期刊名称:Techne : Journal of Technology for Architecture and Environment
电子版ISSN:2239-0243
出版年度:2020
卷号:20
页码:175-183
DOI:10.13128/techne-8056
语种:English
出版社:Firenze University Press
摘要:The construction schedule is the most important construction document as it indicates total project duration, project stages and times of activities, costs, logical sequences, quality and safety. Hence, the quality of a phase schedule presented by a contractor must be assessed by the owner’s consultant either before the commencement of works or during the bidding phase. Only few international standards concerning schedule quality exist, and most of them are not specific for construction. A construction-oriented schedule quality evaluation procedure, based upon a set of 75 requirements has been proposed. Three different versions of a construction schedule for a case study of a seismic rehabilitation project have been evaluated with the aim of performing the proposed method’s proof-of-concept.