applicants to be receivable.
4. RAC is the court of first instance for administrative cases
concerning legitimacy of legal acts or actions of state (or municipal)
administrative entities, also legitimacy or validity of their refusal to
perform, or protraction of, actions within their competence when the
complainant or the defendant are entities of state or municipal
administration. RAC, as a court of first instance, also investigates
complaints/petitions against the decisions of municipal administrative
dispute commissions and, in cases provided for by law, against the
decisions adopted by other institutions for preliminary extrajudicial
investigation of disputes (LAP, Art. 18 and Art.15). The case hearing
proceedings at court of first instance. Article 68 of LAP stipulates
that the chairman or judge of the court who by virtue of an order
recognised the appeal to be receivable, determine, as necessary, the
following mandatory issues relating to the preparation for the hearing
of the case in the court:
--take measures to secure the claim;
--decide on the summoning of specialists or on expert examination;
--perform other actions necessary when preparing for the hearing of
the case; etc.
The court or the judge may, upon a motivated petition of the
participants in the proceedings or upon its own initiative, take
measures with a view to securing a claim. The claim may be secured at
any stage of the proceedings if failure to take provisional measures to
secure a claim may impede the enforcement of the court decision or
render the decision unenforceable. Provisional measures may be as
follows:
--granting an injunction restraining the defendant from certain
actions;
--stay of execution under the writ of execution;
--suspension of validity of a contested act.
The judge or the court hears the petition for securing the claim
within one day from the receipt thereof, without notifying the defendant
and other participants in the proceedings. If such a petition is filed
together with the complaint/petition, it will be heard within one day
from the acceptance of the complaint/petition. The court or the judge
makes an order on securing the claim, in which the procedure and manner
of the execution thereof is indicated. A separate appeal may be filed
against the court order on the issues regarding the securing of claims.
The filing of a separate appeal against the order to secure the claim
will not stay the execution of the order or suspend the hearing of the
case. The court order to secure the claim will be executed without
delay. The order to replace a measure securing a claim or to cancel the
measure aimed at securing a claim are executed upon the expiry of the
time limit for filing an appeal against such orders and, where the
complaint has been filed, upon making an order to reject the appeal.
Where the injunctions are not complied with, the guilty persons are
imposed a fine by a court order in the amount of up to LTL 1,000 (LAP,
Art. 71).
On 28 July 2005, RAC issued a ruling satisfying in part the request
on provisional measures laid out in the plaintiffs' complaint and
suspended the building permit No. NR/594/05-0666 issued by the
Administration of Vilnius City Municipality on 3 June 2005 to the
investor for the construction of an apartment house in Vilnius until the
court judgement is this case becomes effective, but rejected the request
to suspend the order No. 30-1849 "On Approval of the Detailed Plan
of a Territory in Vilnius" issued by the director of the
Administration of Vilnius City Municipality on 19 November 2004. The
ruling stated that the defendant was entitled to file a separate appeal
against the provisional measures to the Supreme Administrative Court of
Lithuania (hereinafter SACL), within 7 days upon receiving a copy of the
ruling. The defendant used its right of appeal and, on 25 August 2005,
SACL issued a ruling satisfying the defendant's appeal. The request
of the plaintiffs to apply provisional measures was rejected. Thus, in
the case analysed here, the construction operations were suspended for
28 days (20 business days) between 28 July 2005 and 25 August 2005 (see
Fig. 1).
The defence of infringed rights in administrative courts raises
issues with application of provision measures. On one hand, failure to
suspend construction may impede the enforcement of a court decision, or
render the decision unenforceable, when the litigation (which may take
several years) is over. On the other hand, suspended construction may
translate into huge financial losses to the investor and failure to
complete the construction investment project. Should the defendant
prevail in the litigation, the entity to reimburse the loss is unclear.
Judicial practise has seen cases when the non-prevailing party, the
public concerned, had to reimburse the defendant any loss incurred due
to the suspension of construction (SACL ruling in the administrative
case, 20 February 2006, No. [A.sup.11]-792/2006). It may be an
unbearable burden to the public concerned and such scenario restricts
the right of the public concerned to defend its allegedly infringed
rights (SACL ruling in the administrative case, 19 January 2007, No.
[A.sup.3]-64-07). This issue is yet to be finally resolved in judicial
practice. Below is the estimation of the investor's losses for July
2005 due to the suspended construction (see Table 1).
The investor specifies that on top of the above costs other costs
and losses are possible, such as the cost of object's conservation,
the loss of skilled workforce, the growing cost of the property under
construction, the failure to fulfil obligations toward the banks
financing the construction and the subcontractors working on the object,
the delay of all financing and work schedules for an indefinite term
with the schedule also affected by weather conditions in the future. The
amounts estimated above show that in the reviewed case, the suspension
of construction for 20 business days might have cost the investor at
least LTL 2,726.16 x 20 = LTL 54,523.20 (RAC ruling in the
administrative case, 28 July 2005, No. [AS.sup.5]-375/2005; SACL ruling
in the administrative case, 25 August 2005, No. [AS.sup.5]-375/2005).
5. The court of the first instance makes orders on separate issues
that are not decided on the merits during the proceedings. The court
makes orders in the conference room. The orders are signed by all judges
who participated in the hearing (LAP, Art. 105). The decision in the
case heard on the merits is rendered by the administrative court in the
conference room by a majority vote of the judges. Where oral hearing of
the case is held, after the closing statements by the participants in
the proceedings the court retires to the conference room to adopt the
decision or make an order. Having adopted the decision or made an order,
the court returns to the courtroom and the chairman of the chamber or
the judge rapporteur reads out the introduction and substantive
provisions of the decision or order and briefly orally presents the
motives of the decision or order. By way of exception, having regard to
the complexity and scope of the case, the chamber of judges hearing the
case on appeal may, by virtue of a motivated order, defer the adopting
and pronouncement of the decision or order for not longer than a ten-day
period. The decision or order, the adopting and pronouncement whereof
was deferred, may be pronounced by one of the judges who heard the case,
in the absence of other judges of the chamber (LAP, Art. 139). Upon
hearing the case, the administrative court adopts one of the following
decisions:
--to reject the complaint/petition as unfounded;
--to meet the complaint/petition and revoke the contested act (part
thereof) or to obligate the appropriate entity of administration to
remedy the committed violation or carry out other orders of the court;
--to meet the complaint/petition and to obligate the entity of
municipal administration to implement the law, the Government resolution
or another legal act accordingly;
--to meet the complaint and settle the dispute in any other manner
provided for by law;
--to meet the complaint/petition and to award damages caused by
unlawful acts of entities of public administration (Civil Code, Art.
6.271; LAP, Art. 88) (Lietuvos Respublikos Civilinis kodeksas).
In the reviewed case, RAC accepted the complaint of the plaintiffs
on 28 July 2005 and held its first session on 24 October 2005. On 3
November 2005 (10 days after the first session) RAC pronounced its
decision to reject the complaint (RAC decision in the administrative
case, 3 November 2005, No. 1-1874-18/05; see Fig. 1).
6. Hearing of a case in a court of appeal. To ensure expedience of
the proceedings, protect the interests of the prevailing party and
ensure definite relations between the parties, the law sets a time limit
for the party dissatisfied with the court decision, or another person
taking part in the proceedings, to execute its right of appeal. The
decisions of RAC as a court of first instance can be appealed against to
SACL within fourteen days upon pronouncement of the decision (LAP, Art.
127). An appeal hearing is similar to the court proceedings in a court
of first instance. Having heard the case, the court of appeal has a
right:
--uphold the decision of the court of first instance and reject the
appeal;
--reverse the decision of the court of first instance and adopt a
new decision;
--amend the decision of the court of first instance;
--reverse the decision of the court of first instance and dismiss
the case or leave the appeal unconsidered;
--reverse the decision of the court of first instance fully or in
part and refer the case to the court of first instance for holding a de
novo hearing (see Fig. 1).
The case specified in point 2 means the court makes a decision;
other points are instances of a motivated court order (LAP, Art. 140).
Having reversed the challenged court decision, the court of appeal has a
right to refer the case to the court of first instance for de novo
hearing if:
--a large amount of new evidence has to be collected in order to
disclose the circumstances of the case;
--not all claims have been investigated by the court of first
instance (LAP, Art. 141).
The decision, ruling or order of the appellate court becomes
effective on the day it is made and is not subject to appeal by
cassation (LAP). The person who has filed an appeal is entitled to
withdraw the appeal before the closing statements. A written petition by
the appellant whereby the appeal is withdrawn is attached to the case
file while the oral statement will be recorded in the minutes of the
court hearing and signed by the appellant. The court terminates the
appeal proceedings by virtue of an order, unless the decision has been
appealed against by other persons. The court notifies other participants
in the appeal proceedings of the withdrawal of the appeal. The person
who withdraws the appeal has no right to file the appeal de novo (LAP,
Art. 132).
On 8 November 2005, five days after pronouncement of the RAC
decision (less than 14 days), the plaintiffs filed an appeal to the
SACL. On 15 February 2006, the first session in the court of appeal was
held. On 21 February 2006 (six days after the first session in the court
of appeal), the ruling of SACL satisfied part of the plaintiffs'
complaint: the decision of Vilnius RAC pronounced on 3 November 2005 was
reversed and the case referred to the same court for holding de novo
hearing (SACL ruling in the administrative case, 21 February 2006, No.
[A.sup.7]-850-06; see Fig. 1).
On 29 May 2006 RAC held its second session. On 8 June 2006 (10 days
after the second session) RAC pronounced its decision to dismiss the
part of the administrative case dealing with the demand of the
plaintiffs to revoke the order No. 30-1849 "On Approval of the
Detailed Plan of a Territory in Vilnius" issued by the director of
the Administration of Vilnius City Municipality on 19 November 2004 and
to reject the other part of the complaint (RAC ruling in the
administrative case, 8 June 2006, No. 1-1479-19/06; see Fig. 1).
On 19 June 2006, 11 days after pronouncement of the RAC decision
(less than 14 days), the plaintiffs filed an appeal to the SACL. On 16
January 2007, the court of appeal gathered for its second session. On 26
January 2007 (10 days after the second session in the court of appeal),
SACL passed its resolution satisfying part of the plaintiffs'
complaint: the decision of Vilnius RAC pronounced on 8 June 2006 was
reversed and the case referred to the court of first instance for
holding de novo hearing (SACL ruling in the administrative case, 26
January 2007, No. [A.sup.14]-110-07; see Fig. 1).
7. It is not always possible to hear a case on the merits and adopt
a court decision during the first and only session, although the court
makes all efforts to hear a case in one session if it does not translate
into improper case hearing. But it is complicated, and sometimes
impossible, even with proper preparation for judicial hearing, although
this stage attempts to ensure hearing the case on merits during the
first court session. Unexpected impediments often emerge and the
judicial hearing takes one, two, three and sometimes even ten or more
sessions. The chairman or judge of the court who by virtue of an order
recognised the appeal/petition to be receivable, decides, as necessary,
on the summoning of specialists or on the conduct of an expert
examination. Specialists are invited where special knowledge is required
in the court in the course of the investigation of the case for
examining and evaluating documents, articles or actions. The
explanations of the specialist are recorded in a separate document and
signed by the specialist or recorded in the minutes of the court
hearing. In the latter case the specialist has the right of access to
the minutes and is entitled to present his comments in writing under his
signature (LAP, Art. 61). If questions arise in the administrative case
that require special knowledge in the area of science, art, technology
and crafts, the court or the judge appoints an expert or charges an
appropriate expert institution to carry out the expert examination. The
questions, on which the opinion of an expert is requested may be put to
the court by each participant in the proceedings, however, the questions
will be finally determined by the court or the judge. The expert's
opinion is presented in writing in the report of the expert examination.
Where there are several experts appointed to the case, their joint
opinion is signed by those of them who approve the opinion. The experts
who disagree with them draw up their opinion separately. The
expert's opinion is not binding on the court. However, the court
must motivate its disagreement with the expert's opinion (LAP, Art.
62).
On 14 May 2007 RAC held its third session. On 24 May 2007 (10 days
after the third session) RAC pronounced its decision to hear the case on
the merits de novo. All persons (natural and legal) with ownership
rights to any individual properties (apartments, premises) in the
residential house in Vilnius were invited to take part in the case. The
case hearing was postponed until 2 July 2007. The State Enterprise
Centre of Registers was charged with a duty to provide the court with
data about all persons with ownership rights to individual properties
(apartments, premises) in the said residential house by 8 June 2007. The
court decided to summon a fire safety professional to the court session.
On 2 July 2007, RAC held its fourth session. On 12 July 2007 (10 days
after the fourth session), RAC pronounced its decision to reject the
plaintiffs' complaint as ungrounded (RAC ruling in the
administrative case, 24 May 2007, No. I-6027-14/07; RAC ruling in the
administrative case, 12 July 2007, No. I-6027-14/07, see Fig. 1).
8. Appeals can be filed either directly with the appellate court or
through the court the decision, ruling or order whereof is appealed
against. Having received the appeal, the appellate court compels the
presentation of the administrative case file and determines the issue of
admissibility of the appeal. As necessary, the appellate court may refer
the issue of admissibility of appeal to the court of the first instance
the decision, ruling or order whereof is appealed from (LAP, Art. 129).
All parties to the proceedings are entitled to file an appeal. Claims
that were not filed when the case was heard at the court of the first
instance are not allowable in the appeal. Claims that are inextricably
connected to the filed claims are not deemed to be new claims (LAP, Art.
130). While hearing the case on appeal, the court reviews the legality
and validity of both the contested and uncontested parts of the decision
as well as the legality and validity of the decision in respect of the
persons who did not file the appeal. The court is not bound by the
arguments of the appeal and must review the case in full (LAP, Art. 136)
On 19 July 2007, seven days after pronouncement of the RAC decision
(less than 14 days), the plaintiffs filed an appeal to the SACL. On 16
April 2008 the court of appeal held its third session. On 28 April 2008
(10 days after the third session in the court of appeal) SACL pronounced
its ruling upholding the decision of Vilnius RAC pronounced on 12 July
2007 and rejecting the plaintiffs' appeal. This ruling was not
subject to appeal (SACL ruling in the administrative case, 28 April
2008, No. A-438-679/2008; see Fig. 1).
9. The prevailing party to the proceedings is entitled to recover
costs from the non-prevailing adverse party (LAP, Art. 44). The party
interested in the recovery of costs files with the court a written
petition with the calculation and substantiation of the costs incurred.
Petitions for the recovery of costs that have not been filed with the
court by the termination of the hearing of the case on the merits must
be filed with the court within 14 days after the coming into effect of
the decision. The court hears the petitions filed with the court before
the termination of the hearing of the case on the merits by adopting a
decision on the administrative case. In other cases, the court as a rule
disposes of the petition for the recovery of costs by making an order in
a written proceeding. The order made by the court of the first instance
on the recovery of costs may be appealed to the Supreme Administrative
Court of Lithuania within seven days from its pronouncement (LAP, Art.
45)
On 20 May 2008, Vilnius RAC pronounced its ruling to satisfy part
of the request by the third party, the 690th association of residential
construction, to recover the costs and awarded the 690th association of
residential construction the amount of LTL 9,500 to cover representation
costs, for which the plaintiffs were jointly and severally liable (RAC
ruling in the administrative case, 20 May 2008, No. I-6027-14/2007; see
Fig. 1). The court in this case did not award to the defendant loss
recovery from the plaintiffs for the suspended construction (the
provisional measures were effective for 28 days).
Conclusions
1. A successful implementation of a construction investment project
demands for determining and sorting out all potential problems related
to stakeholder groups as early as the procedure of detailed territorial
planning. Open, patient attempts to determine the needs of the public
concerned are necessary. An open dialogue requires collaboration and
sometimes negotiations. Thus, the disputing parties must accept and
understand different, often opposite, needs and interests and search for
possible solutions through joint efforts. In the case analysed here, the
public concerned was not informed about the approval of the detailed
plan and the issuing of the building permit, which means the investor
failed to consider the interests of the public concerned and lost any
chance to resolve the dispute out of court.
2. Handling of disputes related to the infringement of rights of
the public concerned might lead, and actually do lead, to huge losses
suffered by both the investors and the public concerned. It happens
because such disputes usually take lengthy periods for resolving. In the
case analysed here, the litigation took three years. It is not always
possible to hear a case on the merits and adopt a court decision during
the first and only session, although the court makes all efforts to hear
a case in one session. But it is complicated, and sometimes impossible,
even with proper preparation for judicial hearing. Unexpected
impediments often emerge and the judicial hearing takes one, two, three
and sometimes even ten or more sessions. A case in point is the conflict
analysed here, which took five sessions in the court of first instance
and four sessions in the court of appeal, with a total of nine sessions.
Thus, the plaintiffs were obliged to pay to their lawyers for three
years and, on top of that, to reimburse LTL 9,500 to the defendant of
lawyer costs as the non-prevailing party; they were lucky not to be
liable for the reimbursement of about LTL 50,000 for the provisional
measures. Also, no expert examinations were required. The investor,
although completed the project, was forced to reduce the height of the
new residential building with a considerable drop in expected profits.
The construction was suspended for a month, but the project was
implemented before the litigation was over and the building failed to
receive the certificate of occupancy for a long time.
3. The defence of infringed rights in administrative courts raises
issues with application of provision measures. On one hand, failure to
suspend construction may impede the enforcement of the court decision,
or render the decision unenforceable, when the litigation (which may
take several years) is over. On the other hand, suspended construction
may translate into enormous financial losses to the investor and failure
to complete the construction investment project. Besides, should the
defendant prevail in the litigation, the entity to reimburse the loss is
unclear. Judicial practise has seen cases when the non-prevailing party,
the public concerned, had to reimburse the defendant any loss incurred
due to the suspension of construction. It may be an unbearable burden to
the public concerned and such scenario restricts the right of the public
concerned to defend its allegedly infringed rights. This issue is yet to
be finally resolved in judicial practice.
4. Based on the research, a conceptual model was crafted to enable
analysis of formal model behaviour in future studies and to build up a
complex system which would facilitate any construction project to plan
and apply preventive measures mitigating the risk of a judicial dispute
as early as the first project planning stage.
Caption: Fig. 1. Defence of infringed rights in an administrative
court, an actual case (diagram compiled by the authors)
Caption: Fig. 2. Defence of infringed rights in an administrative
court, an actual case (diagram compiled by the authors)
doi:10.3846/20294913.2013.817489
References
Bao, H.; Yee-Loong Chong, A.; Wang, H., Wang, L., Huang, Y. 2012.
Qantitative decision making in land banking: a Monte Carlo simulation
for China's real estate developers, International Journal of
Strategic Property Management 16(4): 355-369.
http://dx.doi.org/10.3846/1648715X.2012.735272
Burinskiene, M.; Rudzkiene, V.; Venckauskaite, J. 2011. Effects of
quality of life on the price of real estate in Vilnius city,
International Journal of Strategic Property Management 15(3): 295-311.
http://dx.doi.org/10.3846/1648715X.2011.617857
Chamodrakas, I.; Leftheriotis, I; Matakos, D. 2011. In-depth
analysis and simulation study of an innovative fuzzy approach for
ranking alternatives in multiple attribute decision making problems
based on TOPSIS, Applied Soft Computing 11(1): 900-907.
http://dx.doi.org/10.1016/j.asoc.2010.01.010
Chou, J-S.; Lin, C. 2013. Predicting disputes in public-private
partnership projects: classification and ensemble models, Journal of
Computing in Civil Engineering 27(1): 51-60.
http://dx.doi.org/10.1061/(ASCE)CP.1943-5487.0000197
Desierto, D.A. 2013. Conflict of Treaties, Interpretation, and
Decision-Making on Human Rights and Investment During Economic Crises,
Transnational Dispute Management Journal 1. http://www.
transnational-dispute-management.com/article.asp?key=1930
Erdis, E. 2013. The effect of current public procurement law on
duration and cost of construction projects in Turkey, Journal of Civil
Engineering and Management 19(1): 121-135.
http://dx.doi.org/10.3846/13923730.2012.746238
Kersuliene, V.; Zavadskas, E. K.; Turskis, Z. 2010. Selection of
rational dispute resolution method by applying new step-wise weight
assessment ratio analysis (SWARA), Journal of Business Economics and
Management 11(2): 243-258. http://dx.doi.org/10.3846/jbem.2010.12
Koziratskiy, J. L.; Koziratskiy, A. J.; Grevtsev, A. I.; Parinov,
M. L.; Kushchev, S. S. 2008. Kompiuternoe modelirovanie konflikta
slozhnykh sistem [Computerised modelling ofa conflict in complex
systems], Vestnik VGU. Seriia: Sistemnyy analiz i informatsionnye
tekhnologii 2.
Lakis, J. 2008. Konfliktu sprendimas ir valdymas [Conflict
Resolution and Management]. Vilnius: Mykolo Romerio universitetas.
Lietuvos Respublikos administraciniu bylu teisenos istatymas [The
Law on Administrative Proceedings of the Republic of Lithuania] (in
Lithuanian).
Lietuvos Respublikos civilinio proceso kodeksas. [Code of Civil
Procedure of the Republic of Lithuania] (in Lithuanian).
Lietuvos Respublikos Civilinis kodeksas. [The Civil Code of the
Republic of Lithuania] (in Lithuanian).
Lietuvos Respublikos teritoriju planavimo istatymas [The Law on
Territorial Planning of the Republic of Lithuania] (in Lithuanian).
Lietuvos Respublikos Visuomenes informavimo ir dalyvavimo
teritoriju planavimo procese nuostatai [Regulations on Informing the
General Public and Public Participation in the Territorial Planning
Procedures of the Republic of Lithuania] (in Lithuanian).
Lin, M.-C.; Tserng, H. P.; Ho, S.-P.; Yuong, D.-L. 2011. Developing
a construction-duration model based on a historical dataset for building
project, Journal of Civil Engineering and Management 17(4): 529-539.
http://dx.doi.org/10.3846/13923730.2011.625641
Mitkus, S.; Sostak, O. R. 2008. Modelling the process for defence
of third party rights infringed while implementing construction
investment projects, Technological and Economic Development of Economy
14(2): 208-223. http://dx.doi.org/10.3846/1392-8619.2008.14.208-223
Mitkus, S.; Sostak, O. R. 2009. Preservation of healthy and
harmonious residential and work environment during urban development,
International Journal of Strategic Property Management 13(4): 339-357.
http://dx.doi.org/10.3846/1648-715X.2009.13.339-357
Park, M.; Chu, Y.; Lee, H.-S.; Kim, W. 2009. Evaluation methods for
construction projects, Journal of Civil Engineering and Management
15(4): 349-359. http://dx.doi.org/10.3846/1392-3730.2009.15.349-359
Pinter, U; Psunder, I. 2013. Evaluating construction project
success with use of the M-TOPSIS method, Journal of Civil Engineering
and Management 19(1): 16-23.
http://dx.doi.org/10.3846/13923730.2012.734849
Sostak, O. R.; Vakriniene, S. 2011. Mathematical modelling ofthe
dispute proceedings between investors and third parties on allegedly
violated third-party rights, Journal of Civil Engineering and Management
17(1): 126-136. http://dx.doi.org/10.3846/13923730.2011.560628
Statybos Techninis Reglamentas STR 2.02.01:2004 "Gyvenamieji
pastatai" [Construction Technical Regulation STR 2.02.01:2004
"Residential Buildings" (in Lithuanian).
Tettey, T.; Marwala, T. 2007. Conflict modelling and knowledge
extraction using computational intelligence methods, in 11th
International Conference of Intelligent Engineering Systems, 29 June-1
July, 2007, Budapest, Hungary, 161-166.
Urbanaviciene, V.; Kaklauskas, A.; Zavadskas, E. K. 2009. The
conceptual model of constructional and real estate negotiation,
International Journal of Strategic Property Management 13(1): 53-70.
http://dx.doi.org/10.3846/1648-715X.2009.13.53-70
Wang, Y.-R.; Yu, C.-Y.; Chan, H.-H. 2012. International predicting
construction cost and schedule success using artificial neutral networks
ensemble and support vector machines classification models,
International Journal of Project Management 30(4): 470-478.
http://dx.doi.org/10.1016/j.ijproman.2011.09.002
Yang, J.; Shen, G. Q.; Ho, M.; Drew, D. S.; Chan, A. P. C. 2009.
Exploring critical success factors for stakeholder management in
construction projects, Journal of Civil Engineering and Management
15(4): 337-348. http://dx.doi.org/10.3846/1392-3730.2009.15.337-348
Yeh, K.-C.; Tsai, M.--H., Kang, S.-C. 2012. On-site building
information retrieval by using projection-based augmented reality,
Journal of Computing in Civil Engineering 26(3): 342-355.
http://dx.doi.org/10.1061/(ASCE)CP.1943-5487.0000156
Zavadskas, E. K.; Kaklauskas, A. 2008. Model for Lithuanian
construction industry development, Transformations in Business &
Economics 7(1): 152-168.
Zavadskas, E. K.; Kaklauskas, A.; Banaitis, A. 2010b. Application
of e-technologies for regional development: the case of Vilnius city,
Journal of Business Economics and Management 11(3): 415-427.
http://dx.doi.org/10.3846/jbem.2010.20
Zavadskas, E. K.; Turskis, Z. 2011. Multiple criteria decision
making (MCDM) methods in economics: an overview, Technological and
Economic Development of Economy 17(2): 397-427.
http://dx.doi.org/10.3846/20294913.2011.593291
Zavadskas, E. K.; Turskis, Z.; Tamosaitiene, J. 2010a. Risk
assessment of construction projects, Journal of Civil Engineering and
Management 16(1): 33-46. http://dx.doi.org/10.3846/jcem.2010.03
Olga Regina SOSTAK, Daiva MAKUTENIENE
Vilnius Gediminas Technical University, Sauletekio al. 11, LT-10223
Vilnius, Lithuania
Corresponding author Olga Regina Sostak
E-mail:
[email protected]
Received 19 December 2011; accepted 31 December 2012
Olga Regina SOSTAK. Doctor. Faculty of Fundamental Sciences,
Vilnius Gediminas Technical University (VGTU), Sauletekio al. 11, 10223
Vilnius, Lithuania. Master of Civil engineering (2006, Vilnius Gediminas
Technical University), Doctor of science (2011, Vilnius Gediminas
Technical University). Research interests: land planning, construction
investment, decision making, conflict resolution.
Daiva MAKUTENIENE. Doctor, Associate Professor in the Faculty of
Fundamental Sciences, Vilnius Gediminas Technical University (VGTU).
Sauletekio al. 11, 10223 Vilnius, Lithuania. Architect (1984, Vilnius
Civil Engineering Institute), Master of Informatics engineering (1997,
Vilnius Technical University), Doctor of science (2001, Vilnius
Gediminas Technical University). Research interests: computer aided
design, intelligent design in computer-aided civil engineering,
information visualization technologies.
Table 1. Investor's losses due to the suspended construction
The name of the costs Calculations, LTL Total,
LTL
Daily maintenance costs of the construction site:
Object's security: 48 hours x 9.5 = 456 +
VAT = 538.08
Facilities for rest, 16.44 + VAT = 19.40
etc.:
Bio toilet: 5.74 + VAT = 6.77
Electricity costs: 50 kW x 0.264 = 15.84 +
VAT = 18.69
Land lease: 429.06 + VAT = 506.29
Costs of auxiliary LTL 1,048 / 31
staff: days = 33.80
1,123.03
Daily costs for the staff of the association of
residential construction hired specifically for
this object:
Engineer for technical LTL 2,059.84 / 31 days = 66.45
supervision of
construction:
Project manager: LTL 1,574.40 / 31 days = 50.79
117.24
Amounts invested by the association of residential
construction (per day):
LTL 815,000 x 6 % / 365
days = 133.97
133.97
Daily costs for staff and workers, working on
the object, during the downtime:
LTL 41,909.64 / 31
days = 1,351.92
1,351.92
The maintenance costs of the object per one calendar
day amount 2,726.16