Monitoring of interactions of a monumental historical complex located on an earth embankment.
Miedzialowski, Czeslaw ; Malesza, Jaroslaw ; Malesza, Mikolaj 等
Introduction
To preserve historic structures for future generations, the
engineer often needs to disregard the inflexibility of contemporary
standards and norms imposed by law and must travel back in time to fully
understand the context in which the structure was conceived, designed,
constructed and maintained (Izquiredo-Encarnacion 2012; Pfeifer,
Cankurtaran 2013; Perez Galvez et al. 2013). New technologies applied
within an engineering project including meticulous investigations, model
analysis and execution process required to create large underground
spaces and involving geotechnical survey, consolidation and
strengthening of the substratum are presented in Mahmood (2012),
Goeppert and Haspel (2013).
In the course of time, partitions of historic masonry structures
crack forming macro-elements, which makes it impossible to produce a
numerical model of the structure and simulate its behaviour. A numerical
model can only show the results based on real data. On the other hand,
each historic masonry structure must be examined using extensive
historic studies. Instead of virtual analytical modelling methods,
historic masonry reconstructions require deep historic knowledge of the
subject (Blasi, Ottoni 2012; Bednarz et al. 2011; Sliaupa 2013).
Some cracked masonry structures can be repaired using low
segregation grouts with hydraulic lime to improve the rheological
parameters through reduction of plastic viscosity and yield stress, as
proposed in Baltazar et al. (2012), Bochen and Labus (2013). The impact
of environmental conditions on the durability of brick masonry and the
necessary measures of masonry repair to be undertaken are discussed in
Hamid and Orphy (2012), Silva et al. (2013). Changing environmental
conditions such as wetting/drying and salt crystallization resulting
from the rise and fall of ground water as well as relative humidity play
a destructive role in the deterioration of the quality leading to
excessive destruction of masonry walls. According to Roca (2012), on the
one hand, structural modelling enables computer simulation of the
effects of technological interventions on the structural response thus
verifying and comparing their efficiency. Besides, monitoring carried
out during and after the intervention verifies adequate performance of
strengthening.
In the study of historic constructions, three different phases
should be considered, i.e. diagnosis, safety evaluation and design of
intervention (Roca 2006; Quist et al. 2013). They provide concepts and
methodological guidelines to be observed in order to obtain
scientifically derived conclusions on the true conditions, safety and
needs of repair or strengthening. Diversified vertical settlements
require accurate techniques for displacement monitoring. A monitoring
system based on the principles of communicating vessels, emphasizing the
relation with the structural behaviour of buildings is presented in
Scherenmans and Van Balen (2006).
The papers (i.e. Ramos et al. 2006) present a way of assessing
damages in masonry structures at early stages of degradation, finding
adequate correspondence between dynamic behaviour and internal crack
growth.
Limit analysis of historic massive masonry structures with rigid
block models was successfully used in the works (Orduna et al. 2006;
Korkanc 2013; Lott 2013), and the results obtained were comparable to
those of micro-models. According to Basu (2006), systematic analysis and
modern investigative techniques are of great help ascertaining the
extent and cause of damages. In a historic building, diagnostic analysis
is of utmost importance to protect structures from further deterioration
or ultimate damage. In some cases of monumental buildings, structural
aspects and safety factors take precedence over sentiments and myths
linked with cultural aspects.
Damage of masonry structures mainly relates to cracks, foundation
settlements, material degradation and displacements (Tarque et al.
2013). Localized cracks usually split structures into macro-blocks.
Damage methods (Ramos, Lourenco 2008; Silva et al. 2014) were applied to
experimental models, in which progressive and controlled damage
scenarios were induced by controlled loads.
An acoustic emission technique was used (Carpinteri et al. 2008) to
evaluate the time dependence of damage because cracking, in fact, is
accompanied by the emission of elastic waves which propagate inside the
body of material.
As can be seen from the presented review of the literature on the
subject, the discussed problems are very significant in practice but, at
the same time, they pose some technical difficulties due to historical,
structural and technological complexity of renovating and strengthening
activities. Besides, some other aspects of the problems specifically
concerning the foundation and location of large historic complexes on
man backfilled hills have not been fully described in literature
sources.
Underground constructions always produce settlements that may
affect the architectural heritage (Camos et al. 2012). The prediction of
damage to buildings induced by ground movements is an essential task
when designing underground elements. Diversified settlements of historic
buildings are caused by various subsoil factors influencing correct
decisions about remedial measures (Meli, Sanchez-Ramirez 2006).
Excessive settlement of the structure creates problems to building
operation despite of small structural harm.
The present paper is devoted to the technical history of one of the
oldest historic complexes. It emphasizes how hasty and inconsiderate
decisions from a technical point of view produce undesired effects in
the form of accelerated degradation of structure and buildings. Wigry
Hill is located in Suwalki region in the north eastern part of Poland.
The Hill is located on the peninsula of the Wigry Lake, the former
island of the lake. Twenty-eight buildings and engineering structures
constitute the former Monastery and remains one of the most precious
historic heritage sites in this part of Poland (Wigry 1959). Figure 1
shows an aerial view of the Hill with its buildings at present
(Miedzialowski, Malesza 2006). Constructions on the Hill began in 1667,
when King of Poland John Casimir granted an extra fund and permission to
establish a church and monastery following the Camaldolese Rule. The
building site was chosen according to the principles of the eremite
rules that require a location far away from urban centres and transport
routes, a place surrounded by water and forests. Made of timber, first
monastery buildings were destroyed by fire in 1671. A few years later,
in 1678, a new masonry church was erected following the design of
Italian architect Peter Putinni. Camaldolese monks extended their
possessions until the end of their monastic activities in the year 1800.
The Royal House was the last large investment and construction and was
used after its completion as a bishop's residence. Later, in the
following time periods, the Monastery buildings were used for parish
functions; and during the World War I, they were partly adapted for use
as a hospital and in part, as a war camp for prisoners. World War I
brought almost all buildings to ruin, as seen in Figure 2. Only the
church, foundations and the underground structures remained.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
In the interwar period, the Roman-Catholic Church building and
hermitages were reconstructed. The Chancellor Chapel and Royal House
cannot be seen at the main entrance to the church as they had been
destroyed during the war.
During the World War II, the reconstructed church building was
destroyed again by artillery fire, which can be seen in Figure 3.
After the World War II in 1949, the reconstruction process of the
Wigry Hill buildings was resumed starting from the church and presbytery
while the remaining buildings were brought back to life later, starting
1958. They were rebuilt on the old foundations and underground
structures with no detailed inventory or assessment of their technical
state. Likewise, the processes of remedial and reconstruction works
began without any archival and historic sources and documents. The south
western view of the reconstructed church is shown in Figure 4. As can be
seen, there are no buildings at the front of the church and no
hermitages behind.
[FIGURE 3 OMITTED]
[FIGURE 4 OMITTED]
During the two World Wars, the buildings were undergoing
destructions and disassembling and were finally brought to ultimate
devastation.
At present, some reconstructed buildings of the Wigry Hill are used
for religious purposes of the Roman Catholic Church while some other
parts of the complex are used as a Training and Recreation Centre. All
the construction works realized on the Wigry Hill required raising the
level of the ground adjoining the existing buildings as well as the
surrounding terraces using main and intermediary massive retaining
walls. The upper and the bottom terraces with the difference of ground
levels of 6-8 m were constructed in that way.
1. Monitoring and analysis of backfilled earth subbase under the
Monastery buildings
1.1. Sub-base monitoring
Analysis of geologically multilayered substratum of the Hill was
carried out by digging boreholes in accordance with a planned grid of
holes and sections shown in Figure 5. According to the geotechnical
reports, the upper substratum is formed by a backfill of low compaction
especially in the top layers of the Hill.
Some chosen sections of the substratum illustrating its laminated
composite geology are illustrated in Figure 6.
[FIGURE 5 OMITTED]
[FIGURE 6 OMITTED]
Soil analysis, investigations and tests made it possible to
conclude that the multi-layered substratum considered to have been a
backfill was primarily composed of natural mineral sandy soil. Thus, it
appears that the older, originally erected Monastery buildings were foun
ded on non-backfilled soil sub-base. Three basic layers were determined
within the hill laminated soil structure:
--upper layer of mineral non-cohesive and lowcohesive soil with
brick and stone backfill 0.5 to 6.0 m thick with degree of compaction
0.05 to 0.20;
--middle layer composed of older backfill containing mineral
non-cohesive ID = 0.2 to 0.7 and cohesive soil IL = 0.2 to 0.55. This
layer is considered as the bearing stratum;
--finally, the bottom layer composed of medium and coarse sands of
varying compaction laminated with cohesive soil in the form of clay,
i.e. a layer of natural mineral soil.
In the reconstruction process, the existing old foundations
supplemented with new segments were used as required by the user.
Unfortunately, the underground works, foundations, tunnels and retaining
massive walls were reconstructed without required design and inventory
works, which was discovered as a result of later investigations where
all former underground structures were filled with crushed bricks and
debris. Cross-section of the Wigry Hill and existing buildings are shown
in Figure 7a, while the underground galleries are shown in Figure 7b.
[FIGURE 7 OMITTED]
The Wigry Hill soil lacking adequate formation and levelling of the
surrounding terrain as well as proper water and sewage disposal system
was penetrated with precipitation and snowmelt water. In a note made in
the Church inventory in 1800 when some buildings were disassembled, we
can read the following: "retaining walls supporting the hill
backfill are in a poor state particularly those of the west and south
sides where in the result of destroyed drain pipes, rain water percolate
through holes in the walls" (Malesza, Miedzialowski 2006).
The hermitages at the bottom terraces were constructed partly on
the retaining walls and partly on basements filled with crushed bricks
and debris. As a result of non-uniform settlement, the hermitage
buildings were subjected to cracking and were virtually excluded from
use. Destruction and degradation processes are currently observed in all
monastery buildings. The mid-part of the eastern retaining wall
underwent destruction in 1987 (Miedzialowski, Malesza 2008). Some parts
of the walls collapsed while others were displaced due to sewage and
water pressure. Poorly backfilled former drifts and tunnels behind the
retaining walls would collect water and sewage from leaky septic tanks
resulting in increased pressure to the walls. The retaining wall became
displaced outwards. In addition in 1999, greater displacements were
caused by the damaged sewage network running along the retaining walls.
Furthermore, the earthquake that measured 5.3 on the Richter scale
strongly deteriorated cracking and failure state of buildings in 2004.
Initially, main processes of degradation and destruction were
observed in the region of hermitages situated on bottom terraces. The
water and sewage system became leaky and started cracking, which
commenced a process of considerable destruction of the hermitages. The
other buildings and structures also underwent cracking and large
displacements especially around window sills and in corners as well as
in contact zones of adjoined buildings compelling the user to conduct
renewal and repair works on the basis of developed concepts and strategy
of improvement and renovation (Miedzialowski, Malesza 2008).
Reconstruction of the Hill buildings/infrastructure required
raising the ground level of terraces with surrounding main and
subsidiary retaining walls. In that way, the upper and the lower
terraces with the difference of ground levels of 6-8 m were constructed.
Incomplete archival building documentation in possession during the
reconstruction resulted in some irregularities in the static work of
newly reconstructed building structures resting on earlier old
foundations and remaining elements of structures buried in the ground.
Whole post-monastery complex on the island of Wigry lake is
presently used as a recreation centre and the former monk hermitages are
used as hotel apartments. New materials and technologies were applied
within the period of the Monastery complex reconstruction. Main changes
involved securing the stability of the retaining walls and foundations
of hermitages. A static diagram of the former retaining walls with
unloading vaults over gallery reducing the lateral load from earth
pressure and hydrostatic pressure of ground water is shown in Figure 7b.
The basements under the vaults were used in the monastery for stores,
baths and cellars. After the reconstruction, the vaults were demolished
increasing the lateral load due to ground pressure against the retaining
walls. The unloading chambers were used in the reconstruction to
stabilize the overloaded retaining walls, returning to the former idea
of the structures.
1.2. Selected results of stability assessment-measurement report
Five stages of surveying were specified to assess vertical and
horizontal displacements within the Hill. In the first stage of
measurements, twenty-eight bench-marks and datum points and ten feeler
gauges were installed to monitor displacements and cracks in the
structures. Significant vertical displacements from 0.3 to 5.6 mm within
two-years were surveyed from points 1001 to 1039 in the control grid.
The largest displacements in value, i.e. 7.6 mm, were observed at point
1007 of the southern retaining wall and 3.6 mm in the corner of the
northeastern wall.
Inspection and assessment of displacements are shown in Table 1 of
the Garden Tower--1.5 mm, the Royal House--2.0 mm, and the Gate
Keeper's House--1.0 mm pointed towards destructive activities of
water penetrating from leaking water and sewage systems rather than
dynamic influence of earthquakes. The last fifth report was produced
using measurements and surveys after the modernization of the water and
sewage networks, which eliminated the negative influence of the leaking
system that softened and washed-out the sub-base, especially the
backfilled substratum. As many as 143 height and vertical displacement
measurement points including 22 benchmarks and 94 points marked on
buildings and structures with additional 16 stabilized traverse ground
points were spaced across the Hill. Precise levelling electronic
instrument DiNi-11 of 0.3 mm accuracy was used in surveying. The grid
used for measurements of horizontal displacements was composed of 11
polygonal points, 28 feeler gauges and 92 deflection control points of
the retaining walls, out of which 30 points were installed on the
eastern wall, 33 along the southern wall, 23 points marked on the
northern wall and finally 6 gauges - on the Garden Tower. The benchmarks
and some selected surveying points on the lower hermitage terrace are
presented in Figure 8.
[FIGURE 8 OMITTED]
Displacements were measured applying:
--precise levelling method for vertical surveying datum points and
control benchmarks;
--deflection measurements of the southern wall and the hermitages
of the lower terrace applying side levelling method;
--deflection of the northern and the eastern wall applying the side
levelling method;
--horizontal displacements were measured using feeler gauges.
Table 1 presents some selected deflections of the northern
retaining wall.
The relative benchmark stability indicates displacements of -4.5 mm
at points 11 of the Garden Tower and points 19 of the Boiler House.
Hermitages of the lower terraces and the southern wall showed
displacements from +0.9 to -1.3 mm. Cracks in the hermitages were
widened by +0.7 mm. Also, cracks in the wall of the Boiler House widened
from +0.5 to +1.3 mm. The northern retaining wall exposed an increase of
vertical displacements from -0.6 to -1.1 mm and the northern part of the
wall displaced from -0.7 to -1.7 mm. Vertical displacements of the NE of
the corner of the eastern wall achieved -13 mm.
Horizontal deflections and the widths of cracks remain the main
method of horizontal deformation measurements. Significant increase of
the crack widths amounting +0.7 mm was measured in the walls of the
lower hermitages. The northern retaining wall exposed an increase of the
crack widths from +0.2 to +1.7 mm. The southern retaining wall does not
indicate horizontal displacements, while the eastern corner indicates
the displacement of -3 mm in the outward direction. The eastern
retaining wall shows displacements from +3 to +6 mm.
Four years of monitoring have shown that the structures of the
eastern and southern retaining walls and lower terrace hermitages
considered as hazardous in behaviour are generally stable and do not
display any dangerous displacements. Water percolation and infiltration
into soil caused some noticeable vertical displacements of the Garden
Tower, the Boiler Room and horizontal deflection in the northern corner
of the eastern wall only.
2. Analysis and assessment of masonry and concrete structures
constructed on the backfilled earth embankment
All the Monastery buildings have been already reconstructed except
for some auxiliary ones. This can be seen in Figures 1 and 2. At the
same time, a progressive process of degradation and damage has been
observed. The mid-part of the eastern retaining wall underwent damage in
1987. A part of the wall was pushed out while another part was subjected
to a considerable displacement under the pressure of water and
outflowing wastes from the damaged sewage system. Previously unknown old
galleries were revealed behind the retaining walls collecting rainwater
and leaks from the sewage and water systems and increasing the damage.
Figure 9 presents the actual state and displacements of the eastern
retaining wall.
[FIGURE 9 OMITTED]
In 1999, another part of the retaining structure underwent large
displacements forcing the owner to conduct some remedial work to improve
the water sewage system and construct a chamber to reduce pressure on
the wall. Some main processes of degradation and destruction were
observed in the region of the hermitages located on the lower terraces.
The water sewage system underwent unsealing and cracking, which started
a process of large destruction of the hermitages as shown in Figure 10.
[FIGURE 10 OMITTED]
Cracks and element failure particularly in the lintels, at the
element contacts and edges of openings were noticed in almost all
buildings and structures.
Apart from the presented destruction processes, some other
unfavourable factors have been observed to cause degradation and failure
of all buildings on the Wigry Hill.
These factors include very low degree of compaction and backfilled
character of soil forming the Hill. Others come from water infiltrating
the soil of the Hill and negatively affecting and damping the masonry
walls of all structures.
Incomplete archival building documentation used for the
reconstruction caused faults in the static work of newly reconstructed
building structures laid on older previously existing foundations and
former parts of the structures buried in the ground. In addition, severe
climate of the north eastern part of Poland intensifies the degradation
of buildings and engineering structures with their outer finishes. These
negative effects on the retaining wall are presented in Figure 11.
[FIGURE 11 OMITTED]
3. Pilot analysis and protections
The destructive factors presented above forced the authorities
administering/in charge of the Wigry complex to commence the current
protecting and repair works in parallel with development of an adequate
strategy and concept of revalorization activity concerning the Monastery
complex. Within the framework of repair and protection works, pilot
studies of the retaining walls including their static and strength
analysis have been carried out. Preliminary exposures of both sides of
the wall including their geometry are presented in Figure 12a. The
safety factor of wall stability against overturning is defined as the
ratio between the sum of resisting moments ([M.sub.u]) and the sum of
overturning moments ([M.sub.w]). In evaluating these moments, the
vertical component of the active thrust on the wall may be considered in
two different ways: as decreasing the overturning moment, or increasing
the resisting one. Wall stability against overturning can be assessed
using the position of the resultant force on the base, which is
unaffected by the assumed thrust surface. Contrary to overturning,
safety factors against sliding and bearing capacity are unaffected by
the assumed thrust surface. The overturning moment was computed using
the following equation:
[M.sub.W] = [P.sub.1] x [z.sub.1], (1)
where: [P.sub.1]--active lateral earth pressure resultant acting on
the pressure surface at beck of wall; [z.sub.1]--vertical distance from
the bottom of footing and level of applied horizontal force. The
resisting moment was obtained using the formula below:
[M.sub.u] = [n.summation over (i = 1)] [G.sub.1] x [a.sub.i] +
[P.sub.2] x [z.sub.2], (2)
where: [G.sub.1]--vertical dead loads of the wall;
[a.sub.i]--distances from the vertical loads to the front face of the
wall; [P.sub.2] resultant of the lateral passive pressure acting on the
pressure surface at front of wall; [z.sub.2]--corresponding vertical
distance from the bottom of footing and level of applied horizontal
passive resultant.
It follows from the analysis of loadings shown in Figure 11 that
the retaining wall fails to fulfil the required conditions of the
overturning stability of the structure:
[M.sub.w] = 216.69 x 2.92 = 632.74 [kNm]; (3)
[M.sub.u] = 88.80 x 0.6 + 33.30 x 1.5 + 203.96-1.05 + 8.68 x 0.58 =
322.42 [kNm]; (4)
[M.sub.u] = 322.42 [kNm] < [M.sub.w] = 632.74 [kNm]. (5)
[FIGURE 12 OMITTED]
The massive retaining wall in Figure 12a subjected to increased
horizontal soil pressure and environmental destructions was temporarily
protected using timber bracings and supports, which is shown in Figure
12b.
The unloading structure in the form of a chamber in the upper part
of the wall securing its stability is presented in Figure 12c.
[M.sub.w] = 78.02-1.75 = 136.56 [kNm]; (6)
[M.sub.u] = 409.43 [kNm] > [M.sub.w] = 136.56 [kNm]. (7)
Instead of timber bracing presented in Figure 12b, the stability of
the wall can be protected applying an anchoring system of the wall. The
tieback ground anchor system was considered but the final cost
eliminated this method of wall protection.
Some immediate sources of water and sewage leakage were eliminated.
New concept of elimination of the old leaking sewage septic tanks and
replacing them to the Hill outside is shown in Figure 13.
[FIGURE 13 OMITTED]
Incomplete archival building documentation during the
reconstruction caused some incorrectness in the static work of the newly
reconstructed building structure with the old existing foundations and
the earlier parts of the structures remaining in the ground. Severe
climate of the north eastern part of Poland has also intensified or sped
up the degradation of the buildings and engineering structures with
their outer finishes.
In addition, the earthquake measuring 5.3 on the Richter scale
deteriorated the cracking and failure state of the buildings in 2004,
which was discovered as a result of monitoring the structures.
Supplementary initial investigations of dynamic effects were
analysed and some of the selected results are presented in the form of
displacements in Figure 14 (Malesza, Miedzialowski 2008).
Conclusions
The problems presented in the paper such as excessive settlements,
cracking of structural elements, structural failure and other defects
clearly indicate incorrect former reconstruction and repair works of the
Monastery buildings. The works were undertaken and conducted without
prior investigations of sub-base soil conditions and previously built
structures remaining in the Hill from the earlier stages of
construction.
[FIGURE 13 OMITTED]
[FIGURE 14 OMITTED]
Furthermore, larger than expected deformations of the sub-base due
to its low degree of compaction caused excessive cracking of buildings
as well as destruction of the existing water and sewage system. The
paper underlines how reconstruction decisions based on incomplete
technical data produce undesired effects in the form of accelerated
degradation of structure and buildings including:
--insufficient identification and diagnosis of the technical state
of buildings and soil sub-base conditions before making decisions on
reconstruction;
--improper identification of areas or parts of backfilled ground
soil or covered with rubble from damaged buildings;
--unsatisfactory static and strength analyses of structural
elements;
--leaking water and sewage system;
--use of building materials and technologies for reconstruction,
which are incompatible with the ones used in the historic structures.
Water and sewage system was improvidently planned in the past. The
stability of massive retaining walls was insufficiently accounted for
and, at present, they fail to fulfil the required structural standards.
This necessitates construction of unloading chambers. According to
historic sources, the unloading chambers behind the retaining walls
existed during the Camaldolese time and use of the Monastery. Different
buildings were set in varying soil conditions; i.e. hermitage
foundations were laid partly on backfilled soil and partly on the
retaining walls. As a result, excessive settlement and displacements
caused cracking and failure in structural elements.
Present day technical state of historic Monastery buildings require
more precise and systematic repair and renovation of existing buildings.
Proposed strategy and conception of renovation require the following
steps except to ensure immediate protection:
--Soil deep investigations to identify the stability of the Hill;
--Improvement of the water and sewage system;
--Supplementary inventory of buildings and structures;
--Design and expertise works concerning the stabilization of earth
embankment and repairs of water and sewage system and buildings;
--Professional construction works.
References
Baltazar, L. G.; Henriques, F. M. A.; Jorne, F. 2012. Hydraulic
lime grouts for masonry injection--effects of admixtures on the fresh
grout properties, in The Conference of Structural Analysis of Historic
Constructions (SAHC 2012), 2012, DWE, Wroclaw, Poland, 1763-1770.
Basu, S. 2006. Investigations of historical structures--a study of
rational and irrational forces, in The Conference of Structural Analysis
of Historic Constructions (SAHC 2006), 2006, New Delhi, India,
1487-1494.
Bednarz, L.; Gorski, A.; Jasienko, J. 2011. Simulations and
analyses of arched brick structures, Automation in Construction 20(7):
741-754. http://dx.doi.org/10.1016/j.autcon.2011.01.005
Blasi, C.; Ottoni, F. 2012. The role of structural monitoring in
historical building conservation, in The Conference of Structural
Analysis of Historic Constructions (SAHC 2012), 2012, DWE, Wroclaw,
Poland, 166-182.
Bochen, J.; Labus, M. 2013. Study on physical and chemical
properties of external lime-sand plasters of some historical buildings,
Construction and Building Materials 45: 11-19.
http://dx.doi.org/10.1016/j.conbuildmat.2013.03.086
Camos, C.; Molins, C.; Arnau, O.; Galvec, J. 2012. Numerical
simulation of the structural behaviour of buildings under tunnelling
induced settlements, in The Conference of Structural Analysis of
Historic Constructions (SAHC 2012), 2012, DWE, Wroclaw, Poland, 432-440.
Carpinteri, A.; Lacidogena, G.; Manuello, A.; Binda, L. 2008. The
Ancient Athena Temple in Syracuse (Sicily): an investigation on
structural stability, in RILEM Symposium "On Site Assessment of
Concrete, Masonry and Timber Structures" (SACoMaTiS2008), 2008,
Varenna, Italy, 727-736.
Goeppert, K.; Haspel, L. 2013. National Stadium Warsaw, Poland,
Structural Engineering International 23(3): 311-316.
http://dx.doi.org/10.2749/101686613X13439149157713
Hamid, A. A.; Orphy, M. 2012. Durability of historic brick masonry,
in The Conference of Structural Analysis of Historic Constructions (SAHC
2012), 2012, DWE, Wroclaw, Poland, 1836-1843.
Izquiredo-Encarnacion, J. M. 2012. Codes, policies and earthquakes
as applied to historic preservation projects, in The Conference of
Structural Analysis of Historic Constructions (SAHC 2012), 2012, DWE,
Wroclaw, Poland, 94-104.
Korkanc, M. 2013. Deterioration of different stones used in
historical buildings within Nigde province, Cappadocia, Construction and
Building Materials 48: 789-803.
http://dx.doi.org/10.1016/jxonbuildmat2013.07.033
Lott, G. 2013. Sourcing stone for the conservation and repair of
historical buildings in Britain, Quarterly Journal of Engineering
Geology and Hydrogeology 46(4): 405-420.
http://dx.doi.org/10.1144/qjegh2013-004
Mahmood, G. 2012. Conservation, repair and extension of Imam Reza
Holy Shrine, in The Conference of Structural Analysis of Historic
Constructions (SAHC 2012), 2012, DWE, Wroclaw, Poland, 141-149.
Malesza, M.; Miedzialowski, C. 2008. Monitoring of interaction of
monumental historic complex located on Earth Embankment, in RILEM
Symposium "On Site Assessment of Concrete, Masonry and Timber
Structures" (SACoMaTiS 2008), 2008, Varenna, Italy, 1239-1246.
Malesza, M.; Miedzialowski, Cz. 2006. The modern methods of
analysis in reconstruction of historical buildings, in The Conference of
Structural Analysis of Historic Constructions (SAHC2006), 2006, New
Delhi, India, 1231-1238.
Meli, R.; Sanchez-Ramirez, A. R. 2006. Structural rehabilitation
historical buildings affected by subsidence in Mexico City, in The
Conference of Structural Analysis of Historic Constructions (SAHC 2006),
2006, New Delhi, India, 1503-1510.
Miedzialowski, C.; Malesza, M. 2006. Catalogue of historical and
technical elaborations of Comeldoli Monastery. Bialystok, Poland. 56 p.
Miedzialowski, C.; Malesza, M. 2008. Principles of renovation of
Wigry Hill. Report. Bialystok, Poland. 12 p.
Orduna, A.; Roeder, G.; Arisa, J. C. 2006. Development of
macro-block models for masonry walls subject to lateral loading, in The
Conference of Structural Analysis of Historic Constructions (SAHC 2006),
2006, New Delhi, India, 1075-1082.
Perez Galvez, F.; Rubio de Hita, P.; Ordonez Martin, M. J.; Morales
Conde, M. J.; Rodriguez Linan, C. 2013. Sustainable restoration of
traditional building systems in the historical centre of Sevilla
(Spain), Energy and Buildings 62: 648-659.
http://dx.doi.org/10.1016/j.enbuild.2012.05.009
Pfeifer, M.; Cankurtaran, U. 2013. "New old" calculation
methods on the example of the historical Bergheimer Bath in Heidelberg,
Beton- und Stahlbetonbau 108(8): 570-579.
http://dx.doi.org/10.1002/best.201300043
Quist, W.; Nijland, T.; van Hees, R. P. 2013. Replacement of Eocene
white sandy limestone in historical buildings: over 100 years of
practice in the Netherlands, Quarterly Journal of Engineering Geology
and Hydrogeology 46(4): 431-138. http://dx.doi.org/10.1144/qjegh2013-023
Ramos, L. F.; Lourenco, P. B. 2008. Post-accident damage
investigation based on vibration measurements applied to masonry
structures, in RILEM Symposium "On Site Assessment of Concrete,
Masonry and Timber Structures" (SACoMaTiS2008), 2008, Varenna,
Italy, 453-462.
Ramos, F. L.; de Roeck, G.; Lourenco, P. B.; Campos-Costa, A. 2006.
Vibration based identification of masonry structures, in The Conference
of Structural Analysis of Historic Constructions (SAHC 2006), 2006, New
Delhi, India, 641-650.
Roca, P. 2012. Knowledge--based seismic assessment of architectural
heritage, in The Conference of Structural Analysis of Historic
Constructions (SAHC 2012), 2012, DWE, Wroclaw, Poland, 2906-2913.
Roca, P. 2006. The study and restoration of historical structures:
from principles to practice, in The Conference of Structural Analysis of
Historic Constructions (SAHC 2006), 2006, New Delhi, India, 9-16.
Scherenmans, L.; Van Balen, K. 2006. Hydrostatic levelling system:
monitoring of historical structures, in The Conference of Structural
Analysis of Historic Constructions (SAHC 2006), 2006, New Delhi, India,
529-536.
Silva, R.; Oliveira, D.; Miranda, T. 2013. Rammed earth
construction with granitic residual soils: the case study of northern
Portugal, Construction and Building Materials 47: 181-191.
http://dx.doi.org/10.1016/j.conbuildmat.2013.05.047
Silva, B.; Dalla, B.; da Porto, F. 2014. Compression and sonic
tests to assess effectiveness of grout injection on threeleaf stone
masonry walls, International Journal of Architectural Heritage 8(3):
408-435. http://dx.doi.org/10.1080/15583058.2013.826300
Sliaupa, S. 2013. Modelling of the ground motion of the maximum
probable earthquake and its impact on buildings, Vilnius city, Journal
of Vibroengineering 15(2): 532-543.
Tarque, N.; Lai, C. G.; Bozzoni, F. 2013. Expected ground motion at
the historical site of Poggio Picenze, Central Italy, with reference to
current Italian building code, Engineering Geology 166: 100-115.
http://dx.doi.org/10.1016Zj.enggeo.2013.09.003
Wigry Initial historic documents. 1959. Collective work. Historical
Buildings Preservation Atelier in Bialystok, Poland.
Czeslaw MIEDZIALOWSKI. The Head of the Structural Mechanics at the
Faculty of Civil and Environment Engineering in Bialystok Technical
University. Professor of Structural Mechanics. He has published over 150
outputs at conferences and in periodical journals in Poland and abroad.
Most of his research work focuses on the following topics:
implementation of numerical methods in the structural mechanics,
interaction of soil-building structures, durability of structures in
historical buildings.
Czeslaw MIEDZIALOWSKI (a), Jaroslaw MALESZA (a), Mikolaj MALESZA
(a), Leonas USTINOVICHIUS (b)
(a) Bialystok University of Technology, ul. Wiejska 45a, 15-351
Bialystok, Poland
(b) Vilnius Gediminas Technical University, Sauletekio al. 11,
10223 Vilnius, Lithuania
Received 19 Jun 2013; accepted 21 Jan 2014
Corresponding author: Czeslaw Miedzialowski
E-mail:
[email protected]
Jaroslaw MALESZA. PhD in Bialystok University of Technology,
Faculty of Civil and Environment Engineering. Author of papers on Civil
Engineering Structure published in Poland and abroad. Co-author of the
monograph on Timber Structures. His main research work is focused on the
following topics: structural analyses and investigations of the
reinforced concrete, stiffness, stability and load bearing capacity of
timber structure in civil engineering.
Mikolaj MALESZA. Bialystok University of Technology, Faculty of
Civil and Environmental Engineering. PhD in Civil Engineering. Published
over 85 outputs. Monographic book on Wood-Framed Structures, Timber
Structures and Historic Timber Structures. His research work mainly
focuses on the following topics: structural analyses and investigations
of the reinforced concrete, stiffness, stability and load bearing
capacity of timber structure in civil engineering, durability of
structures in historical buildings and municipal infrastructures.
Leonas USTINOVICHIUS. Prof., Dr Habil, the Chair of the Laboratory
of Construction Technology and Management, Vilnius Gediminas Technical
University. Dr (1989), Dr Habil (2002). Publications: more than 150
scientific papers. Research interests include building technology and
management, decision-making theory, automation in design, expert
systems.
Table 1. Selected horizontal displacements of the northern wall
Marked X mm X mm X mm dx dx
points 9.2007 7.2006 6.2005 7.2006 6.2005
Base points
1011 0.0 0.0 0.0 0.0 0.0
1012 0.0 0.0 0.0 0.0 0.0
400 -0.5 -0.5 0.0 0.0 -0.5
413 0.0 0.0 0.0 0.0 0.0
The ground level
401 589.5 589.5 590.0 0.0 -0.5
402 516.5 516.5 516.5 0.0 0.0
403 533.0 533.5 533.5 -0.5 -0.5
404 536.0 536.5 537.0 -0.5 -1.0
405 563.5 563.0 563.5 0.5 0.0
406 603.5 603.0 603.5 0.5 0.0
407 590.5 590.0 590.5 0.5 0.0
The top of the wall
500 849.0 848.5 849.0 0.5 0.0
501 869.5 870.0 871.0 -0.5 -1.5
502 917.0 916.5 917.5 0.5 -0.5
503 919.0 919.0 920.0 0.0 -1.0
504 921.5 921.5 922.0 0.0 -0.5
505 942.5 942.5 943.0 0.0 -0.5
506 955.5 956.0 957.0 -0.5 -1.5
507 990.0 989.5 990.5 0.5 -0.5
508 1028.5 1028.0 1030.0 0.5 -1.5
1. Minus means wall deflection outside (toward north)