Mathematical modelling of dispute proceedings between investors and third parties on allegedly violated third-party rights/Ginco proceso tarp investuotoju ir treciuju asmenu del galimai pazeistu treciuju asmenu teisiu matematinis modeliavimas.
Sostak, Olga Regina ; Vakriniene, Sigute
1. Introduction
In most of our cities, some parts undergo intensive transformations
related to commercialisation, land use and the density of buildings
(Kaklauskas et al. 2007; Bardauskiene 2007; Turskis et al. 2006;
Zavadskas et al. 2004; Kaganova et al. 2008). Several examples in
European cities show that development can embrace internal urban areas
(Mcdonald et al. 2009; Kaklauskas et al. 2009; Miller et al. 2004).
Currently, Lithuanian cities also witness concentrated development
(Zavadskas et al. 2009; Viteikiene and Zavadskas 2007; Burinskiene 2009;
Jakaitis et al. 2009). It allows using the existing infrastructure and
abandoned urban territories. Such planning also reduces the amount of
used land and creates a lasting environment, the immensely dense
population of which is not always able to function properly (Burinskiene
and Rudzkiene 2009; Lahdenpera 2009; Petrovic et al. 2009; Greater
London Authority 2003; Ribeiro 2008; Lindgren and Castell 2008). On one
hand, it is a natural stage related to the renovation of neglected
valuable urban areas. On the other hand, the course and outcomes at this
stage reveal gaps within the renewal process. We are inclined to blame
the drawbacks of laws regulating urban planning and protection of visual
identity (investors cannot always be expected to abandon their
self-centred ends for the sake of urban values, etc.) (Dringelis 2005;
Vrubliauskas 2005; Jakaitis 2004; Mickaityte et al. 2008; Banaitis and
Banaitiene 2007; Majamaa et al. 2008). This is in a large part
influenced by a confusing, non-effective system for the coordination of
constructions with government institutions and the public. The
regulation of constructions is confusing; builders breach the introduced
requirements; officials are frequently provided with the right to easily
choose the requirements necessary to be applied. An inappropriate
distribution of functions among government institutions and private
subjects raise a number of problems (Sostak and Kutut 2009). One of the
outcomes of inappropriate legal regulation is the violation of the
third-party rights (i.e. the parties not directly related to the
investment construction process: the owners of neighbouring plots,
users, communities of residential districts, etc.). The article analyses
the influence of third-party rights infringed during construction
planning on the implementation of an investment project.
The development of the national economy is impossible without
construction: people use construction products--various buildings--to
live, work and satisfy other social needs. Construction investment
contributes to national economic growth and development extensively
(Urbanavieiene et al. 2009; Zavadskas and Kaklauskas 2005, 2008). The
investment process in construction is long and complicated; it requires
enormous financial, intellectual and other resources. If judicial
disputes occur during this process, the investor may incur huge loss,
and project implementation may be postponed for an indefinite term.
Litigation may continue for several years (The judgement of the Supreme
Administrative Court of Lithuania of 19 January 2007 in the
administrative case; The judgement of the Supreme Administrative Court
of Lithuania of 26 January 2007 in the administrative case). Thus,
investors are most concerned to avoid any legal disputes and should pay
considerable attention to their prevention.
Violations of third-party rights are of benefit neither to third
parties, nor to the parties of the investment process, because, on one
hand, such violations might wrongfully cause the deterioration of the
conditions for life and other activities of third persons. On the other
hand, violations of third-party rights at the stage of construction
planning may affect the implementation of the investment project,
because all solutions violating third-party rights also violate the
provisions of legal acts and can be disputed as stipulated by the Law on
Administrative Proceedings (hereinafter LAP 2000), the Law on
Territorial Planning (2004) and other legal acts (Mitkus and Sostak
2009).
In a construction project, judicial disputes are an unwanted risk
factor, which may disrupt the entire project. It is therefore necessary
to plan and apply preventive measures for the mitigation of such risk at
the initial planning stage of a construction project. To evaluate and
eliminate these risk factors, state-of-the-art technologies for
construction project planning and management must be integrated into
each step of construction project planning and implementation. It is
necessary to employ innovative methods for construction project planning
and implementation when the conditions are indeterminate (Kahraman and
Kaya 2010; Blaszczyk and Nowak 2009). Risk management strategies and the
development of a risk management plan must be improved, risk analysis
methods and technologies must be used, and the risk reporting mechanism
must be implemented. For a successful construction project, it is worth
to employ the functions of project management. It is necessary to
analyse the risk using the knowledge of relevant experts and to properly
evaluate the scope of possible negative effects and their outcomes to
the construction project. The findings should influence the subsequent
decision-making process. Risks must be monitored and decision-making
must be analysed throughout the project lifecycle. Before launching a
project, an investor must be ready for any "surprises".
Forecasting is the most important part of any strategy, because the
actions recommended for certain situations stem from the forecasts of
possible outcomes. Thus, investors must be aware of the defence
procedures taking place in administrative courts when third-party rights
are violated during territorial planning--they must assess possible
actions of third parties.
The process consists of the following main stages: 1) third parties
learn about the violation of their rights (infringement determined); 2)
a pretrial defence of infringed rights (advance instance). Before an
administrative court is involved, separate legal acts or actions/
omissions of public administration entities foreseen by laws can be, and
in cases established by laws must be, disputed by applying to an advance
institution for out-of-court case hearing. The procedures for a pretrial
defence of third-party rights are defined in Article 25 of The Law on
Administrative Proceedings of the Republic of Lithuania (LAP 2000).
Unless the laws foresee otherwise, administrative disputes may be heard
out-of-court by public municipal commissions for administrative disputes
and the Supreme Commission for Administrative Disputes (LAP 2000, Art.
26); 3) a judicial defence of violated rights. The Law on Administrative
Proceedings of the Republic of Lithuania foresees that a decision of a
respective commission for administrative disputes or another institution
for advance out-of-court hearing of disputes made after hearing an
administrative dispute out-of-court can be appealed against to an
administrative court by the dispute party which is discontent with the
decision of such commission for administrative disputes or another
institution for advance out-of-court hearing of disputes. The
appellation must be submitted to the administrative court within 20 days
upon the announcement of the decision (LAP 2000, Art. 32); 4) the case
proceedings at a court of first instance. Art. 68 of LAP (2000) foresees
that the chairman of the court or the judge who made the decision to
accepted the claim, if necessary, take care of the following important
aspects of preparation for the trial: a) prepare claim guarantee
measures; b) make a decision on the invitation of experts or inspection;
c) perform other actions required for preparation for the trial; etc. It
is not always possible to complete a trial fully and to make a judgment
at the first and single court session; although the court attempts to
complete a trial within one session if it does not impair proper
settlement. However, it is rather difficult, and sometimes impossible,
even if the proceedings are prepared properly, though it is the aim of
such preparation to guarantee full completion of a trial already at the
first session. Unforeseen obstacles are rather frequent; therefore, the
proceedings continue for one, two, three and sometimes even ten or more
sessions (Lauzikas et al. 2005); 5) the case proceedings at a court of
appeal. In order to guarantee the expedition of the process, to protect
the interests of the winning party in the case and to guarantee definite
relations between the parties, the law specifies a period for party
discontent with the court decision or for another person participating
in the case to exercise their right of appeal. Judgements of county
administrative courts announced after a trial in the court of first
instance can be appealed against to the Supreme Administrative Court of
Lithuania within fourteen days after the announcement of the judgement
(LAP 2000, Art. 127). The proceedings of an appeal are similar to
proceedings at the court of first instance. A judgement, a resolution or
a rule of the court of appeal comes into force on the day of its
announcement and cannot be appealed against in cassation (LAP 2000).
A peace treaty can be signed at any stage. A compromise is achieved
in such case and further litigation is avoided (Mitkus and Sostak
2008a).
If a judicial dispute occurs when the construction project is
already launched, the investor must also consider all possible actions
of judicial institutions. The lessons learned about risk management
during the implementation of construction projects should be used in
future projects (Zavadskas et al. 2010; Park et al. 2009; Yang et al.
2009; Antucheviciene et al. 2010). Mathematical modelling of the problem
in question and the selection of a proper method for optimisation help
with determining the optimal investor's behaviour strategy that
would allow expecting a certain average profit irrespective of the
strategies of third parties and decisions of judicial institutions. Our
research employs the mathematical model for stochastic dynamic
programming.
2. Mathematical Modelling of a Dispute between Investors and Third
Parties on Allegedly Violated Third-party rights with the Help of
Stochastic Dynamic Programming
The analysis of the procedure related to the defence of violated
third-party rights in administrative courts leads to a conclusion that a
judicial dispute may either ruin a construction investment project
completely or to cut the expected profits considerably. Largely, it
depends on the decisions of the interested communities (third persons)
that object to the construction and on the decisions of judicial
institutions hearing the disputes. Naturally, investors are most
interested to avoid any legal disputes. A possible preventive measure to
mitigate such risk is an assessment and proper analysis of all possible
future events related to the occurrence of such risk before the
investment project is launched. For that purpose, the investor must come
up with the scenarios of actions in possible situations and to plan
strategic options. The investor, which is most interested to avoid any
legal disputes, should assess all possible risk factors that may affect
the implementation of a construction project. To illustrate such
assessment, we shall turn to mathematical modelling of a dispute between
investors and third parties on allegedly violated third-party rights.
The dispute between investors and third parties on possibly infringed
third-party rights was modelled by creating a tree of the behaviour
variants of dispute parties (Fig. 1).
[FIGURE 1 OMITTED]
Besides, the tree of variants helps in finding mistakes made
afterwards and in correcting them (Mitkus and Sostak 2008b; Mitkus 2004;
Nollke 2007; Ross Quinlan 1993). The tree of the behaviour variants of
dispute parties in Fig. 1 models all possible actions of third persons,
judicial institutions and the investor in a certain situation. The
outcomes of their actions are assessed.
Dynamic programming will be used to find an optimal behaviour
strategy for an investor. Dynamic programming is a method of calculation
applied in a solution to the multi-stage problems of optimisation. It
means that we need to break a complex problem of optimisation into a
string of simpler problems. When these problems are solved, it is easy
to find an answer to an original problem. Problems are divided following
the Belman's Principle of Optimality: an optimal solution
(management) has the property that whatever the initial state and
initial solution are, the remaining solutions must constitute an optimal
policy with regard to the state resulting from the first solutions. Note
that by a dynamic problem we usually mean any process which depends on
time (in our case, the court proceedings related to the defence of the
infringed rights depend on time) (Ciocys and Jasilionis 1990; Taha
1997).
For further modelling, we shall look at the tree of the behaviour
variants of dispute parties and make a tree of behaviour strategies for
the investor (Fig. 2). If we want to solve the tree of behaviour
strategies for the investor mathematically - to perform mathematical
modelling--we need numerical values for our specific research case. The
values are shown in Table 1. The numerical values are based on actual
cases brought to Lithuanian courts (The judgement of the Supreme
Administrative Court of Lithuania of 20 February 2006 in the
administrative case; The judgement of the Supreme Administrative Court
of Lithuania of 19 January 2007 in the administrative case; The
judgement of the Supreme Administrative Court of Lithuania of 26 January
2007 in the administrative case). We base our research on a general
(abstract) model. The analysis of specific dispute cases in the future,
however, could use corrected values and assess all individual aspects
related to the conflict.
[FIGURE 2 OMITTED]
3. The Model for Stochastic Dynamic Programming
Let f ([S.sub.i]) be the likely (expected) average investor's
profit ensured by state [S.sub.i] and optimal strategy
[x.sub.i]--selected from the set of possible strategies in this
situation. The Belman's Principle of Optimality gives us recurrent
equations for all situations [S.sub.i] :
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII], (1)
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII], is the pool of
investor's original strategies in the situation (state) [S.sub.i].
Here [[m.sub.i].summation over (j=1)] [x.sub.ij] = 1 and
[x.sub.ij] [greater than or equal to] 0, j = 1, 2, ... , mi.
When the number of possible strategies is [m.sub.i], breaking the
set of strategies using Index 2 satisfies equation [J.sub.is] [union]
[J.sub.ib] = {1, 2, ..., [m.sub.i]}.
Generally, the intersection of index sets [J.sub.is] and [J.sub.ib]
is a non-empty set, which means that the same strategy can lead to the
final state or to a situation when the investor must chose a strategy
again.
When j [member of] [J.sub.is], strategy [X.sub.ij] may lead the
investor to situation [S.sub.ijk] (probability [p.sub.ijk]). The number
of situations enabled by the investor's choice of strategy
[x.sub.ij] is marked as [n.sub.ij].
When j [member of] [J.sub.ib] , strategy [x.sub.ij] leads the
investor (probability [P.sub.ijk]) to the final state with profit
[P.sub.jb].
f([S.sub.ijk]) is the likely (expected) average profit ensured by
state [S.sub.ijk] and the optimal strategy selected from the pool of
possible strategies in this state.
In our model for stochastic dynamic programming, probabilities
[p.sub.ijk] and [p.sub.ijb] depend on the probability of decisions made
by other institutions.
We shall proceed with the analysis of possible behaviour strategies
for an investor that invests into a construction project, seeks maximum
profits but faces the opposition of the community. We shall also look at
the problem in which optimal strategies are determined using multi-stage
optimisation--dynamic programming.
Here, probabilities [p.sub.ijk] and [p.sub.ijb] depend on the
probability of certain decisions made by the community opposing the
construction and judicial institutions hearing the disputes.
Let us define possible judicial situations.
Let [T.sub.k] be possible judicial states, k = [bar.1.7] (in our
research, there are seven of these states).
In each state [T.sub.k], courts may make one of two decisions:
[A.sub.k] or [B.sub.k].
Let the probabilities of events [A.sub.k] and [B.sub.k] be
[q.sub.kl] = P([A.sub.k]) and [q.sub.k2] = P([B.sub.k]), [q.sub.kl] +
[q.sub.k2] = 1 [q.sub.kl] [greater than or equal to] [q.sub.k2] [greater
than or equal to] 0.
The first judicial state [T.sub.1] is possible if breaches are
determined in planning and implementing construction investment projects
and if the interested community applies with a claim to an advance
institution for out-of-court case hearing. There are two possible events
in such situation:
1) [A.sub.1]: the advance hearing institution rejects the claim
(determines that the solutions of the construction investment project do
not violate rights of the interested community).
2) [B.sub.1]: the advance hearing institution satisfies the claim.
Let us assess the probabilities of the events:
[q.sub.11] = P([A.sub.1]) = 0.40 , [q.sub.12] = P([B.sub.1]) =
0.60.
The second judicial state [T.sub.2] is possible if the advance
hearing institution rejects the claim of the interested community and
the interested community applies to a court of first instance. There are
two possible events in such situation:
1) [A.sub.2] : the claim of the interested community is rejected.
2) [B.sub.2] : the claim of the interested community is satisfied.
Let us assess the probabilities of the events:
[q.sub.21] = P([A.sub.2]) = 0.50, [q.sub.22] = P([B.sub.2]) = 0.70.
The third judicial state [T.sub.3] is possible if the court of
first instance rejects the claim of the interested community and the
interested community applies to a court of appeal. There are two
possible events in such situation:
1) [A.sub.3]: the claim of the interested community is rejected and
the investor makes profit [P.sub.7].
2) [B.sub.3] : the claim of the interested community is satisfied
and the cancellation of the solutions related to the construction
investment project is initiated--the investor suffers loss N.
Let us assess the probabilities of the events:
[q.sub.31] = P([A.sub.3]) = 0.50, [q.sub.32] = P([B.sub.3]) = 0.50.
The judicial state [T.sub.4] is possible if the court of first
instance satisfies the claim of the interested community and the
investor applies to a court of appeal. There are two possible events in
such situation:
1) [A.sub.4] : the investor's claim is rejected and the
cancellation of the solutions is initiated--the investor suffers loss N.
2) [B.sub.4]: the investor's claim is satisfied and the
investor makes profit [P.sub.8].
Let us assess the probabilities of the events: [q.sub.41] =
P([A.sub.4]) = 0.50, [q.sub.42] = P([B.sub.4]) = 0.50.
The fifth judicial state [T.sub.5] is possible if the advance
institution for out-of-court case hearing satisfies the claim of the
interested community and the investor applies to a court of first
instance. There are two possible events in such situation:
1) [A.sub.5]: the investor's claim is satisfied;
2) [B.sub.5]: the investor's claim is rejected.
Let us assess the probabilities of the events: [q.sub.51] =
P([A.sub.5]) = 0.50 , [q.sub.52] = P(B5) = 0.50 .
The sixth judicial state [T.sub.6] is possible if the court of
first instance rejects the investor's claim and the investor
applies to a court of appeal. There are two possible events in such
situation:
1) [A.sub.6] : the investor's claim is rejected and the
cancellation of the solutions is initiated--the investor suffers loss N.
2) [B.sub.6] : the investor's claim is satisfied and the
investor makes profit [P.sub.10].
Let us assess the probabilities of the events: [q.sub.61] =
P([A.sub.6]) = 0.50, [q.sub.62] = P([B.sub.6]) = 0.50.
The seventh judicial state T7 is possible if the court of first
instance satisfies the investor's claim and the interested
community applies to a court of appeal. There are two possible events in
such situation:
1) [A.sub.7] : the claim of the interested community is satisfied
and the cancellation of the solutions is initiated--the investor suffers
loss N.
2) [B.sub.7] : the claim of the interested community is rejected
and the investor makes profit [P.sub.12].
Let us assess the probabilities of the events:
[q.sub.71] = P([A.sub.7]) = 0.50, [q.sub.72] = P([B.sub.7]) = 0.50.
Let [V.sub.j] be the possible states of the interested community
(situations when the community decides), j = [bar.1,5] (in our research,
there are five of these states).
The interested community may act in two different ways in each
state: either to refrain from applying to a judicial institution (event
[C.sub.j]) or to apply (event [D.sub.j]).
There are respective probabilities [p.sub.j1] and [p.sub.j2], where
[p.sub.j1] + [p.sub.j2] = 1, p.sub.j1] [greater than or equal to]
[p.sub.j2] [greater than or equal to] 0.
The first state of interested community [V.sub.1] is possible if
the investment solution violates rights. There are two possible events
in such case:
1) [C.sub.1] : the interested community fails to see the violations
in the investment solution or fails to submit its suggestions or
objections before the deadline, thus the investor makes profit P.
2) [D.sub.1] : the interested community determines the violations
in the investment solution and submits its suggestions and/or objections
before the deadline.
Let us assess the probabilities of the events:
[p.sub.11] = P([C.sub.1]) = 0.80, [p.sub.12] = P([D.sub.1]) = 0.20.
The second state of interested community [V.sub.2] is possible if
the investor rejects the suggestions submitted by the interested
community regarding the violations in the investment solution. There are
two possible events in such case:
1) [C.sub.2] : the interested community does not apply to an
advance institution for out-of-court dispute hearing and the investor
makes profit [P.sub.3].
2) [D.sub.2] : the interested community applies to an advance
institution for out-of-court dispute hearing.
Let us assess the probabilities of the events:
[p.sub.21] = P([C.sub.2]) = 0.30, [p.sub.22] = P([D.sub.2]) = 0.70.
The third state of interested community [V.sub.3] is possible if
the advance institution for out-of-court dispute hearing rejects the
claim of the interested community. There are two possible events in such
case:
1) [C.sub.3] : the interested community does not apply to a court
of first instance and the investor makes profit [P.sub.4].
2) [D.sub.3] : the interested community applies to a court of first
instance.
Let us assess the probabilities of the events:
[p.sub.31] = P([C.sub.3]) = 0.25 , [p.sub.32] = P([D.sub.3]) =
0.75.
The fourth state of interested community [V.sub.4] is possible if
the court of first instance rejects the claim of the interested
community. There are two possible events in such case:
1) [C.sub.4] : the interested community does not apply to a court
of appeal and the investor makes profit [P.sub.6].
2) [D.sub.4] : the interested community applies to the court of
appeal.
Let us assess the probabilities of the events:
[p.sub.4l] = P([C.sub.4]) = 0.15, [p.sub.42] = P([D.sub.4]) = 0.85.
The fifth state of interested community [V.sub.5] is possible if
the court of first instance satisfies the investor's claim. There
are two possible events in such case:
1) [C.sub.5] : the interested community does not apply to a court
of appeal and the investor makes profit [P.sub.11].
2) [D.sub.5] : the interested community applies to a court of
appeal.
Let us assess the probabilities of the events:
[P.sub.51] = P([C.sub.5]) = 0.45, [p.sub.52] = P([D.sub.5]) = 0.55.
Let [S.sub.i] be the possible states of the investor--the
situations when the investor decides, i = [bar.0.5] (in our research,
there are six of these states).
In each state, the investor can choose from either two or three
behaviour strategies. Mixed behaviour strategies are also possible, when
each original strategy has a probability assigned:
[x.sub.i1] is the probability the first strategy [s.sub.i1] will be
selected; is the probability the second strategy [s.sub.i2] will be
selected; [x.sub.i3] is the probability the third strategy [s.sub.i3]
will be selected. [x.sub.i1] + [x.sub.i2] + [x.sub.i3] = 1, [x.sub.il]
[greater than or equal to] 0, l = 1,2,3.
[S.sub.0] is the zero state of the investor. In this state, the
investor contemplates whether the investment project is worth launching.
[S.sub.1] is the first state of the investor. If violations are de
termined, the investor has three strategies to choose from:
[x.sub.11] : to accept the suggestions of the interested community
and to make profit [P.sub.1].
[x.sub.12] : to sign a peace treaty and to make profit [P.sub.2].
[x.sub.13] : to reject the suggestions of the interested community.
[S.sub.2] is the second state of the investor. If the interested
community applies to a court of first instance, the investor has
two strategies to choose from:
[x.sub.21] : to sign a peace treaty with the interested community
and to make profit P5.
[x.sub.22] : to reject the peace treaty.
[S.sub.3] is the third state of the investor. If the court of first
instance satisfies the claim of the interested community, the investor
has two strategies to choose from:
[x.sub.31] : to refrain from an application to a court of appeal
and to suffer loss N.
[x.sub.32] : to apply to a court of appeal.
[S.sub.4] is the fourth state of the investor. If the advance
institution for out-of-court dispute hearing satisfies the claim of the
interested community after the hearing, the investor has three
strategies to choose from:
[x.sub.41] : to refrain from applying to a court of first instance
and to suffer loss N.
[x.sub.42] : to sign a peace treaty with the interested community
and to make profit [P.sub.9].
[x.sub.43] : to apply to a court of first instance.
[S.sub.5] is the fifth state of the investor. If the court of first
instance rejects the investor's claim, the investor has two
strategies to choose from:
[x.sub.51] : to refrain from applying to a court of appeal and to
suffer loss N.
[x.sub.52] : to apply to a court of appeal.
We shall proceed with further mathematical modelling and, using the
data from our graph (Fig. 2), shall come up with the recurrent equations
(2):
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII]. (2)
In each state, we need to solve the problem of linear optimisation:
max([c.sub.1][x.sub.i1] + [c.sub.2][x.sub.i2] + ... + [c.sub.mi]
[x.sub.imi]), [[m.sub.i].summation over (j=1)] [x.sub.ij] = 1,
[x.sub.ij] [greater than or equal to] 0,
j = 1, 2, ..., [m.sub.i], in which one of the optimal plans is
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII].
Thus, we can replace the recurrent equations with simplified
versions (3):
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII]. (3)
In order to determine optimal behaviour strategies for the
investor, a programme code for a solution to the recurrent equations (3)
has been developed in the EXEL environment (see Table 2). Let us analyse
calculations in question.
[FIGURE 3 OMITTED]
We solve the recurrent equations to find the specific values of
profit in the final state and to determine specific probabilities that
the community and judicial institutions will take one or another action.
These values are the expected average profit for each state (situation)
f ([S.sub.i]) and the optimal situation management marked as
[x.sup.*.sub.t]. Obviously, original strategies are optimal for each
state; their probability is equal to one.
Optimal investor's strategies determined using our
calculations are shown in Fig. 3. A broad analysis of determining the
dependency of the solutions on the parameters is possible. If, for
instance, the size of loss N in the final situation varies between 1 and
1000, the optimal investor's behaviour remains the same, only
values f ([S.sub.5]) and f ([S.sub.3]) change (1,000 monetary units were
used as a measuring unit throughout research).
Further research should focus on the analysis of the
investor's possibilities of choosing only the projects that would
trigger the most positive reactions of third persons with increasing
f([S.sub.1]) values.
Therefore, future research should consider the inclusion of several
trees of the behaviour variants of dispute parties with the same
starting point So and equivalent to the tree used in this research. An
investor, when in state So, could select an optimal project based on the
same Belman's Principle (see Fig. 3).
4. Conclusions
1. Violations of third-party rights are of benefit neither to third
persons, nor to the parties of the construction investment process,
because, on one hand, such violations might wrongfully cause the
deterioration of conditions for life and other activities of third
persons. On the other hand, violations of third-party rights at the
stage of construction planning may affect the implementation of the
investment project, because all solutions violating third-party rights
also violate the provisions of legal acts and can be disputed as
stipulated by the Law on Administrative Proceedings (LAP), the Law on
Territorial Planning and other legal acts.
2. Investors may incur, and do incur, huge losses when solving
disputes on the infringement of third-party rights.
3. In order to make the relations between investors and third
parties more rational, a mathematical model of a dispute on allegedly
infringed third-party rights has been developed. It helps with
determining optimal investor's strategies for each situation of
decision-making and thus ensures a certain average profit to the
investor irrespective of the strategies chosen by third persons if the
probabilities of selecting these strategies are known.
4. The mathematical model for stochastic dynamic programming (EXEL
programme code for recurrent equations (3) is used) enables a broad
analysis of the dependencies between the optimal investor's
strategy and the probabilities that third parties will select a certain
strategy. It also helps in analyzing the possible numerical values of
profit (or loss).
doi: 10.3846/13923730.2011.560628
References
Antucheviciene, J.; Zavadskas, E. K.; Zakarevieius, A. 2010.
Multiple criteria construction management decisions considering
relations between criteria, Technological and Economic Development of
Economy 16(1): 109-125. doi:10.3846/tede.2010.07
Banaitis, A.; Banaitiene, N. 2007. Development of a rational
housing model: The Lithuanian case, International Journal of Environment
and Pollution 30(3-1): 430-142. doi:10.1504/IJEP.2007.014820
Bardauskiene, D. 2007. Ekspertiniu vertinimu taikymas rengiant
miesto bendraji plan? [The expert's estimates application in the
preparation of city general plan], Technological and Economic
Development of Economy 13(3): 223-236.
Blaszczyk, T.; Nowak, M. 2009. The time-cost trade-off analysis in
construction project using computer simulation and interactive
procedure, Technological and Economic Development of Economy 15(4):
523-539. doi:10.3846/1392-8619.2009.15.523-539
Burinskiene, M. 2009. New methodology for sustainable development
towards sustainable transportation system, Technological and Economic
Development of Economy 15(1): 5-9. doi:10.3846/1392-8619.2009.15.5-9
Burinskiene, M.; Rudzkiene, V. 2009. Future insights, scenarious
and expert method application in sustainable territorial planning,
Technological and Economic Development of Economy 15(1): 10-25.
doi:10.3846/1392-8619.2009.15.10-25
Ciocys, V.; Jasilionis, R 1990. Matematinis programavimas
[Mathematical programming]. Vilnius: Mokslas.
Dringelis, L. 2005. Miesto viesosios erdves: pokyciu tendencijos ir
savitumo issaugojimas [Public Urban Areas: trends of changes and
preservation of peculiar features], Urbanistika ir architektura [Town
Planning and Architecture] 29(1): 50-53.
Greater London Authority. 2003. Housing for a Compact City. Greater
London Authority Architecture and Urbanism Unit.
Jakaitis, J. 2004. Neformalaus veikimo veiksniu itaka urbanistinei
raidai [Influence of factors of informal activities on urban
development], Urbanistika ir architektera [Town Planning and
Architecture] 18(3): 132-143.
Jakaitis, J.; Paliulis, N.; Jakaitis, K. 2009. Aspects of the
national urban policy management under conditions of integrated
planning, Technological and Economic Development of Economy 15(1):
26-38. doi:10.3846/1392-8619.2009.15.26-38
Kaganova, O.; Akmatov, A.; Undeland, C. 2008. Introducing more
transparent and efficient land management in post-socialist cities:
lessons from Kyrgyzstan, International Journal of Strategic Property
Management 12(3): 161-181. doi:10.3846/1648-715X.2008.12.161-181
Kaklauskas, A.; Zavadskas, E. K.; Saparauskas, J. 2009. Conceptual
modelling of sustainable Vilnius development, Technological and Economic
Development of Economy 15(1): 154-177.
doi:10.3846/1392-8619.2009.15.154-177
Kaklauskas, A.; Zavadskas, E. K.; Vainienas, P.; Jonaitis, V.;
Stragys, V. 2007. Lietuvos statybu 2007-2030 vizija ir strategija.
Gyvenimo kokybe [A vision and strategy for Lithuanian construction
2007-2030. Quality of life], in Lietuvos nacionaline statybu
technologiju platforma [Lithuanian National Construction Technology
Platform], 30-38.
Kahraman, C.; Kaya, I. 2010. Investment analyses using fuzzy
probability concept, Technological and Economic Development of Economy
16(2): 43-57. doi:10.3846/tede.2010.03
Lahdenpera, P. 2009. Phased multi-target areal development
competitions: algorithms for competitor allocation, International
Journal of Strategic Property Management 13(1): 1-22.
doi:10.3846/1648-715X.2009.13.1-22
Lauzikas, E.; Mikelenas, V.; Nekrosius, V. 2005. Civilinio proceso
teise [Law of Civil Process]. Vol. 2. Vilnius: JUSTITA.
Lietuvos Respublikos administraciniu bylu teisenos istatymas. 2000
[The Law on Administrative Proceedings of the Republic of Lithuania],
Valstybes zinios, 11 10 2000, No. 85-2566.
Lietuvos Respublikos teritorije planavimo estatymas. 2004 [The Law
on Territorial Planning of the Republic of Lithuania], Valstybes zinios,
07 02 2004, No. 21-617.
Lindgren, T.; Castell, P. 2008. Open space management in
residential areas--how it is organised and why, International Journal of
Strategic Property Management 12(3): 141-160.
doi:10.3846/1648-715X.2008.12.141-160
Majamaa, W.; Junnila, S.; Doloi, H.; Niemisto, E. 2008. Enduser
oriented public-private partnerships in real estate industry,
International Journal of Strategic Property Management 12(1): 1-17.
doi:10.3846/1648-715X.2008.12.1-17
McDonald, S.; Malys, N.; Maliene, V. 2009. Urban regeneration for
sustainable communities: A case study, Technological and Economic
Development of Economy 15(1): 49-59. doi:10.3846/1392-8619.2009.15.49-59
Mickaityte, A.; Zavadskas, E. K.; Kaklauskas, A.; Tupenaite, L.
2008. The concept model of sustainable buildings refurbishment,
International Journal of Strategic Property Management 12(1): 53-68.
doi:10.3846/1648-715X.2008.12.53-68
Miller, Ch. J. M.; Packham, G. A.; Pickernell, D. G.; Mcgovern, M.
2004. Building for the future: The potential importance of the
construction industry in Welsh economic development policy, Construction
Management and Economics 22(5): 533-540.
doi:10.1080/01446190310001649128
Mitkus, S. 2004. Statybos dalyviu rizika ir atsakomybe uz statybos
produktu defektus [Risk and liability of parties in the construction
process for defects of construction products], Technological and
Economic Development of Economy 10(3): 109-115.
Mitkus, S.; Sostak, O. R. 2008a. Peculiarities of defence of public
and private interests, Socialiniai tyrimai [Social Researches] 2(12):
75-93.
Mitkus, S.; Sostak, O. R. 2008b. Modelling the process for defence
of third party rights infringed while implementing construction
investment projects, Technological and Economic Development of Economy
14(2): 208-223. doi:10.3846/1392-8619.2008.14.208-223
Mitkus, S.; Sostak, O. R. 2009. Preservation of healthy and
harmonious residential and work environment during urban developent,
International Journal of Strategic Property Management 13(4): 339-357.
doi:10.3846/1648-715X.2009.13.339-357
Nollke, M. 2007. Kaip iveikti neapibreztuma: optimaliu sprendime
priemimo budai [How to overcome uncertainty: methods for optimal
decisions]. [cited 2 April 2008]. Available from Internet:
<http://www.elitarium.
ru/2007/01/09/tekhniki_vyrabotki_optimalnykh_reshenijj. html>.
Park, M.; Chu, Y.; Lee, H.-S.; Kim, W. 2009. Evaluation methods for
construction projects, Journal of Civil Engineering and Management
15(4): 349-359. doi:10.3846/1392-3730.2009.15.349-359
Petrovic, J.; Ivkovic, I.; Vujacic, I.; Zezelj, S. 2009.
Possibilities of buses on alternative fuel in public urban transport in
elgrade, Technological and Economic Development of Economy 15(1): 78-89.
doi:10.3846/1392-8619.2009.15.78-89
Ribeiro, L. F. 2008. Urban regeneration economics: The case of
Lisbon's old downtown, International Journal of Strategic Property
Management 12(3): 203-213. doi:10.3846/1648-715X.2008.12.203-213
Ross Quinlan, J. 1993. C 4.5: Programs for Machine learning. Morgan
Kaufmann Publishers, Inc.
Sostak, O. R.; Kutut, V. 2009. Neteisetos statybi pletros tyrimas
Kursiu nerijos nacionaliniame parke [Investigation of expansion of
illegal construction in the national park of Curonian spit), Verslas:
teorija ir praktika [Business: Theory and Practice] 10(3): 223-232.
doi:10.3846/1648-0627.2009.10.223-232
Taha, H. A. 1997. Operations research: An introduction. 6th
Edition. Prentice Hall.
The Supreme Administrative Court of Lithuania. 2006. Lietuvos
vyriausiojo administracinio teismo 2006 m. vasario 20 d. sprendimas
administracineje byloje pareiskejai A. S., B. S. ir T. Z. pries Vilniaus
m. savivaldybes administracija, Nr. [A.sup.11]-792/2006 [The resolution
of the Supreme Administrative Court of Lithuania of 20 February 2006 in
the administrative case the Applicants A. S., B. S. and T. Z. vs. the
Administration of Vilnius City Municipality, No. [A.sup.11]-792/2006].
[cited 25 September 2007]. Available from Internet:
<http://www.lvat.lt/ Default.aspx?item=nutart&lang=1>.
The Supreme Administrative Court of Lithuania. 2007a. Lietuvos
vyriausiojo administracinio teismo 2007 m. sausio 19 d. nutartis
administracineje byloje pareiskejai T. Z. pries Vilniaus m. savivaldybes
administracija, Nr. [A.sup.3]-64-07 [The judgement of the Supreme
Administrative Court of Lithuania of 19 January 2007 in the
administrative case The Applicant T. Z. vs. the Administration of
Vilnius City Municipality, No. [A.sup.3]-64-07]. [cited 25 September
2007]. Available from Internet: <http://www.lvat.lt/Default.
aspx?item=nutart&lang=1>.
The Supreme Administrative Court of Lithuania. 2007b. Lietuvos
vyriausiojo administracinio teismo 2007 m. sausio 26 d. nutartis
administracineje byloje pareiskejai O. S., L. K. pries Vilniaus m.
savivaldybes administracija, Nr. A14-110-07 [The judgement of the
Supreme Administrative Court of Lithuania of 26 January 2007 in the
administrative case The Applicant O.S., L. K vs. the Administration of
Vilnius City Municipality, No. A14-11007]. [cited 25 September 2007].
Available from Internet:
<http://www.lvat.lt/Default.aspx?item=nutart&lang=1>.
Turskis, Z.; Zavadskas, E. K.; Zagorskas, J. 2006. Sustainable city
compactness evaluation on the basis of GIS and ayes rule, International
Journal of Strategic Property Management 10(3): 185-207.
Urbanavieiene, V.; Kaklauskas, A.; Zavadskas, E. K. 2009. The
conceptual model of constructional and real estate negotiation,
International Journal of Strategic Property Management 13(1): 53-70.
doi:10.3846/1648-715X.2009.13.53-70
Viteikiene, M.; Zavadskas, E. K. 2007. Evaluating the
sustainability of Vilnius city residential areas, Journal of Civil
Engineering and Management 13(2): 149-155.
Vrubliauskas, D. 2005. Miesto bendruomeniu vaidmuo tausojant
istorines aplinkos savituma [The role of urban communities in
preservation of distinctive features of historical environment],
Urbanistika ir architektura [Town Planning and Architecture] 29(1):
33-36.
Yang, J.; Shen, G. Q.; Ho, M.; Drew, D. S.; Chan, A. P. C. 2009.
Exploring critical success factors for stakeholder management in
construction Projects, Journal of Civil Engineering and Management
15(4): 337-348. doi:10.3846/1392-3730.2009.15.337-348
Zavadskas, E. K.; Kaklauskas, A.; Vainiunas, P.; Saparauskas, J.
2004. A model of sustainable urban development formation, International
Journal of Strategic Property Management 8(4): 219-229.
Zavadskas, E. K.; Kaklauskas, A.; Turskis, Z.; Kalibatas, D. 2009.
An approach to multi-attribute assessment of indoor environment before
and after refurbishment of dwellings, Journal of Environmental
Engineering and Landscape Management 17(1): 5-11.
doi:10.3846/1648-6897.2009.17.5-11
Zavadskas, E. K.; Kaklauskas, A. 2005. Working out a rational model
of Lithuanian construction industry development, Journal of Business
Economics and Management 6(2): 71-80.
Zavadskas, E. K.; Kaklauskas, A. 2008. Model for Lithuanian
construction industry development, Transformations in Business &
Economics 7(1): 152-168.
Zavadskas, E. K.; Turskis, Z.; Tamosaitiene, J. 2010. Risk
assessment of construction projects, Journal of Civil Engineering and
Management 16(1): 33-46. doi:10.3846/jcem.2010.03
Olga Regina Sostak (1), Sigute Vakriniene (2)
Department of Law, Vilnius Gediminas Technical University,
Sauletekio al. 11, LT-10223 Vilnius, Lithuania
E-mails: (1)
[email protected] (corresponding author); (2)
[email protected]
Received 14 Jun. 2010; accepted 31 Jan. 2011
Olga Regina SOSTAK. A PhD student at the Department of Law, Vilnius
Gedminas Technical University (VGTU). Sauletekio al. 11, LT-10223
Vilnius, Lithuania. MA in Civil Engineering (2006, Vilnius Gediminas
Technical University). Research interests: land planning, construction
investment, decision making, stochastic programming.
Sigute VAKRINIENE. A graduate in mathematics from Vilnius
University (1963). Doctor (1972). Associate Professor at the Faculty of
Fundamental Science, the Department of Mathematical Statistic, Vilnius
Gediminas Technical University, Sauletekio al. 11, LT-10223 Vilnius,
Lithuania. Research interests: operation research-game theory,
stochastic programming.
Table 1. A numerical expression of behaviour strategies for the
investor shown in the tree
No. PROFIT LTL %
1 P = P3 = P4 = LTL 1m * 100%
2 P1 = LTL 500,000 ** 50%
3 P2 = P5 = P9 = LTL 950,000 *** 95%
4 P6 = P11 = P7 = LTL 980,000 **** 98%
5 P8 = P10 = P12 = LTL 950,000 ***** 95%
6 N = LTL 1 mi ****** -100%
* successful completion of the construction investment project;
** changed project solutions cut the profits by LTL 500,000;
*** a peace treaty is signed with the interested community,
profit decreases by LTL 50,000;
**** the annual litigation expenditures make up LTL 10,000
(2 years), thus profit decreases by LTL 20,000;
***** the annual litigation expenditures make up LTL 10,000
(3 years), plus LTL 20,000 for forensic examinations; thus
profit decreases by LTL 50,000;
****** the construction investment project is cancelled.
Table 2. Optimal investor's strategies calculated using the
programme code developed in the EXEL environment
Situation f ([S.sub.5]) [x.sup.*.sub.5]
[S.sub.5] -25 [x.sub.52] = 1
Situation f ([S.sub.3]) [x.sup.*.sub.3]
[S.sub.3] -25 [x.sub.32] = 1
Situation f ([S.sub.4]) [x.sup.*.sub.4]
[S.sub.4] 950 [x.sub.42] = 1
Situation f ([S.sub.2]) [x.sup.*.sub.2]
[S.sub.2] 950 [x.sub.21] = 1
Situation f ([S.sub.1]) [x.sup.*.sub.1]
[S.sub.1] 968.5 [x.sub.13] = 1