首页    期刊浏览 2024年11月30日 星期六
登录注册

文章基本信息

  • 标题:Schedule contingency analysis for transit projects using a simulation approach.
  • 作者:Gurgun, Asli Pelin ; Zhang, Ye ; Touran, Ali
  • 期刊名称:Journal of Civil Engineering and Management
  • 印刷版ISSN:1392-3730
  • 出版年度:2013
  • 期号:August
  • 语种:English
  • 出版社:Vilnius Gediminas Technical University
  • 摘要:Schedule delays and cost overruns are challenging for large-scale construction projects with long durations. Uncertainties embedded in such projects affect both schedule and cost (Tseng et al. 2009). Project delays are common in practice and the amount of delay vary with the nature of the project. In construction, delay could be defined as the time overrun either beyond completion date specified in a contract, or beyond the date that parties agreed upon delivery of a project (Assaf, Al-Hejji 2006). The delays are usually accompanied by cost overruns and the problem is experienced by both developed and developing countries (Kaliba et al. 2009). Cost overrun and time overrun generally result from factors that occur at various phases of the project life cycle (Bhargava et al. 2010). Delays in construction projects are a universal phenomenon and develop slowly during the course of the work (Ahmed et al. 2003). Causes of delay in large construction projects, average of time overrun is between 10% and 30% of original duration (Assaf, Al-Hejji 2006).
  • 关键词:Contingency theory (Management);Industrial project management;Local transit;Project management

Schedule contingency analysis for transit projects using a simulation approach.


Gurgun, Asli Pelin ; Zhang, Ye ; Touran, Ali 等


Introduction

Schedule delays and cost overruns are challenging for large-scale construction projects with long durations. Uncertainties embedded in such projects affect both schedule and cost (Tseng et al. 2009). Project delays are common in practice and the amount of delay vary with the nature of the project. In construction, delay could be defined as the time overrun either beyond completion date specified in a contract, or beyond the date that parties agreed upon delivery of a project (Assaf, Al-Hejji 2006). The delays are usually accompanied by cost overruns and the problem is experienced by both developed and developing countries (Kaliba et al. 2009). Cost overrun and time overrun generally result from factors that occur at various phases of the project life cycle (Bhargava et al. 2010). Delays in construction projects are a universal phenomenon and develop slowly during the course of the work (Ahmed et al. 2003). Causes of delay in large construction projects, average of time overrun is between 10% and 30% of original duration (Assaf, Al-Hejji 2006).

It is clear that the complex nature and immense size of the large-scale projects require effective planning (Capka 2004). Project managers should know the probability of time overrun in order to take necessary corrective actions. One obvious planning approach is to use this information to include sufficient contingency for the project schedule. Other corrective actions may include but not limited to a change of project delivery method (Design Build vs Design Bid Build, etc.), use of new equipment or technology, redrafting dispute resolution procedures and expediting construction permits. Therefore, a distinct need has emerged to develop facilitated methods for evaluating the probability of construction time overruns (Luu et al. 2009).

The causes of undesired growths in schedule and cost have attracted construction management researchers worldwide and many reports and research studies can be found in the literature. The issue of optimism bias in organizational dynamics in construction and concluded that it is imperative to have explicit and systematic evaluation methods to achieve large-scale projects' objectives (Son, Rojas 2011).

[FIGURE 1 OMITTED]

Transportation projects are typical candidates that deserve thorough investigations for possible reasons of both schedule and cost growths. This twofold issue has been investigated at some depth (Bakshi, Touran 2009). It has been shown that there are many reasons for schedule delays and cost overruns including optimistic original estimates, lack of scope definition at the start of the project, increase in scope during project development phase due to pressure from project stakeholders, errors in estimation and lack of appropriate contingency budget (Booz Allen Hamilton Inc. 2005). In many construction projects, the owner plans for unexpected events that may affect project cost by adding a contingency to the estimated cost (Touran 2003). If the contingency is overestimated and allocated, the use of capital may be deemed inefficient and if it is underestimated, it contributes to increase the probability that the project may fail (Tseng et al. 2009). There are many factors affecting a project performance; disturbances in the supply of materials and equipment, irregular financing, design errors, inclement weather, equipment failures, inefficient contractors, administrative and legal disturbances, etc. (Rogalska, Hejducki 2007), and the risks in several infrastructural projects including road and railroad projects (Lam 1999). Construction delay and overrun is a critical function in construction of public projects and the time required to complete these projects is frequently greater than the time specified in the contract (Al-Momani 2000). It is clear that contingency is critical in scheduling and it can be developed for project schedule as a time buffer that is set aside to cope with uncertainties during project design and construction.

Several quantitative studies have been made to determine the project duration, schedule contingencies and time overruns; Bayesian belief networks to quantify the probability of construction delays (Luu et al. 2009), real options approach for contingency estimation (Tseng et al. 2009), and three-stage least-squares technique to identify the factors that significantly affect cost and time overruns (Bhargava et al. 2010). Monte Carlo simulation has been used to estimate project contingency and allocate among project activities (Barraza 2011).

The estimation of highway project duration can be made on the basis of past experience or using historical data from similar projects in similar contractual circumstances (Irfan et al. 2011). They investigated the project duration on the basis of variables known at the planning phase such as planned cost, project and contract type, and then developed a model using data from the State of Indiana, spanning the years 1996-2001.

In this study, a probabilistic approach is proposed to calculate schedule contingency in transit projects. The objective is to estimate schedule contingencies for the different level of completion of a project and to achieve the project completion without delay. For this purpose, Joint Confidence Level-Probabilistic Calculator (JCL-PC) approach proposed by Butts and Linton (2009) is adopted as the probabilistic method. The method is modified and used for transportation projects and applied on a set of data obtained from Booz Allen Hamilton Inc. (2005) report.

[FIGURE 2 OMITTED]

[FIGURE 3 OMITTED]

1. JCL-PC approach

In a NASA Cost Estimating Symposium, Butts and Linton (2009) presented an approach, which aims to provide guidelines for developing more accurate cost estimates for NASA projects. The objective is mathematically compensating the optimism bias inherent in NASA cost estimating activity. The optimism bias is handled by looking at the historical performance of projects completed in the past and assume that the effectiveness of the owner agency will be the same as was in previous projects and hence, the same level of cost overruns and schedule delays will happen in future projects. The method is called Joint Confidence Level-Probabilistic Calculator approach (JCL-PC) and is based on the hypothesis that, in the beginning phases of a project, there are many unknown risks and over time the project will have a high probability of exceeding estimated costs and scheduled duration (Butts, Linton 2009).

The JCL-PC equation developed through this holistic algorithm is used to correct the overly optimistic cost and schedule estimates in NASA projects. The aim is to define the probability that the actual cost and schedule will be equal or less than the targeted cost and schedule date. The lessons learned and the benefits obtained by using the proposed method have also been collected (NASA 2010). It basically helps to improve project planning by strengthening risk management through quantification of risks in terms of cost and schedule impacts. Enforcing scheduling best practices, JCL-PC provides the picture of the project ability to achieve cost and schedule goals, and to help the determination of schedule and cost reserves. At any confidence level, the project can be baselined or rebaselined for schedule analysis and rebudgeted for cost analysis.

In this approach, a histogram of cost or schedule overruns is used. A ratio is selected using a simulation approach such that it ensures that the established budget or schedule will not be exceeded with a specified confidence level (Touran, Zhang 2011). It is assumed that as the project progresses, optimism biases will fade and quantifiable risks become clearer.

In order to make the appropriate correction of the estimate at a specified confidence level, a multiplier is calculated in JCL-PC method from Eqn (1). Afterwards, the base estimate is multiplied by this multiplier M and the required budget or schedule is estimated at a specified confidence level:

M = (1 + z) x 1 x (Percent complete); (1)

projects required budget or duration =

M x projectbaseestimate. (2)

In Eqn (1), the percent cost or schedule growth in previously completed similar projects is represented by z value from distribution Z. The sum of percent remaining and percent complete is always 100% and refer to the project under consideration. Base estimate is project schedule (or cost) after all contingencies have been removed. These definitions indicate that as more of the project is completed, the required contingency becomes smaller for the remaining portion. One major issue with the JCL-PC approach is that for various levels of project completion, the delay distribution for z remains the same. It is reasonable to assume that as project approaches completion, the delay distribution should represent smaller values because the magnitude of delays should become smaller. The authors of this paper have modified the JCL-PC approach to account for this important shortcoming of the NASA approach.

2. The proposed approach in the context of transit projects

In this study, 28 transit projects' historical data is used to show the proposed approach for establishing the project's schedule contingency. The data is obtained from Booz Allen Hamilton Inc. report (2005). The following phases of the project lifecycle are reported with their duration and delay data as listed in Table 1. The average duration of all projects for total, preliminary engineering, final design and construction phases are 8.4 years, 2.3 years, 2.7 years and 4.0 years respectively. These are completed transit projects in the United States characterized by three different mode types; heavy rail, light rail and bus way.

Project development phases can be defined as:

* Preliminary Engineering (PE)/Final Environmental Impact Statement (FEIS);

* Final Design (FD), which is at the end of design effort in traditional design-bid-build contracts and before going to bid;

* Construction.

Since the schedule growth is available for this set of projects, it is possible to construct the histogram of the distribution of schedule growth at the end of construction phase which actually reflects the real project completion times with delays (Fig. 1). It shows that the average schedule growth is 34% of the original duration and the standard deviation of the schedule growth is 22% (Fig. 1). Using Chi-square test of goodness of fit, a Normal Distribution is fitted to this data set.

The means of cumulative schedule growths are then calculated and the schedule contingency amount at the end of each phase is determined. Afterwards, these values are mapped against percent completions for all phases. It is assumed for the purpose of this study that PE/FEIS, FD and Construction phases refer to 5%, 15% and 100% completions respectively and the mapping is conducted for each phase independently (Touran, Zhang 2011). The average schedule contingencies at the end of PE/FEIS, FD and Construction phases are determined as 44%, 13% and 0% respectively as shown in Table 2. Three fitted sets of data against percent completions (0%, 5%, 15% and 100%) are shown in Figures 2 (a-c).

The other percent completion levels can be estimated by using the mean lines of schedule growth at the end of each phase (u) which are fitted according to the data points expressed above and calculated depending on the corresponding phase interval.

The separate equations for determining the mean values for the PE/FEIS, FD and Construction phases are expressed below in Eqns (3-5):

[[mu].sub.PE/FEIS] = -11.122x + 1; (3)

[[mu].sub.FD] = -3.1615x + 0.602; (4)

[[mu].sub.Construction] = -1503x + 0: 1503, (5)

where x is percent completion for the project, expressed in decimal format.

Eqns (3), (4) and (5) can be used to calculate the means of schedule contingency remaining at a given percent completion between 0-0.05 (PE/FEIS), 0.05-0.15 (FD) and 0.15-1 (Construction) respectively, assuming linear changes in delay during each of these phases.

For different completion percentages, the appropriate normal distribution value is used to determine the values of M which is the JCL-PC multiplier (Eqn 1). A distribution for M is simulated for each percentage point and then used to calculate the value of M for the specified confidence levels as proposed by Butts and Linton (2009). The amount of the schedule growth at a given percent completion is then determined by multiplying the total schedule contingency value (obtained by using JCL-PC multiplier) and the schedule contingency remaining at that stage. A sample table is provided in Table 3 in order to show the notations that are used in the calculations.

3. Application

In order to use the lines fitted, a hypothetical transit project is considered and it is assumed that the owner wants to establish a schedule contingency at different confidence levels as a percentage of base duration. Base duration is the established project duration excluding all contingencies. If the estimate is prepared at the end of PE/FEIS phase (approximately 5% completion), the simulation results in Table 5 show that 18.5%, 21.3%, 24.8% schedule contingency is determined (as the percentage of the base estimate) with a probability of 65%, 75% and 85%, respectively. If this estimate is made for 50% completion, then the amount will be about 1.8%, 2.6% and 3.5% of the base duration, respectively. It is obvious that as the project progresses, the schedule contingency that should be added to the base estimate decreases. This pattern is observed in simulation results and it is shown as an example in Figure 3. The JCL notations used for simulation in the application and JCL multipliers determined by simulation are presented in Table 4. All of the simulation results including these values generated for different levels of project completions vs. probabilities are shown in Table 5. It should be noted that the aim of the proposed method is to establish sufficient contingency to ensure the project completion without any delay.

Summary and conclusions

In this paper, a methodology is proposed to analyze the project schedule contingency for transit projects by considering various stages of project completion for different contingency levels. It considers the usage of schedule contingency as the project progresses. It takes into account the variations of both the mean values and standard deviations of time extensions at different percent completions. Since the calculations are based on actual data set of transit projects, the schedule growth rates can be obtained more accurately for desired confidence levels. This would provide opportunity to all project parties to make more realistic estimates in their schedules and plans during various stages of the project; and be prepared to take necessary action in case the available schedule contingency falls below reasonable levels.

doi: 10.3846/13923730.2013.768542

References

Ahmed, S. M.; Azhar, S.; Kappagantula, P.; Gollapudi, D. 2003. Delays in construction: a brief study of Florida construction industry, in ASC Proceedings of the 39th Annual Conference, 10-12 April, 2003, Clemson University, Clemson, South Carolina, 257-266.

Al-Momani, A. H. 2000. Construction delay: a quantitative analysis, international Journal of Project Management 18(1): 51-59. http://dx.doi.org/10.1016/S0263-7863(98)00060-X

Assaf, S. A.; Al-Hejji, S. 2006. Causes of delay in large construction projects, international Journal of Project Management 24(4): 349-357. http://dx.doi.org/10.1016/j.ijproman.2005.11.010

Bakshi, P.; Touran, A. 2009. Comparison of current probabilistic approaches for budget estimate for transportation projects, in Proc. of the 7th international Probabilistic Workshop, 2009, Delft, Netherlands, 479-490.

Barraza, G. A. 2011. Probabilistic estimation and allocation of project time contingency, Journal of Construction Engineering and Management ASCE 137(4): 259-265. http://dx.doi.org/10.1061/ (ASCE)CO.1943-7862. 0000280

Bhargava, A.; Anastasopoulos, P. C.; Labi, S.; Sinha, K. C.; Mannering, F. L. 2010. Three-stage least-squares analysis of time and cost overruns in construction contracts, Journal of Construction Engineering and Management ASCE 136(11): 1207-1218. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862. 0000225

Booz Allen Hamilton, Inc. 2005. Managing capital costs for major federally funded public transportation projects. TCRP web-only document 31. Washington, DC: TRB.

Butts, G.; Linton, K. 2009. The joint confidence level paradox a--history of denial, in NASA Cost Symposium. Presentation paper, Kansas City, MO, 109.

Capka, J. R. 2004. Megaprojects--they are a different breed [online], [cited 27 June 2011]. Available from Internet: http://www.fhwa.dot.gov/publications/publicroads/04jul/01.cfm.

Irfan, M.; Khurshid, B. M.; Anastasopoulos, P.; Labi, S.; Moavenzadeh, F. 2011. Planning-stage estimation of highway project duration on the basis of anticipated project cost, project type and contract type, international Journal of Project Management 29(1): 78-92. http://dx.doi.org/10.1016/j.ijproman.2010.01.001

Kaliba, C.; Muya, M.; Mumba, K. 2009. Cost escalation and schedule delays in road construction projects in Zambia, international Journal of Project Management 27(5): 522-531. http://dx.doi.org/10.1016/j.ijproman.2008.07.003

Lam, P. T. I. 1999. A sectoral review of risks associated with major infrastructure projects, international Journal of Project Management 17(2): 77-87. http://dx.doi.org/10.1016/S0263-7863(98)00017-9

Luu, V. T.; Kim, S.; Tuan, N. V.; Ogunlana, S. O. 2009. Quantifying schedule risk in construction projects using Bayesian belief networks, international Journal of Project Management 27(1): 39-50. http://dx.doi.org/10.1016/j.ijproman.2008.03.003

NASA. 2010. Joint confidence level (JCL) FAQ [online], [cited 27 June 2011]. Available from Internet: http://www.nasa.gov/pdf/394931main_JCL_FAQ_10_12_09.pdf.

Rogalska, M.; Hejducki, Z. 2007. Time buffers in construction process scheduling, Journal of Civil Engineering and Management 13(2): 143-148.

Son, J.; Rojas, E. M. 2011. Impact of optimism bias regarding organizational dynamics on project planning and control, Journal of Construction Engineering and Management ASCE 137(2): 147-157. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000260

Touran, A. 2003. Probabilistic model for cost contingency, Journal of Construction Engineering and Management ASCE 129(3): 280-284. http://dx.doi.org/10.1061/(ASCE)0733-9364(2003) 129:3(280)

Touran, A.; Zhang, Y. 2011. Contingency vs. percent completion in infrastructure projects, in Proc. of Modern Methods and Advances in Structural Engineering and Construction, ISEC-6, 2011, Zurich, Switzerland, 99-104.

Tseng, C.-L.; Zhao, T.; Fu, C. C. 2009. Contingency estimation using a real options approach, Construction Management and Economics 27(11): 1073-1087. http://dx.doi.org/10.1080/01446190903222411

Asli Pelin Gurgun (a), Ye Zhang (b), Ali Touran (b)

(a) Department of Civil Engineering, Okan University, Tuzla Campus, 34959, Akfirat-Tuzla, Istanbul Turkey

(b) Department of Civil and Environmental Engineering, Northeastern University, 360 Huntington Avenue,

Received 27 Jun. 2011; accepted 2 Nov. 2011

Corresponding author: Asli Pelin Gurgun

E-mail: [email protected]

Asli Pelin GURGUN. She is an Assistant Professor in the Department of Civil Engineering at Okan University, in Istanbul, Turkey. Her research interests cover risk analysis, risk management, simulation, decision making, project management, project delivery systems green construction.

Ye ZHANG. He is a PhD candidate in the Department of Civil & Environmental Engineering, Northeastern University, Boston, USA. His research interests cover project management, construction management, risk analysis and management, simulation, and cost estimating.

Ali TOURAN. He is a Professor in the Department of Civil and Environmental Engineering at Northeastern University, in Boston, USA, where he is the coordinator of the graduate program in Construction Management. He is the author or co-author of more than 90 technical papers in journals and conference proceedings. Dr Touran's research is in the area of risk analysis of infrastructure projects, simulation, and project delivery systems.
Table 1. Case study project schedule analysis (phases are
expressed in "years")

                                  Original project duration
                                  by phase (years)
A         B                       C          D        E

Project                           PE/
Number    Case study projects     FEIS       FD       Construction

1         Atlanta North Line      1          3        6
          Extension
2         Boston Old Colony       1          6        2
          Rehabilitation
3         Boston Silver Line      1          1        10
          (Phase 1)
4         Chicago Southwest       2          3        3
          Extension
5         Dallas South Oak        2          1        3
          Cliff Extension
6         Denver Southwest        4          1        3
          Line
7         Los Angeles Red                    5        1
          Line MOS 1
8         Los Angeles Red                    7        4
          Line MOS 2
9         Los Angeles Red                    10       5
          Line MOS 3
10        Minneapolis             6          1        4
          Hiawatha Line
11        New-Jersey Hudson-      3          1        5
          Bergen MOS1
12        New York 63rd           3          2        7
          Street Connector
13        Pasadena Gold Line      3          4        3
14        Pittsburgh Airport      2          1        7
          Busway (Phase 1)
15        Portland Airport                   2        4
          MAX Extension
16        PortlandBanfield                   3        1
          Corridor
17        Portland Interstate     1          2        2
            MAX
18        Portland Westside/      1          3        4
             Hillsboro MAX
19        Salt Lake North-        1          3        1
          South Line
20        San Fransisco SFO       4          1        6
            Airport Exten.
21        San Juan Tren Urbano    3          1        8
22        Santa Clara Capitol                1        4
          Line
23        Santa Clara Tasman      3          4        2
            East Line
24        Santa Clara Tasman      1          3        3
          West Line
25        Santa Clara Vasona                 1        5
          Line
26        Seattle Busway Tunnel   1          3        3
27        St Louis Saint          3          1        2
            Clair Corridor
28        Washington Largo        3          1        4
          Extension

                                  Approximate project delay by
                                  phase (years)
A         F                       G          H        I

          Original total
          project duration        PE/
Project   (Col.C + Col.D +        FEIS       FD       Construction
Number    Col.E)                  delay      delay    delay

1         10                      0          0        4

2         9                       1          2        0

3         12                      4          0        4

4         8                       0          1        2

5         6                       1          2        -1

6         8                       4          0        0

7         6                                  1        2

8         11                                 2        2

9         15                                 2        1

10        11                      3          1        1

11        9                       1          1        2

12        12                      3          1        0

13        10                      2          4        0
14        10                      4          3        0

15        6                                  0        0

16        4                                  2        0
17        5                       0          0        0
18        8                       1          3        0
19        5                       2          0        -1
20        11                      2          0        2
21        12                      2          1        4
22        5                                  0        0
23        9                       2          1        0
24        7                       2          0        -1
25        6                                  0        0
26        7                       1          3        0
27        6                       0          0        0
28        8                       2          -1       0

                                  Mean: 34
                                  Standard deviation 22

A         J                  K          L
                             Final      Schedule
                             duration   overrun changes
                             (Col.F +   for total
          Total project      Col.G +    project %
Project   delay (Col.G +     Col.H +    (Col.K-
Number    Col.H + Col.I)     Col.I)     Col.F)/(Col.F)

1         4                  14         40

2         3                  12         33

3         8                  20         67

4         3                  11         38

5         2                  8          33

6         4                  12         50

7         3                  9          50

8         4                  15         36

9         3                  18         20

10        5                  16         45

11        4                  13         44

12        4                  16         33

13        6                  16         60
14        7                  17         70

15        0                  6          0

16        2                  6          50
17        0                  5          0
18        4                  12         50
19        1                  6          20
20        4                  15         36
21        7                  19         58
22        0                  5          0
23        3                  12         33
24        1                  8          14
25        0                  6          0
26        7                  11         57
27        0                  6          0
28        1                  9          13

Table 2. Schedule contingencies at the end of each phase

                           Delays in phases (years)
A            B             C                 D               E

                                                             Total
Project      PE/                                             project
Number       FEIS          FD                Construction    delay

1            0             0                 4               4
2            1             2                 0               3
3            4             0                 4               8
4            0             1                 2               3
5            1             2                 -1              2
6            4             0                 0               4
7                          1                 2               3
8                          2                 2               4
9                          2                 1               3
10           3             1                 1               5
11           1             1                 2               4
12           3             1                 0               4
13           2             4                 0               6
14           4             3                 0               7
15                         0                 0               0
16                         2                 0               2
17           0             0                 0               0
18           1             3                 0               4
19           2             0                 -1              1
20           2             0                 2               4
21           2             1                 4               7
22                         0                 0               0
23           2             1                 0               3
24           2             0                 -1              1
25                         0                 0               0
26           1             3                 0               4
27           0             0                 0               0
28           2             -1                0               1

             Cumulative phase delay/total project delay
A            F             G                 H

             PE/FEIS
Project      (Col.B/       FD ([Col.B +      Construction ([Col.B+
Number       Col.E) %      Col.C]/Col.E) %   Col.C + Col.D]/Col.E) %

1            0             0                 100
2            33            100               100
3            50            50                100
4            0             33                100
5            50            150               100
6            100           100               100
7            0             33                100
8            0             50                100
9            0             67                100
10           60            80                100
11           25            50                100
12           75            100               100
13           33            100               100
14           57            100               100
15
16           0             100               100
17
18           25            100               100
19           200           200               100
20           50            50                100
21           29            43                100
22
23           67            100               100
24           200           200               100
25
26           25            100               100
27
28           200           100               100

             Schedule contingency at the end of phases
A            I             J                 K

Project      PE/FEIS                         Construction
Number       (1-Col.F) %   FD (1-Col.G) %    (1-Col.H) %

1            100           100               0
2            67            0                 0
3            50            50                0
4            100           67                0
5            50            - 50              0
6            0             0                 0
7            100           67                0
8            100           50                0
9            100           33                0
10           40            20                0
11           75            50                0
12           25            0                 0
13           67            0                 0
14           43            0                 0
15
16           100           0                 0
17
18           75            0                 0
19           - 100         - 100             0
20           50            50                0
21           71            57                0
22
23           33            0                 0
24           - 100         - 100             0
25
26           75            0                 0
27
28           - 100         0                 0

Notes: Mean 44, 13 and 0.

Table 3. JCL-PC notations used for simulation

A              B                     C

% completion   Schedule contigency   Assume no risks occur
                 remaining

0              Values obtained by    1
                 using Eq. 3, 4
                 and 5

A              D                  E            F

% completion   Normal risk dist.  % project    % project
                                    complete     remaining

0              Risk Normal        0            1- CoLE
                 (mean:SD)+1

A              G                 H               I

% completion   JCL-PC Mult.      Schedule        Schedule
                                   contingency     contingency x
                                                   contingency
                                                   remaining

0              Risk Discrete     Col.G-1         Col.H x Col.B
                 (Col.C;Col.D:
                  Col.E;Col.F)

Notes: Col. A: a given percent complete; Col. B: cumulative schedule
contingency at the end of given percent completion from real data
calculated by fitted lines in Figures 2 (a c) using Eqns (3 5);
Col. C: onstant assuming that no unknown risk would occur
at the given percent completion; Col. D: simulated values using a
simulation software (e.g. @Risk) with schedule growth mean and
standard deviation values from real data, which are 34%
and 0.22, respectively; Col. E: a given percent complete;
Col. F: % project remaining at that stage; Col. G: simulated
values for M (JCL-PC multiplier); Col. H: total schedule contingency
at the end of a given percent completion; Col. I: the amount of
schedule contingency for the rest of the project

Table 4. JCL-PC notations used for simulation in the application

A            B                         C           D

                                       Assume no   Normal risk
                                       unknown      dist. (mean:
%            Schedule contingency      risks       0.34, SD:
completion   remaining                 occur       0.22)

             -11.12 xCol.A + 1                     = RiskNormal
             (for PE/FEIS)--3.1615 x               (0.34;0.22)+ 1
             Col.A + 0.602 (for FD) -
             0.1503 x Col.A + 0.1503
             (for construction)

0            1.00                      1           1.3401
5            0.44                      1           1.3401
10           0.29                      1           1.3401
15           0.13                      1           1.3401
20           0.12                      1           1.3401
25           0.11                      1           1.3401
30           0.11                      1           1.3401
35           0.10                      1           1.3401
40           0.09                      1           1.3401
45           0.08                      1           1.3401
50           0.08                      1           1.3401
55           0.07                      1           1.3401
60           0.06                      1           1.3401
65           0.05                      1           1.3401
70           0.05                      1           1.3401
75           0.04                      1           1.3401
80           0.03                      1           1.3401
85           0.02                      1           1.3401
90           0.02                      1           1.3401
95           0.01                      1           1.3401
100          0                         1           1.3401

A            E                         F           G

%            % project                 % project
completion   completed                 remaining   JCL-PC Mult.

                                       1--ColE     = RiskDiscrete
                                                   (Col.C:Col.D;Col.E;
                                                   Col.F)

0            0                         100         1.3401
5            5                         95          1.3401
10           10                        90          1.3401
15           15                        85          1.3401
20           20                        80          1.3401
25           25                        75          1.3401
30           30                        70          1.3401
35           35                        65          1.3401
40           40                        60          1.3401
45           45                        55          1.3401
50           50                        50          1
55           55                        45          1
60           60                        40          1
65           65                        35          1
70           70                        30          1
75           75                        25          1
80           80                        20          1
85           85                        15          1
90           90                        10          1
95           95                        5           1
100          100                       0           1

A            H                         I

                                       Schedule
%            Schedule                  contingency x
completion   contingency               contingency remaining

             = Col.G-1                 = Col.Hx Col.B

0            0.3401                    0.3401
5            0.3401                    0.1510
10           0.3401                    0.0972
15           0.3401                    0.0435
20           0.3401                    0.0409
25           0.3401                    0.0383
30           0.3401                    0.0358
35           0.3401                    0.0332
40           0.3401                    0.0307
45           0.3401                    0.0281
50           0                         0
55           0                         0
60           0                         0
65           0                         0
70           0                         0
75           0                         0
80           0                         0
85           0                         0
90           0                         0
95           0                         0
100          0                         0

Table 5. Simulated unused contingency values as a percent of base
duration using normal distribution

Project
completion %      5%    10%   15%    20%    25%    30%    35%

0               - 1.5   6.4   11.6   15.9   19.4   22.7   25.7
5               - 0.6   0.0   3.0    5.5    7.5    9.1    10.7
10              - 0.3   0.0   0.0    2.2    3.7    4.9    6.0
15               0.0    0.0   0.0    0.1    1.2    1.8    2.3
20               0.0    0.0   0.0    0.0    0.1    1.2    1.8
25               0.0    0.0   0.0    0.0    0.0    0.1    1.0
30               0.0    0.0   0.0    0.0    0.0    0.0    0.3
35               0.0    0.0   0.0    0.0    0.0    0.0    0.0
40               0.0    0.0   0.0    0.0    0.0    0.0    0.0
45               0.0    0.0   0.0    0.0    0.0    0.0    0.0
50               0.0    0.0   0.0    0.0    0.0    0.0    0.0
55               0.0    0.0   0.0    0.0    0.0    0.0    0.0
60               0.0    0.0   0.0    0.0    0.0    0.0    0.0
65               0.0    0.0   0.0    0.0    0.0    0.0    0.0
70               0.0    0.0   0.0    0.0    0.0    0.0    0.0
75               0.0    0.0   0.0    0.0    0.0    0.0    0.0
80               0.0    0.0   0.0    0.0    0.0    0.0    0.0
85               0.0    0.0   0.0    0.0    0.0    0.0    0.0
90               0.0    0.0   0.0    0.0    0.0    0.0    0.0
95               0.0    0.0   0.0    0.0    0.0    0.0    0.0
100              0.0    0.0   0.0    0.0    0.0    0.0    0.0

Project
completion %     40%    45%   50%    55%    60%    65%    70%

0               28.6    31.3  34.0   36.7   39.5   42.3   45.3
5               12.0    13.3  14.5   15.8   17.1   18.5   19.8
10               7.0    8.0   8.9    9.7    10.6   11.5   12.4
15               2.8    3.2   3.7    4.1    4.6    4.9    5.4
20               2.4    2.9   3.3    3.7    4.1    4.5    4.9
25               1.7    2.3   2.7    3.2    3.6    4.0    4.4
30               1.2    1.8   2.3    2.8    3.2    3.6    4.0
35               0.2    1.1   1.8    2.3    2.7    3.1    3.5
40               0.0    0.4   1.1    1.8    2.2    2.7    3.1
45               0.0    0.0   0.5    1.2    1.7    2.2    2.6
50               0.0    0.0   0.0    0.5    1.2    1.8    2.3
55               0.0    0.0   0.0    0.0    0.5    1.2    1.7
60               0.0    0.0   0.0    0.0    0.0    0.6    1.2
65               0.0    0.0   0.0    0.0    0.0    0.0    0.6
70               0.0    0.0   0.0    0.0    0.0    0.0    0.0
75               0.0    0.0   0.0    0.0    0.0    0.0    0.0
80               0.0    0.0   0.0    0.0    0.0    0.0    0.0
85               0.0    0.0   0.0    0.0    0.0    0.0    0.0
90               0.0    0.0   0.0    0.0    0.0    0.0    0.0
95               0.0    0.0   0.0    0.0    0.0    0.0    0.0
100              0.0    0.0   0.0    0.0    0.0    0.0    0.0

Project
completion %    75%     80%   85%    90%    95%

0               48.5    52.1  56.3   61.6   69.3
5               21.3    22.9  24.8   27.1   30.5
10              13.5    14.5  15.7   17.1   19.8
15               5.9    6.3   6.9    7.7    8.6
20               5.3    5.8   6.3    7.0    8.1
25               4.9    5.3   5.8    6.5    7.5
30               4.4    4.9   5.4    6.0    7.0
35               3.9    4.3   4.9    5.5    6.3
40               3.4    3.8   4.3    4.9    5.8
45               3.0    3.4   3.8    4.3    5.2
50               2.6    3.0   3.5    4.0    4.6
55               2.1    2.5   3.0    3.4    4.2
60               1.6    2.0   2.4    2.9    3.6
65               1.1    1.5   2.1    2.5    2.9
70               0.5    1.0   1.4    1.9    2.5
75               0.0    0.6   1.0    1.5    1.9
80               0.0    0.0   0.6    1.0    1.4
85               0.0    0.0   0.0    0.7    1.0
90               0.0    0.0   0.0    0.0    0.6
95               0.0    0.0   0.0    0.0    0.0
100              0.0    0.0   0.0    0.0    0.0
联系我们|关于我们|网站声明
国家哲学社会科学文献中心版权所有