首页    期刊浏览 2024年12月12日 星期四
登录注册

文章基本信息

  • 标题:Factors affecting the performance of construction projects in the Gaza Strip/Veiksniai, lemiantys statybos projektu igyvendinima Gazos Ruoze.
  • 作者:Enshassi, Adnan ; Mohamed, Sherif ; Abushaban, Saleh
  • 期刊名称:Journal of Civil Engineering and Management
  • 印刷版ISSN:1392-3730
  • 出版年度:2009
  • 期号:September
  • 语种:English
  • 出版社:Vilnius Gediminas Technical University
  • 摘要:Throughout the world, the business environment within which construction organizations operate continues to change rapidly. Organizations failing to adapt and respond to the complexity of the new environment tend to experience survival problems (Lee et al. 2001). With increasing higher users' requirements, environmental awareness and limited resources on one side, and high competition for construction business marketplace on the other side, contractors have to be capable of continuously improving their performance (Samson and Lema 2005).
  • 关键词:Construction management;Industrial project management;Project management

Factors affecting the performance of construction projects in the Gaza Strip/Veiksniai, lemiantys statybos projektu igyvendinima Gazos Ruoze.


Enshassi, Adnan ; Mohamed, Sherif ; Abushaban, Saleh 等


1. Introduction

Throughout the world, the business environment within which construction organizations operate continues to change rapidly. Organizations failing to adapt and respond to the complexity of the new environment tend to experience survival problems (Lee et al. 2001). With increasing higher users' requirements, environmental awareness and limited resources on one side, and high competition for construction business marketplace on the other side, contractors have to be capable of continuously improving their performance (Samson and Lema 2005).

A number of studies have been conducted to examine factors impacting on project performance in developing countries. Faridi and El-Sayegh (2006) reported that shortage of skills of manpower, poor supervision and poor site management, unsuitable leadership, shortage and breakdown of equipment among others contribute to construction delays in the United Arab Emirates. Hanson et al. (2003) examined causes of client dissatisfaction in the South African building industry and found that conflict, poor workmanship and incompetence of contractors to be among the factors which would negatively impact on project performance. Mbachu and Nkando (2007) established that quality and attitude to service is one of the key factors constraining successful project delivery in South Africa. The performance of contractors in Zambia is apparently below expectation; it is not uncommon to learn of local projects that have not been completed or significantly delayed. This poor performance of many local contractors has huge implications in terms of their competitiveness (Zulu and Chileshe 2008).

The construction industry is complex in its nature because it comprises large numbers of parties as owners (clients), contractors, consultants, stakeholders, and regulators. Despite this complexity, the industry plays a major role in the development and achievement of society's goals. It is one of the largest industries and contributes to about 10% of the gross national product (GNP) in industrialized countries (Navon 2005). Palestine is no exception; the local construction industry is one of the main economic engine sectors, supporting the Palestinian national economy. However, many local construction projects report poor performance due to many evidential project-specific causes such as: unavailability of materials; excessive amendments of design and drawings; poor coordination among participants, ineffective monitoring and feedback, and lack of project leadership skills (UNRWA 2006). The ever-important macro-level political and economic factors have also been related to poor projects performance (UNRWA 2006 & 2007).

Project performance can be measured and evaluated using a large number of performance indicators that could be related to various dimensions (groups) such as time, cost, quality, client satisfaction, client changes, business performance, health and safety (Cheung et al. 2004; DETR 2000). Time, cost and quality are, however, the 3 predominant performance evaluation dimensions. Another interesting way of evaluating project performance is through 2 common sets of indicators (Pheng and Chuan 2006). The first set is related to the owner, users, stakeholders, and the general public; the groups of people, who will look at project performance from the macro viewpoint. The second set comprises the developer and the contractor; the groups of people who will look at project performance from the micro viewpoint.

Generally, performance dimensions may have one or more indicators, and could be influenced by various project characteristics. For example, Dissanayaka and Kumaraswamy (1999) found that project time and cost performances get influenced by project characteristics, procurement system, project team performance, client representation's characteristics, contractor characteristics, design team characteristics, and external conditions. Similarly, Iyer and Jha (2005) identified many factors as having influence on project cost performance, these include: project manager's competence, top management support, project manager's coordinating and leadership skills, monitoring and feedback by the participants, decision-making, coordination among project participants, owners' competence, social condition, economic condition, and climatic condition. Coordination among project participants, however, was identified as the most significant of all the factors, having maximum influence on cost performance. Interestingly, Love et al. (2005) examined project time-cost performance relationship, and their results indicate that cost is a poor predictor of time performance. Elyamany et al. (2007) introduced a performance evaluation model for construction companies in order to provide a proper tool for the company's owners, shareholders and funding agencies to evaluate the performance of construction companies in Egypt.

The above examples demonstrate that there is a plethora of factors with the potential to affect the different dimensions of project performance. As such, this paper builds upon the vast amount of published studies (Cheung et al. 2004; DETR 2000; Karim and Marosszeky 1999; Dissanayaka and Kumaraswamy 1999; Ofori et al. 2004; Samson and Lema 2002; Iyer and Jha 2005; Love et al. 2005; UNRWA 2006 & 2007; Ugwu and Haupt 2007; Enshassi et al. 2007; Alinaitwe et al. 2007) in order to identify a comprehensive list of factors affecting the performance of construction projects. Following this, the paper reports on the findings of a survey targeting project owners, consultants and contractors, in an attempt to shed some light on how each project party perceives the relative importance of these factors. Finally, the paper formulates a number of recommendations in order to bridge the gap between the different perceptions thus improving the level of project performance in the Gaza Strip.

2. Methodology

A questionnaire survey was used to elicit the attitude of owners, consultants, and contractors towards the factors affecting the performance of construction projects in the Gaza Strip. Questionnaires were sent to randomly selected owners, consultants, and contractors. Consultants were identified from the listings of consultants association; the target populations of contractors were companies registered with Palestinian contractors union. 120 questionnaires were distributed as follows: 25 to owners; 35 to consultants; and 60 to contractors. 88 were received (response rate of 73%) as follows: 17 (70%) from owners; 25 (72%) from consultants; and 46 (77%) from contractors as respondents. The respondents were asked to indicate, based on their local experience the level of importance of each one of the identified 63 factors of performance on a five-point Likert scale as: not important, slightly, moderately, very, and extremely important. The questionnaire has been validated by the criterion-related reliability test which measures the correlation coefficient between the factors affecting the performance of construction projects in one field and the whole field, and structure validity test (Spearman test).

The respondents were experienced construction project managers, site engineers/office engineers, and organizations' managers (with average experience of 20 years in the construction industry). 63 factors believed to affect project performance were considered in this study and were listed under 10 groups based on the literature reviewed (Okuwoga 1998; Dissanayaka and Kumaraswamy 1999; Reichelt and Lynies 1999; Karim and Marosszeky 1999; Brown and Adams 2000; DETR 2000; Lehtonen 2001; Chan 2001; Samson and Lema 2002; Kuprenas 2003; Cheung et al. 2004; Iyer and Jha 2005; Navon 2005; Love et al. 2005; Ugwa and Haupt 2007). The performance factors were summarized and collected according to previous studies and others as recommended by local experts. The main groups considered in this paper are: time, quality, productivity, client satisfaction, regular and community satisfaction, people, health and safety, innovation and learning, and environment.

The relative importance index method (RII) was used herein to determine owners', consultants', and contractors' perceptions of the relative importance of the identified performance factors. The RII was computed as (Cheung et al. 2004; Iyer and Jha 2005; Ugwu and Haupt 2007):

RII = [summation]W/(A x N),

where W is the weight given to each factor by the respondents and ranges from 1 to 5; A--the highest weight = 5; N--the total number of respondents.

To determine whether there is a significant degree of agreement among the 3 groups of respondents (owners, contractors and consultants), Kendall's coefficient of concordance is used as a measure of agreement among raters. Kendall's coefficient of concordance indicates the degree of agreement on a zero to one scale, and is computed by the following equation (Moore et al. 2003; Frimpong et al. 2003):

W = 12U - (3[m.sup.2]n[(n - 1).sup.2])/([m.sup.2]n(n - 1)),

where:

U = [n.summation over (i=1)] [([summation] R).sup.2],

n--number of factors; m--number of groups; j--the factors 1, 2, ..., N.

Null hypothesis: H0: There is insignificant degree of agreement among owners, contractors and consultants.

* Alternative hypothesis: H1: There is a statistically significant degree of agreement among owners, contractors and consultants.

3. Results and discussion

3.1. Factors affecting the performance of construction projects

Table 1 summarizes the computed RIIs and their ranks as perceived by the 3 responding groups.

Table 2 illustrates the top significant factors affecting the performance of construction projects. It can be inferred from this table that 3 most important factors according to the perception of owner, consultant, and contractor are: average delay because of closures leading to materials shortage, unavailability of resources, and leadership skills for project manager.

According to owners, consultants, and contractors, it seems that the average delay because of closures leading to materials shortage was the most important performance factor as it has the first rank among all factors with relative index (RII) = 0.941 for owners, 0.896 for consultants, and 0.943 for contractors. This agreement between all target groups is traced to the difficult political situation from which the Gaza Strip suffers. Local construction projects suffer from a number of problems because of closures and materials shortage. These problems can be considered as an obstacle for time performance of projects.

As indicated in Table 3, the quality group has been ranked by the owners' respondents in the second position with RII equal to 0.792. It has been ranked by the consultants' respondents in the first position with RII equal to 0.787 and has been ranked by the contractors' respondents in the third position with RII equal to 0.794. This group is the most important one for consultants because consultants are interested in clients and technical factors. Consultants observed that quality of equipment and raw materials in project and availability of personnel with high qualifications strongly affect the quality performance of a project.

The people group has been ranked by the owners' respondents in the third position with RII equal to 0.759. It has been ranked by the consultants' respondents in the 7th position with RII equal to 0.712 and has been ranked by the contractors' respondents in the first position with RII equal to 0.812. It is not surprising to observe that the people group is the most important one for contractors because contractors remarked on competence development between employees and belonging to work strongly affect productivity, cost, and time performance of contractors.

The innovation and learning group has been ranked by the owners' respondents in the first position with RII equal to 0.821. It has been ranked by the consultants' respondents in the 4th position with RII equal to 0.744 and has been ranked by the contractors' respondents in the second position with RII equal to 0.804. This group is the most important one for owners because owners remarked that learning from experience and training the human resources with skills demanded by the project strongly affect project performance.

The following is a brief discussion of the ranking of factors in groups, as shown in Table 1.

3.1.1. Group one: cost factors

The relative importance index (RII) and rank of cost factors are summarized in Table 4. Escalation of material prices has been ranked by the owners' and contractors' respondents in the first position. However, this factor has been ranked by the consultants' respondents in the second position. It is observed that this factor is more important for owners and contractors because escalation of material prices affects the liquidity of owners and the profit rate of contractors. Continuous closures of roads in the Gaza Strip lead to rapid shortages of construction materials and escalation of construction material prices.

Differentiation of currency prices has been ranked by the owners' respondents in the 4th position. It has been ranked by the consultants' respondents in the 3rd position and by the contractors' respondents in the second position. It is not surprising to find out differentiation of currency prices is more important for contractors than for others because this factor affects contractors' profit rate and cost performance. The cash flow of a project has been ranked by the owners' respondents in the second position. It has been ranked by the consultants' respondents in the 4th position and by the contractors' respondents in the 3rd position. Cash flow is more important for owners and contractors than for consultants, because it can give an important evaluation for the owners' and the contractors' cost performance at any stage of project.

Material and equipment cost has been ranked by the owners' respondents in the second position, but it has been ranked by the consultants' and the contractors' respondents in the 5th position. This indicates that this factor is more important for owners than for others. Material and equipment cost is one of the project cost components that affects owners' liquidity and project budget. Our results do not align with those of Iyer and Jha (2005) and Ugwu and Haupt (2007) as materials and equipment cost rarely affect the cost performance of Indian and South African construction projects. This can be attributed to different economic and political situations.

Liquidity of organisation has been ranked by the owners' respondents in the 6th position. It has been ranked by the consultants' respondents in the first position and by the contractors' respondents in the 4th position. Consultants considered this factor as the most important one because cost performance of any project depends mainly on the organisation liquidity. Our result is in line with those of Samson and Lema (2002), as liquidity of the organisation is very important for evaluating of project budget and cost performance. However, Ugwu and Haupt (2007) are not in agreement with our results, as this factor is not important for owners and contractors while it is moderately important for consultants. This might be owing to different economic and political situations.

3.1.2. Group two: time factors

The relative importance index and rank of time factors are summarized in Table 5. According to owners, consultants, and contractors, the average delay because of closures leading to materials shortage was the most important performance factor, as it has the first rank among all factors with RII = 0.941 for owners, 0.896 for consultants, and 0.943 for contractors. This agreement between all target groups is traced to the difficult political situation from which the Gaza Strip suffers. Local construction projects suffer from complex problems because of closures leading to materials shortage. These problems can be considered as an obstacle for time performance of projects.

Unavailability of resources as planned through project duration has been ranked by the owners' respondents in the 3rd position. It has been ranked by the consultants' respondents in the 2nd position and by the contractors' respondents in the 3rd ane. This factor can be considered as important for 3 parties and scores a similar rank from all of them. This factor directly affects the project performance such as time. If resources are not available as planned through project duration, the project will suffer from the problem of time performance. Average delay in payment from owner to contractor has been ranked by the owners', consultants', and contractors' respondents in the 3rd position. This agreement between parties is traced to disputes that will happen between project parties, when the payment from owner is delayed. This will affect project performance, especially time criteria. Karim and Marosszeky (1999) are in agreement with our result, as the average delay in payment from owner to contractor affects the time performance.

Percentage of orders delivered late has been ranked by the owners' respondents in the 6th position and by the consultants' and contractors' respondents in the 4th position. This factor has the same rank for contractors and consultants and it is more important for them because it is related to contractual relationships between them. The contractor cannot implement any stage through a project without having orders from the project consultant. Planned time for project construction has been ranked by the owners' respondents in the 4th position and by the consultants' and contractors' respondents in the 5th position. This factor is more important for owners as they usually want their projects completed as early as possible.

3.1.3. Group three: quality factors

The relative importance index and rank of quality factors are summarized in Table 6. Unavailability of personnel with high experience and qualifications has been ranked by consultants' and contractors' respondents in the first position and by owners' respondents in the second one. This factor is very important for 3 parties because availability of personnel with high experience and qualifications assist them to implement their project with a professional and successful performance.

Participation of managerial levels in decision-making has been ranked by the owners', consultants', and contractors' respondents in the 4th position. This factor scored the same rank from all parties because sharing the managerial levels with decision-making will lead to better implementation and performance of a project and will satisfy the 3 parties to a greater degree. Iyer and Jha (2005) are in agreement with our results as this factor is important to 3 parties because it will improve overall performance of a construction project.

Conformance to specification has been ranked in the first position for owners, but it has been ranked in the 3rd position for both of consultants and contractors. This factor is more important for owners, as it is significant and related to client satisfaction. The owners usually seek to implement their project according to required specifications. Our results are align with those of Iyer and Jha (2005), as this factor is significant for owners because it is strongly related to client satisfaction. Quality of equipment and raw materials in a project has been ranked by the consultants' and contractors' respondents in the 2nd position and by the owners' respondents in the 3rd one. This factor is more important for consultants and contractors than for owners, as they usually want materials applied in a project to be of good quality and according to specification.

3.1.4. Group four: productivity factors

The relative importance index and rank of productivity factors are summarized in Table 7. Sequencing of work according to schedule has been ranked by owners, consultants, and contractors in the first position. This factor is the most important one for 3 parties because sequencing the work according to schedule assists them to conduct a project according to scheduled time for project completion. Our results are align with those of Samson and Lema (2002), as sequencing of work affects the productivity performance of contractors.

Management-labour relationship has been ranked by owners' and contractors' respondents in the 2nd position and by consultants' respondents in the 3rd one. This factor is considered as important for 3 parties as management-labour relationship can assist them by strong coordination and motivation between labour level and managerial level. This will lead to an improvement in productivity and performance of projects.

Number of new projects per year has been ranked by owners' and contractors' respondents in the 5th position and has been ranked by consultants' respondents in the 3rd position. This factor is considered more important for consultants. Owners and contractors considered the number of new projects/year rarely affect the performance of projects. Consultants believed that number of new projects/year affect the degree of experiences and skills learned from executed projects and that will affect the degree of project performance based on previous or current experiences.

3.1.5. Group 5: client satisfaction factors

The relative importance index and rank of client satisfaction factors are summarized in Table 8. Leadership skills for project managers have been ranked by owners', consultants', and contractors' respondents in the 1st position. This factor is the most important one for 3 parties because leadership skills for project managers affect the degree of project performance and client satisfaction. Cheung et al. (2004) observed that this factor is important for effectiveness of project performance. Our results are align with those of Cheung et al. (2004), as this factor is important for 3 parties because it is significant for effectiveness of project performance.

Number of reworks has been ranked by owners', consultants', and contractors' respondents in the 5th position. This factor has the same rank for 3 parties because number of reworks affect the relationship between them. Number of disputes between owner and project parties have been ranked by owners' respondents in the 2nd position and by consultants' and contractors' respondents in the 4th position. This factor is more important for owners because disputes between owner and project parties will affect relationships between them and the degree of client satisfaction will be affected. All of that affects the performance of project. Information coordination between owner and project parties has been ranked by the owners' and contractors' respondents in the 3rd position and by the consultants' respondents in the 2nd position.

3.1.6. Group 6: regular and community satisfaction factors

The relative importance index and rank of regular and community satisfaction factors are summarized in Table 9. Neighbours and site condition problems have been ranked by the owners' and contractors' respondents in the 1st position and by the consultants' respondents in the second one. This factor is more important for owners and contractors because it is strongly related to client satisfaction and contractors' performance.

Quality and availability of regulator documentation has been ranked by the consultants' respondents in the 1st position and by the owners' and contractors' respondents in the 2nd position. Quality and availability of regulator documentation is more important for consultants because it affects the performance of consultants and community satisfaction. This result is in line with Samson and Lema (2002), as this factor affects the contractors' performance because it affects regular and community satisfactions.

It can be understood, that there is a strong agreement between owners and contractors for ranking all regular and community satisfaction factors because they are more related to contractors' performance and client satisfaction. Generally, it can be said that 3 parties are in agreement for ranking these factors.

3.1.7. Group 7: people factors

The relative importance index and rank of people factors are summarized in Table 10.

Belonging to work it has been ranked by the owners, consultants, and contractors respondents in the first position. This factor is the most important one for 3 parties because belonging to work usually improves productivity and performance of project. Iyer and Jha (2005) are in agreement with our result as this factor is important for three parties because belonging to works improves productivity and performance of a project.

Employees' motivation has been ranked by the owners' respondents in the 2nd position. It has been ranked by the consultants' respondents in the 3rd position and by the contractors' respondents in the 4th position. This factor is less important for contractors because it is rarely that contractors motivate employees in the Gaza Strip. Iyer and Jha (2005) remarked that this factor is moderately important for contractors because of absence of motivation systems in construction projects. However, other factors are ranked as more important for one party than others, as shown previously.

3.1.8. Group 8: health and safety factors

The relative importance index and rank of health and safety factors are summarized in Table 11. Application of health and safety factors in organizations has been ranked by the consultants' and contractors' respondents in 1st position, but has been ranked by the owners' respondents in the 2nd one. However, this factor is very important for 3 parties because application of health and safety factors in construction projects will improve overall performance of such projects. This result is in line with Cheung et al. (2004), as this factor strongly affects the performance of projects because it affects the safety of employees.

Reportable accident rate in project has been ranked by the owners' respondents in the 1st position. It has been ranked by the consultants' respondents in the 3rd position and by the contractors' respondents in the 4th position. Owners considered this factor as the most important one, because reportable accident rate usually affects the safety performance and the client satisfaction degree in construction projects. Ease of access to the site (location of project) has been ranked by the owners' respondents in the 3rd position and by the consultants' and contractors' respondent in the 2nd position. This factor is more important for consultants and contractors because the access to the site is more relevant to them and affects the degree of safety for their employees.

3.1.9. Group 9: innovation and learning factors

The relative importance index and rank of innovation and learning factors are summarized in Table 12. Learning from own experience and past history has been ranked by the owners' respondents in the 1st position and by the consultants' and contractors' respondents in the 2nd position. This factor is more important for owners than for others. Owners can use their own experience and past history to improve and develop performance of their current and future projects. Samson and Lema (2002) remarked that learning from own experience and past history affects the performance of projects because it affects the innovation and learning required to construct projects.

Learning from best practice and experience of others has been ranked by the owners' respondents in the 3rd position and by the consultants' and contractors' respondents in the 1st position. Contractors and consultants considered this factor as a more important one than owners did. This is because learning from best practice and experience of others can improve and develop consultants' and contractors' performance.

Training the human resources in the skills demanded by the project has been ranked by the owners' respondents in the 2nd position. It has been ranked by the consultants' respondents in the 5th position and by the contractors' respondents in the 4th one. This factor is less important for contractors and consultants in the Gaza Strip, as they seldom train their employees in required and professional skills.

3.1.10. Group 10: environmental factors

The relative importance index and rank of environment factors are summarized in Table 13. Climate condition at the site has been ranked by the owners', consultants', and contractors' respondents in the 1st position. This factor is the most important one for them, because it affects the productivity and time performance of project. This result is not in agreement with Iyer and Jha (2005), as climate condition is not important for 3 parties. This might be because of different location, weather, and environment.

Noise level has been ranked by the owners', consultants', and contractors' respondents in the 4th position. However, for all parties a noise level is less important than other environmental factors because it is rarely an issue in the Gaza Strip. Ugwu and Haupt (2007) remarked that this factor is not important for owners and consultants but it is moderately important for contractors. Generally, noise level affects the productivity performance of construction projects.

3.2. Degree of agreement among responding groups

To determine whether there is a significant degree of agreement among the 3 groups (owners, contractors, and consultants) Kendall's coefficient of concordance is used as a measure of agreement among raters. For cost, time, quality, productivity, client satisfaction, people, innovation, and learning factors, and all groups together, the p-values (Sig.) are less than L = 0.05 (L is the level of significance), the null hypothesis, H0, is rejected and the alternative hypothesis, H1, is accepted. Therefore, it can be said that there is a significant degree of agreement among the owners, contractors and consultants regarding factors affecting the performance of construction projects in the Gaza Strip.

On the other hand, for regular and community satisfaction, health and safety, and environment factors, the p-values (Sig.) are greater than L = 0.05 (L is the level of significance), then we do not reject the null hypothesis, H0. Therefore, it can be said that there is an insufficient evidence to support the alternative hypothesis, H1. Hence, there is an insignificant degree of agreement among the owners, contractors, and consultants regarding factors affecting the performance of construction projects in the Gaza Strip.

4. Conclusions

A questionnaire-based survey was used to elicit the attitude of owners, consultants, and contractors towards factors affecting the performance of construction projects in the Gaza Strip. 120 questionnaires were distributed as follows: 25 to owners, 35 to consultants and 60 to contractors. 88 questionnaires (73%) were returned as follows: 17 from owners, 25 from consultants, and 46 from contractors as respondents. The respondents were asked to indicate the level of importance of each of the 63 factors of performance in the Gaza Strip as not important, slightly, moderately, very, and extremely important.

The results indicated that the average delay because of closures leading to materials shortage was the most important performance factor, as it has the first rank among all factors from the perspectives of owners, consultants, and contractors. This agreement between all target groups is traced to the difficult political situation from which the Gaza Strip suffers. The most important factors agreed by the owners, consultants, and contractors as the main factors affecting the performance of construction projects in the Gaza Strip were: escalation of material prices, availability of resources as planned through project duration, average delay because of closures leading to materials shortage, availability of personnel with a high experience and qualifications, quality of equipment and raw materials in project, and leadership skills for project managers.

Kendall's coefficient of concordance is used to determine, whether there is a degree of agreement among performance factors for owners, consultants, and contractors. For cost, time, quality, productivity, client satisfaction, people, innovation, and learning factors, and all groups together, there is a significant degree of agreement among the owners, consultants, and contractors. This is because all owners, consultants, and contractors are concerned with these groups. On the other hand, for regular and community satisfaction, health and safety, and environment factors, there is an insignificant degree of agreement among the owners, consultants, and contractors. This is because contractors are concerned with these factors more or less than owners and consultants. The owners and consultants considered the client and technical factors to be more important than the operational ones.

The authors recommended to develop human resources in the construction industry through proper and continuous training programs about construction projects performance. These programs can update participants' knowledge and can assist them to be more familiar with project management techniques and processes. Owners are encouraged to facilitate payment to contractors in order to overcome delay, disputes, and claims. All managerial levels should participate in sensitive and important decision-making. Continuous coordination and relationship between project participants are required through project life cycle for solving problems and developing project performance.

Consultants should be more interested in design cost by using multi-criteria analysis and choosing the most economical criteria in order to improve their performance and to increase owners' satisfaction. In addition, consultants are urged to facilitate and expedite orders delivered to contractors to obtain better time performance and to minimize disputes and claims. Contractors should not increase the number of projects that cannot be performed successfully. In addition, contractors should consider political and business environment risks in their cost estimation for overcoming delay because of closures leading to materials shortages. There should be adequate contingency allowances in order to cover increases in material cost. Proper motivation and safety systems should be established for improving the productivity performance of construction projects in the Gaza Strip. Greater application of health and safety factors are necessary to overcome problems of safety performance.

Contractors are counseled to minimize waste rates through project implementation for improving cost. They should be more interested in conformance to project specification to overcome disputes, time, and cost performance problems. Quality materials should be of a greater interest for contractors in order to improve cost, time, and quality performance. This can be done by applying quality training and meetings that are necessary for performing an improvement. Contractors are urged to be more interested in sequencing of work according to schedule. In addition, contractors should have a cost engineer in their projects to successfully control costs.

Received 6 Nov 2008; accepted 3 Apr 2009

References

Alinaitwe, H. M.; Mwakali, J. A.; Hansson, B. 2007. Factors affecting the productivity of building craftsmen studies of Uganda, Journal of Civil Engineering and Management 13(3): 169-176.

Brown, A.; Adams, J. 2000. Measuring the effect of project management on construction outputs: a new approach, International Journal of Project Management 18: 327-335.

Cavalieri, S.; Terzi, S.; Macchi, M. 2007. A benchmarking service for the evaluation and comparison of scheduling techniques, Computers in Industry 58: 656-666. doi:10.1016/j.compind.2007.05.004

Chan, A. P. C. 2001. Time-cost relationship of public sector projects in Malaysia, International Journal of Project Management 19: 223-229. doi :10.1016/50263-7863 (99)00072-1

Chan, A. P. C.; Chan, D. W. M. 2004. Developing a benchmark model for project construction time performance in Hong Kong, Building and Environment 39: 339-349. doi:10.1016/j.buildenv.2003.08.012

Chan, D. W. M.; Kumaraswamy, M. M. 2002. Compressing construction durations: lessons learned from Hong Kong building projects, International Journal of Project Management 20: 23-35. doi:10.1016/50263-7863(00)00032-6

Cheung, S.-O.; Suen, H. C. H.; Cheung, K. K. W. 2004. PPMS: a Web-based construction project performance monitoring system, Automation in Construction 13: 361-376. doi:10.1016/j.autcon.2003.12.001

Department of the Environment, Transport and the Regions (DETR), (2000), KPI Report for the Minister for Construction by the KPI Working Group, January 2000.

Dissanayaka, S. M.; Kumaraswamy, M. M. 1999. Comparing contributors to time and cost performance in building projects, Building and Environment 34: 31-42. doi:10.1016/50360-1323(97)00068-1

Elyamany, A.; Ismail, B.; Zayed, T. 2007. Performance evaluating model for construction companies: Egyptian case study, Journal of Construction Engineering and Management 133(8): 574-581. doi:10.1061 /(ASCE)073 3-9364(2007)133:8(574)

Enshassi, A.; Mohamed, S.; Abu Mustafa, Z.; Mayer, P. E. 2007. Factors affecting labor productivity in building projects in the Gaza Strip, Journal of Civil Engineering and Management 13(4): 245-254.

Faridi, A.; El-Sayegh, S. 2006. Significant factors causing delay in the UAE construction industry, Construction Management and Economics 24(11): 1167-1176. doi:10.1080/01446190600827033

Frimpong Yaw; Oluwoye, J.; Crawford, L. 2003. Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study, International Journal of Project Management 21: 321326. doi:10.1016/50263-7863(02)00055-8

Hanson, D.; Mbachu, J.; Nkando, R. 2003. Causes of client dissatisfaction in the South African building industry and ways of improvement: the contractors' perspectives, in CIDB, South Africa.

Iyer, K. C.; Jha, K. N. 2005. Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management 23: 283-295. doi:10.1016/j.ijproman.2004.10.003

Karim, K.; Marosszeky, M. 1999. Process monitoring for process re-engineering--using key performance indicators, International Conference on Construction Process Reengineering, CPR 99, Sydney, 12-13 July.

Kuprenas, J. A. 2003. Project management actions to improve design phase cost performance, Journal of Management in Engineering 19(1): 25-32. doi:10.1061/(ASCE)0742-597X(2003)19:1(25)

Lee, A.; Cooper, R.; Aouad, G. 2001. A methodology for designing performance measures for the UK construction industry. Salford University.

Lehtonen Tutu Wegelius. 2001. Performance measurement in construction logistics, International Journal of Production Economics 69: 107-116. doi:10.1016/50925-5273(00)00034-7

Love, P. E. D.; Tse, R. Y. C.; Edwards, D. J. 2005. Time-cost relationships in australian building construction projects, Journal of Construction Engineering and Management 131(2): 187-194. doi:10.1061/(ASCE)0733-9364(2005)131:2(187)

Mbachu, J.; Nkando, R. 2007. Factors constraining successful building project implementation in South Africa, Construction Management and Economics 25(1): 39-54. doi:10.1080/01446190600601297

Moore, D.; McCabe, G.; Duckworth, W.; Sclove, S. 2003. The Practice of business statistics. Freeman, New York. Navon, R. 2005. Automated project performance control of construction projects, Automation in Construction 14: 467-476. doi:10.1016/j.autcon.2004.09.006

Ofori, G.; Dulaimi, M. F.; Ling, F. Y. 2004. improving performance of construction industry in Singapore: motivators, enablers and lessons for developing countries, Journal of Construction Research 5(2): 267-289. doi:10.1142/S1609945104000188

Okuwoga, A. A. 1998. Cost-time performance of public sector housing projects in Nigeria, Habitat Intl. 22(4): 389-395. doi:10.1016/50197-3975(98)00014-9

Pheng, L. S.; Chuan, Q. T. 2006. Environmental factors and work performance of project managers in the construction industry, International Journal of Project Management 24: 24-37. doi:10.1016/j.ijproman.2005.06.001

Reichelt, K.; Lyneis, J. 1999. The dynamic of project performance: Benchmarking the drivers of cost and schedule overrun, European Management Journal 17(2): 135-150. doi:10.1016/50263-2373(98)00073-5

Samson, M.; Lema, N. M. 2005. Development of construction contractors performance measurement framework. Department of Construction Technology and Management, University of Dar es Salaam, Tanzania.

Ugwu, O. O.; Haupt, T. C. 2007. Key performance indicators and assessment methods for infrastructure sustainability a South African construction industry perspective, Building and Environment 42: 665-680. doi:10.1016/j.buildenv.2005.10.018

UNRWA. 2006. Projects completion reports, UNRWA, Gaza.

UNRWA. 2007. Projects completion reports, UNRWA, Gaza.

World Bank. 2004. Infrastructure Assessment, Finance, Private Sector and Infrastructure Group, Middle East & North Africa, December 2004.

Zulu, S.; Chileshe, N. 2008. The impact of service quality on project performance: a case study of building maintenance services in Zambia, in Proc. of the 3rd Built Environment Conference, Association of Schools of Construction of Southern Africa, Cape Town, South Africa.

Adnan Enshassi (1), Sherif Mohamed (2), Saleh Abushaban (3)

(1) School of Civil Engineering, Islamic University of Gaza, P.O. Box 108, Gaza, Palestine

(2) School of Engineering, Griffith University, Gold Coast Campus, QLD 4222, Australia

(3) Continuing Education Center, Community College of Applied Science and Technology, P.O. Box 1415, Gaza, Palestine

E-mail: (1) [email protected]; (2) [email protected]

Adnan ENSHASSI is a Professor and Dean of the Faculty of Engineering at the Islamic University of Gaza (Palestine). Member in the international editorial board of the International Journal of Construction Management (HONGKONG); and the International Journal of Construction Project Management (CANADA). His research interest include safety in construction, productivity improvement, contract management, and risk analysis and management. Author and co-author of over 100 refereed journal and conference publications.

Sherif MOHAMED. Professor and Director of the Centre for Infrastructure Engineering and Management at Griffith University, Queensland (Australia). His research interest lies in the field of project and construction management, focusing mainly on the development of theoretical knowledge and operational tools needed for effective process management. Author and co-author of over 100 refereed journal and conference publications in the last 10 years.

Saleh ABUSHABAN is a research assistant at the Continuing Education Centre, CCAST, Palestine. His research interests include construction productivity and safety in construction.
Table 1. Summary of relative importance index and rank for factors
affecting the performance of construction projects

 Owner

Performance factors RII Rank

(1) Cost factors

Market share of organization 0.600 54
Liquidity of organization 0.729 31
Cash flow of project 0.812 14
Profit rate of project 0.694 38
Overhead percentage of project 0.647 48
Project design cost 0.500 63
Material and equipment cost 0.812 14
Project labour cost 0.741 27
Project overtime cost 0.588 58
Motivation cost 0.600 54
Cost of rework 0.588 58
Cost of variation orders 0.565 62
Waste rate of materials 0.650 46
Regular project budget update 0.638 50
Cost control system 0.725 33
Escalation of material prices 0.847 5
Differentiation of currency prices 0.788 18

(2) Time factors

Site preparation time 0.682 42
Planned time for construction 0.753 26
Percentage of orders delivered late 0.694 40
Time needed to implement variation orders 0.706 35
Time needed to rectify defects 0.659 44
Average delay in claim approval 0.650 46
Average delay in regular payments 0.824 11
Unavailability of resources 0.871 3
Average delay because of closures 0.941 1
leading to materials shortage

(3) Quality factors

Conformance to specification 0.882 2
Unavailability of competent staff 0.859 4
Quality of equipment and raw materials 0.835 9
Quality assessment system in organization 0.706 35
Quality training/meeting 0.659 45

(4) Productivity factors

Project complexity 0.729 31
Number of new projects / year 0.600 54
Management-labour relationship 0.776 22
Absenteeism rate through project 0.776 20
Sequencing of work according to schedule 0.8 17

(5) Client satisfaction factors

Information coordination between owner 0.729 29
 and project parties
Leadership skills for project manager 0.835 7
S geed and reliability of service to owner 0.718 34
Number of disputes between owner 0.753 24
 and project parties
Number of rework incidents 0.635 51

(6) Regular and community satisfaction factors

Cost of compliance to regulators requirements 0.600 54
Number of non-compliance events 0.635 51
Quality and availability of 0.647 49
 regulator documentation
Site condition problems 0.788 18

(7) People factors

Employee attitudes 0.682 41
Recruitment and competence development 0.753 24
Employees motivation 0.765 23
Belonging to work 0.835 9

(8) Health and safety factors

Application of health and safety factors 0.700 37
in organization
Project location is safe to reach 0.694 38
Reportable accidents rate in project 0.729 29
Assurance rate of project 0.671 43

(9) Innovation and learning factors

Learning from own experience and past history 0.847 5
Learning from best practice and 0.824 12
 experience of others
Work group 0.776 20
Review of failures and solving them 0.824 12

(10) Environmental factors

Air quality 0.588 58
Noise level 0.565 61
Wastes around the site 0.635 51
Climate condition 0.729 28

 Consultant

Performance factors RII Rank

(1) Cost factors

Market share of organization 0.709 39
Liquidity of organization 0.842 5
Cash flow of project 0.800 11
Profit rate of project 0.776 14
Overhead percentage of project 0.687 49
Project design cost 0.688 43
Material and equipment cost 0.776 14
Project labour cost 0.744 22
Project overtime cost 0.600 59
Motivation cost 0.584 61
Cost of rework 0.672 51
Cost of variation orders 0.688 43
Waste rate of materials 0.624 57
Regular project budget update 0.742 24
Cost control system 0.728 28
Escalation of material prices 0.832 7
Differentiation of currency prices 0.808 9

(2) Time factors

Site preparation time 0.664 53
Planned time for construction 0.760 18
Percentage of orders delivered late 0.768 17
Time needed to implement variation orders 0.704 40
Time needed to rectify defects 0.672 51
Average delay in claim approval 0.728 28
Average delay in regular payments 0.776 14
Unavailability of resources 0.858 2
Average delay because of closures 0.896 1
leading to materials shortage

(3) Quality factors

Conformance to specification 0.808 9
Unavailability of competent staff 0.848 3
Quality of equipment and raw materials 0.840 6
Quality assessment system in organization 0.712 35
Quality training/meeting 0.728 28

(4) Productivity factors

Project complexity 0.712 35
Number of new projects / year 0.688 43
Management-labour relationship 0.688 43
Absenteeism rate through project 0.688 43
Sequencing of work according to schedule 0.816 8

(5) Client satisfaction factors

Information coordination between owner 0.792 12
 and project parties
Leadership skills for project manager 0.848 3
S geed and reliability of service to owner 0.744 22
Number of disputes between owner 0.728 28
 and project parties
Number of rework incidents 0.712 35

(6) Regular and community satisfaction factors

Cost of compliance to regulators requirements 0.648 55
Number of non-compliance events 0.624 57
Quality and availability of 0.736 25
 regulator documentation
Site condition problems 0.712 35

(7) People factors

Employee attitudes 0.728 28
Recruitment and competence development 0.688 43
Employees motivation 0.696 42
Belonging to work 0.736 25

(8) Health and safety factors

Application of health and safety factors 0.728 28
in organization
Project location is safe to reach 0.704 40
Reportable accidents rate in project 0.680 50
Assurance rate of project 0.632 56

(9) Innovation and learning factors

Learning from own experience and past history 0.752 20
Learning from best practice and 0.760 18
 experience of others
Work group 0.736 25
Review of failures and solving them 0.752 20

(10) Environmental factors

Air quality 0.592 60
Noise level 0.512 63
Wastes around the site 0.584 61
Climate condition 0.656 54

 Contractor

Performance factors RII Rank

(1) Cost factors

Market share of organization 0.726 39
Liquidity of organization 0.839 10
Cash flow of project 0.848 9
Profit rate of project 0.739 38
Overhead percentage of project 0.662 47
Project design cost 0.582 63
Material and equipment cost 0.813 16
Project labour cost 0.739 37
Project overtime cost 0.617 55
Motivation cost 0.609 58
Cost of rework 0.587 62
Cost of variation orders 0.662 46
Waste rate of materials 0.639 51
Regular project budget update 0.743 35
Cost control system 0.765 32
Escalation of material prices 0.889 4
Differentiation of currency prices 0.874 5

(2) Time factors

Site preparation time 0.596 61
Planned time for construction 0.765 30
Percentage of orders delivered late 0.774 29
Time needed to implement variation orders 0.693 43
Time needed to rectify defects 0.639 50
Average delay in claim approval 0.765 30
Average delay in regular payments 0.839 11
Unavailability of resources 0.904 3
Average delay because of closures 0.943 1
leading to materials shortage

(3) Quality factors

Conformance to specification 0.822 13
Unavailability of competent staff 0.865 6
Quality of equipment and raw materials 0.861 7
Quality assessment system in organization 0.743 34
Quality training/meeting 0.674 44

(4) Productivity factors

Project complexity 0.761 33
Number of new projects / year 0.630 53
Management-labour relationship 0.796 22
Absenteeism rate through project 0.743 36
Sequencing of work according to schedule 10.804 20

(5) Client satisfaction factors

Information coordination between owner 0.809 19
 and project parties
Leadership skills for project manager 0.904 2
S geed and reliability of service to owner 0.822 13
Number of disputes between owner 0.720 40
 and project parties
Number of rework incidents 0.627 54

(6) Regular and community satisfaction factors

Cost of compliance to regulators requirements 0.604 59
Number of non-compliance events 0.614 56
Quality and availability of 0.653 48
 regulator documentation
Site condition problems 0.707 41

(7) People factors

Employee attitudes 0.795 23
Recruitment and competence development 0.809 17
Employees motivation 0.791 24
Belonging to work 0.849 8

(8) Health and safety factors

Application of health and safety factors 0.787 25
in organization
Project location is safe to reach 0.774 28
Reportable accidents rate in project 0.600 60
Assurance rate of project 0.635 52

(9) Innovation and learning factors

Learning from own experience and past history 0.818 15
Learning from best practice and 0.822 12
 experience of others
Work group 0.787 27
Review of failures and solving them 0.809 17

(10) Environmental factors

Air quality 0.671 45
Noise level 0.613 57
Wastes around the site 0.649 49
Climate condition 0.707 41

Table 2. The top significant factors affecting the performance
of construction projects

 Owner

Factors RII Rank

Escalation of material prices 0.847 5
Unavailability of resources as planned through 0.871 3
 the project duration
Average delay because of closures leading to 0.941 1
 materials shortage
Unavailability of personals with high experience 0.859 4
 and qualincation
Quality of equipments and raw materials in project 0.835 9
Leadership skills for project manager 0.835 7

 Consultant

Factors RII Rank

Escalation of material prices 0.832 7
Unavailability of resources as planned through 0.858 2
 the project duration
Average delay because of closures leading to 0.896 1
 materials shortage
Unavailability of personals with high experience 0.848 3
 and qualincation
Quality of equipments and raw materials in project 0.840 6
Leadership skills for project manager 0.848 3

 Contractor

Factors RII Rank

Escalation of material prices 0.889 4
Unavailability of resources as planned through 0.904 3
 the project duration
Average delay because of closures leading to 0.943 1
 materials shortage
Unavailability of personals with high experience 0.865 6
 and qualincation
Quality of equipments and raw materials in project 0.861 7
Leadership skills for project manager 0.904 2

Table 3. Summary of relative importance index and rank of major
groups affecting the performance of construction projects

 Owner

Performance groups RII Rank

Cost 0.679 8
Time 0.753 4
Quality 0.792 2
Productivity 0.736 5
Client satisfaction 0.734 6
Regular and community satisfaction 0.668 9
People 0.759 3
Health and safety 0.698 7
Innovation and learning 0.821 1
Environment 0.629 10

 Consultant

Performance groups RII Rank

Cost 0.724 5
Time 0.757 3
Quality 0.787 1
Productivity 0.718 6
Client satisfaction 0.765 2
Regular and community satisfaction 0.680 9
People 0.712 7
Health and safety 0.686 8
Innovation and learning 0.744 4
Environment 0.586 10

 Contractor

Performance groups RII Rank

Cost 0.726 7
Time 0.769 5
Quality 0.794 3
Productivity 0.747 6
Client satisfaction 0.779 4
Regular and community satisfaction 0.646 10
People 0.812 1
Health and safety 0.699 8
Innovation and learning 0.804 2
Environment 0.660 9

Table 4. Summary of relative importance index and
rank of cost factors

 Owner

Cost factors group RII Rank

Market share of organization 0.600 12
Liquidity of organization 0.729 6
Cash filow of project 0.812 2
Pront rate of project 0.694 8
Overhead percentage of project 0.647 10
Project design cost 0.500 17
Material and equipment cost 0.812 2
Project labour cost 0.741 5
Project overtime cost 0.588 14
Motivation cost 0.600 12
Cost of rework 0.588 14
Cost of variation orders 0.565 16
Waste rate of materials 0.650 9
Regular project budget update 0.638 11
Cost control system 0.725 7
Escalation of material prices 0.847 1
Differentiation of currency prices 0.788 4

 Consultant

Cost factors group RII Rank

Market share of organization 0.709 10
Liquidity of organization 0.842 1
Cash filow of project 0.800 4
Pront rate of project 0.776 5
Overhead percentage of project 0.687 13
Project design cost 0.688 11
Material and equipment cost 0.776 5
Project labour cost 0.744 7
Project overtime cost 0.600 16
Motivation cost 0.584 17
Cost of rework 0.672 14
Cost of variation orders 0.688 11
Waste rate of materials 0.624 15
Regular project budget update 0.742 8
Cost control system 0.728 9
Escalation of material prices 0.832 2
Differentiation of currency prices 0.808 3

 Contractor

Cost factors group RII Rank

Market share of organization 0.726 10
Liquidity of organization 0.839 4
Cash filow of project 0.848 3
Pront rate of project 0.739 9
Overhead percentage of project 0.662 12
Project design cost 0.582 17
Material and equipment cost 0.813 5
Project labour cost 0.739 8
Project overtime cost 0.617 14
Motivation cost 0.609 15
Cost of rework 0.587 16
Cost of variation orders 0.662 11
Waste rate of materials 0.639 13
Regular project budget update 0.743 7
Cost control system 0.765 6
Escalation of material prices 0.889 1
Differentiation of currency prices 0.874 2

Table 5. Summary of relative importance index
and rank of time factors

 Owner

Time factors group RII Rank

Site preparation time 0.682 7
Planned time for project construction 0.753 4
Percentage of orders delivered late 0.694 6
Time needed to implement variation orders 0.706 5
Time needed to rectify defects 0.659 8
Average delay in claim approval 0.650 9
Average delay in payment from 0.824 3
 owner to contractor
Unavailability of resources as 0.871 2
 planned through project duration
Average delay because of closures 0.941 1
 leading to materials shortage

 Consultant

Time factors group RII Rank

Site preparation time 0.664 9
Planned time for project construction 0.760 5
Percentage of orders delivered late 0.768 4
Time needed to implement variation orders 0.704 7
Time needed to rectify defects 0.672 8
Average delay in claim approval 0.728 6
Average delay in payment from 0.776 3
 owner to contractor
Unavailability of resources as 0.858 2
 planned through project duration
Average delay because of closures 0.896 1
 leading to materials shortage

 Contractor

Time factors group RII Rank

Site preparation time 0.596 9
Planned time for project construction 0.765 5
Percentage of orders delivered late 0.774 4
Time needed to implement variation orders 0.693 7
Time needed to rectify defects 0.639 8
Average delay in claim approval 0.765 5
Average delay in payment from 0.839 3
 owner to contractor
Unavailability of resources as 0.904 2
 planned through project duration
Average delay because of closures 0.943 1
 leading to materials shortage

Table 6. Summary of relative importance index and rank of quality
factors

 Owner Consultant Contractor

Quality factors group RII Rank RII Rank RII Rank

Conformance to 0.882 1 0.808 3 0.822 3
 specification
Unavailabilit of 0.859 2 0.848 1 0.865 1
 personals with high
 experience and
 qualification
Quality of equipments 0.835 3 0.840 2 0.861 2
 and raw materials in
 project
Participation of 0.812 4 0.784 4 0.800 4
 managerial levels
 with decision-making
Quality assessment 0.706 5 0.712 6 0.743 5
 system in organization
Quality training/meeting 0.659 6 0.728 5 0.674 6

Table 7. Summary of relative importance index and rank of
productivity factors

 Owner Consultant Contractor

Productivity factors RII Rank RII Rank RII Rank

Project complexity 0.729 4 0.712 2 0.761 3
Number of new 0.600 5 0.688 3 0.630 5
 projects/year
Management-labour 0.776 2 0.688 3 0.796 2
 relationship
Absenteeism rate 0.776 2 0.688 3 0.743 4
 through project
Sequencing of work 0.800 1 0.816 1 0.804 1
 according to schedule

Table 8. Summary of relative importance index and rank of
client satisfaction factors

 Owner Consultant Contractor
Client satisfaction
group RII Rank RII Rank RII Rank

Information coordination 0.729 3 0.792 2 0.809 3
 between owner and
 project parties
Leadership skills for 0.835 1 0.848 1 0.904 1
 project manager
Speed and reliability 0.718 4 0.744 3 0.822 2
 of service to owner
Number of disputes 0.753 2 0.728 4 0.720 4
 between owner and
 project artier
Number of reworks 0.635 5 0.712 5 0.627 5

Table 9. Summary of relative importance index and rank of
regular and community satisfaction factors

 Owner Consultant Contractor
Regular and community
and satisfaction group RII Rank RII Rank RII Rank

Cost of compliance to 0.600 4 0.648 3 0.604 4
 regulators
 requirements
Number of non-compliance 0.635 3 0.624 4 0.614 3
 to regulation
Quality and availability 0.647 2 0.736 1 0.653 2
 of regulator
 documentation
Neighbours and site 0.788 1 0.712 2 0.707 1
 conditions problems

Table 10. Summary of relative importance index and rank of
people factors

 Owner Consultant Contractor

People factors group RII Rank RII Rank RII Rank

Employee attitudes in 0.682 4 0.728 2 0.795 3
 project
Recruitment and 0.753 3 0.688 4 0.809 2
 competence development
 between employees
Employees motivation 0.765 2 0.696 3 0.791 4
Belonging to work 0.835 1 0.736 1 0.849 1

Table 11. Summary of relative importance index and rank of
health and safety factors

 Owner Consultant Contractor
Health and factors
safety group RII Rank RII Rank RII Rank

Application of health 0.700 2 0.728 1 0.787 1
 and safety factors in
 organisation
Easiness to reach the 0.694 3 0.704 2 0.774 2
 site (location of
 project)
Reportable accidents 0.729 1 0.680 3 0.600 4
 rate in project
Assurance rate of 0.671 4 0.632 4 0.635 3
 project

Table 12. Summary of relative importance index and rank of
innovation factors

 Owner Consultant Contractor
Innovation and factors
learning RII Rank RII Rank RII Rank

Learning from own 0.847 1 0.752 2 0.818 2
 experience and past
 history
Learning from best 0.824 3 0.760 1 0.822 1
 practice and
 experience of others
Training the human 0.835 2 0.720 5 0.787 4
 resources in the
 skills demanded by the
 project
Work group 0.776 5 0.736 4 0.787 4
Review of failures and 0.824 3 0.752 2 0.809 3
 solving them

Table 13. Summary of relative importance index and rank of
environmental factors

 Owner Consultant Contractor
Environmental factors
group RII Rank RII Rank RII Rank

Air quality 0.588 3 0.592 2 0.671 2
Noise level 0.565 4 0.512 4 0.613 4
Wastes around the site 0.635 2 0.584 3 0.649 3
Climate conditions 0.729 1 0.656 1 0.707 1
联系我们|关于我们|网站声明
国家哲学社会科学文献中心版权所有