摘要:In this article the rational value of overburden cut width and thickness of transportless overburden at mining of two dispersed flat seams IV-V and VI at Kureinsky section of Sibirginsky open pit mine are presented, which makes it possible to minimize the volume of rock re-excavation under the condition of the planned annual productivity of coal on the open pit and to ensure reduction of stripping costs. This task is complicated by the fact that the dip angle at the section is close to the limit on the condition of the possibility of spoiling of internal dump, and since the overburden rocks of the section are represented mainly by large-block sandstones on the clay cement and siltstones and their compressive strength is 60-80 MPa, then it is required to use a drilling and blasting method of their preparation for excavation. Under such conditions, optimizing the parameters of the transportless excavation scheme is of special importance for effective mining of the section.